ODOT contract 260354 bid tabulation

MAH-US 224-17.72 (PART 1 AND PART 2) (MAJOR RECONSTRUCTION). Let by Ohio DOT on July 30, 2026, MAH. 4 bids received; low bid $14,293,540 by Marucci & Gaffney Excavating Co, +11% against the engineer's estimate of $12,881,000.

Owner
Ohio DOT
Letting
30 JUL 2026
Pay items
240
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Marucci & Gaffney Excavating Co$14,293,540Low+11%
2Karvo Companies Inc$14,804,327+4.0%+15%
3S E T Inc$15,490,000+8.0%+20%
4Shelly & Sands Inc$16,568,986+16%+29%
ODOT contract 260354: bids by rank

Engineer's estimate: $12,881,000.

Bid tabulation

LinePay itemUnitQuantity1. Marucci & Gaffney Excavating Co2. Karvo Companies Inc3. S E T Inc4. Shelly & Sands Inc
1Clearing and grubbing (201E11000)LS1$150,000$25,000$100,000$30,000
2Pavement removed (202E23000)SY11,511$17.00$15.00$28.00$25.00
3Walk removed (202E30000)SF18,493$2.00$2.00$3.50$2.00
4Concrete median removed (202E30600)SY96$18.00$85.00$21.00$30.00
5Traffic island removed (202E30800)SY311$30.00$40.00$26.00$30.00
6Curb removed (202E32000)FT4,832$3.00$25.00$7.00$15.00
7Curb removed, as per plan (202E32001)FT644$10.00$20.00$17.00$5.00
8Curb and gutter removed (202E32500)FT8,902$4.50$20.00$10.00$15.00
9Pipe removed, 24" and under (202E35100)FT562$40.00$50.00$20.00$30.00
10Guardrail removed (202E38000)FT41$6.00$5.00$6.00$5.35
11Catch basin removed (202E58100)EACH22$500.00$1,000.00$750.00$750.00
12Excavation (203E10000)CY9,661$25.00$30.00$40.00$60.00
13Embankment (203E20000)CY2,513$35.00$30.00$25.00$40.00
14Subgrade compaction (204E10000)SY17,028$2.00$1.00$2.00$5.00
15Excavation of subgrade (204E13000)CY1,207$30.00$25.00$30.00$45.00
16Granular material, type B (204E30010)CY1,207$80.00$65.00$80.00$135.00
17Proof rolling (204E45000)HR4$125.00$500.00$250.00$400.00
18Geotextile fabric (204E50000)SY3,623$2.10$2.00$2.00$1.20
19Steel sheet piling left in place, as per plan (504E11101)SF2,713$5.00$10.00$20.00$15.00
20Steel sheet piling left in place, as per plan (504E11101)SF2,713$25.00$28.00$25.00$40.00
21Guardrail, type MGS (606E15050)FT50$70.00$59.00$65.00$63.00
22Anchor assembly, MGS type E (606E26150)EACH1$4,500.00$3,780.00$4,000.00$4,000.00
23Fence, misc.:construction fence (607E98000)FT450$17.00$6.90$6.00$8.00
244" concrete walk (608E10000)SF58,068$13.50$12.00$9.00$10.20
25Curb ramp (608E52000)SF3,472$20.00$20.00$27.00$33.50
26Special - as-built construction plans (690E91000)LS1$10,000$20,000$22,000$25,000
27Special - survey control verification (690E98400)LS1$10,000$15,000$20,000$5,000.00
28Soil analysis test (659E00100)EACH2$10.00$600.00$150.00$25.00
29Topsoil (659E00300)CY1,013$50.00$69.00$80.00$140.00
30Seeding and mulching (659E10000)SY9,060$2.50$1.40$3.00$1.25
31Repair seeding and mulching (659E14000)SY453$1.00$2.00$2.00$1.25
32Inter-seeding (659E15000)SY453$1.00$1.00$1.00$0.25
33Commercial fertilizer (659E20000)TON1.23$750.00$1,500.00$900.00$250.00
34Lime (659E31000)ACRE1.88$275.00$0.05$225.00$25.00
35Water (659E35000)MGAL49$1.00$60.00$10.00$1.00
36Storm water pollution prevention plan (832E15000)LS1$5,000.00$15,000$5,500.00$6,000.00
37Storm water pollution prevention inspections (832E15002)LS1$31,000$30,000$25,000$30,000
38Storm water pollution prevention inspection software (832E15010)LS1$21,000$25,000$32,000$25,000
39Erosion control (832E30000)EACH85,000$1.00$1.00$1.00$1.00
40Removal misc.: inspection well (202E98100)EACH1$10.00$1,000.00$700.00$400.00
41Removal misc.: conduit (202E98200)FT100$20.00$200.00$25.00$15.00
42Tied concrete block mat with type 1 underlayment (601E21050)SY6$175.00$350.00$200.00$320.00
434" unclassified pipe underdrains (605E05200)FT15$40.00$85.00$30.00$30.00
446" base pipe underdrains with geotextile fabric (605E14020)FT15,032$16.00$18.00$20.00$35.00
454" conduit, type F (611E00406)FT30$30.00$50.00$30.00$31.00
466" conduit, type F for underdrain outlets (611E00510)FT719$23.00$25.00$25.00$47.00
476" conduit, type B (611E00900)FT10$60.00$75.00$40.00$150.00
4812" conduit, type B (611E04400)FT1,315$150.00$185.00$120.00$200.00
4912" conduit, type C (611E04600)FT39$200.00$155.00$105.00$170.00
5015" conduit, type B (611E05900)FT389$152.00$155.00$130.00$200.00
5118" conduit, type B (611E07400)FT15$600.00$275.00$210.00$400.00
5224" conduit, type B (611E10400)FT5$825.00$800.00$320.00$600.00
53Conduit, misc.: type B for drainage discharge cont (611E97400)FT100$10.00$5.00$120.00$55.00
54Conduit, misc.: type C for drainage discharge cont (611E97400)FT100$10.00$10.00$105.00$58.00
55Conduit, misc.: type F for drainage discharge cont (611E97400)FT100$10.00$15.00$95.00$42.00
56Catch basin, no. 3 (611E98150)EACH15$5,200.00$5,000.00$4,500.00$7,500.00
57Catch basin, no. 3, as per plan (611E98151)EACH1$5,700.00$5,500.00$5,500.00$8,000.00
58Catch basin, no. 3A (611E98180)EACH23$3,700.00$5,000.00$3,500.00$7,500.00
59Catch basin, no. 2-2B (611E98470)EACH2$3,000.00$3,500.00$3,200.00$6,000.00
60Catch basin adjusted to grade (611E98630)EACH3$1,250.00$1,000.00$1,500.00$1,500.00
61Inlet, no. 2-6 (611E98710)EACH1$12,000$7,500.00$8,500.00$15,000
62Manhole, no. 3 (611E99574)EACH25$7,900.00$7,500.00$5,800.00$8,000.00
63Manhole adjusted to grade (611E99654)EACH14$1,300.00$1,800.00$1,800.00$1,500.00
64Precast reinforced concrete outlet (611E99710)EACH3$550.00$150.00$400.00$700.00
65Inspection well (611E99720)EACH1$100.00$1,000.00$1,200.00$1,500.00
66Special - miscellaneous metal (611E99820)LB400$3.00$2.50$7.00$2.20
67Partial depth pavement repair (441) (251E01000)SY2,000$45.00$25.00$90.00$45.00
68Pavement planing, asphalt concrete, T=1.25" (254E01000)SY80,017$2.50$1.25$2.50$2.30
69Pavement planing, asphalt concrete, T=1.5" (254E01000)SY23,158$3.00$3.00$4.00$3.00
70Asphalt concrete base, PG64-22, (449) (301E56000)CY2,956$310.00$275.00$255.00$300.00
71Asphalt concrete base, PG64-22, (449), (driveways) (301E56100)CY274$310.00$300.00$265.00$300.00
72Aggregate base (304E20000)CY3,073$115.00$100.00$85.00$150.00
73Tack coat (407E10000)GAL113$3.05$3.50$4.00$3.05
74Non-tracking tack coat (407E20000)GAL10,632$3.05$3.50$3.00$3.05
75Fine graded polymer asphalt concrete, type B, (448) (424E14000)CY3,290$272.00$325.00$345.00$270.00
76Asphalt concrete surface course, type 1, (449), (driveways) (441E70500)CY53$700.00$500.00$460.00$700.00
77Asphalt concrete intermediate course, 12.5 MM, type A (448) (442E20170)CY570$322.00$325.00$285.00$322.00
78Asphalt concrete surface course, 12.5 MM, type A (449) (442E22100)CY437$370.00$350.00$375.00$370.00
79Asphalt concrete intermediate course, 12.5 MM, type A (449) (442E22300)CY245$322.00$450.00$365.00$322.00
804" non-reinforced concrete pavement, class QC 1P (452E09010)SY2,331$80.00$60.00$95.00$73.30
828" non-reinforced concrete pavement, class QC MS (452E12050)SY617$128.00$120.00$125.00$147.00
83Combination curb and gutter, type 2 (609E12000)FT7,643$38.00$35.00$40.00$33.50
84Curb, type 4-C (609E24510)FT4,318$25.00$25.00$22.00$24.50
85Curb, type 6 (609E26000)FT6,470$29.00$25.00$24.00$26.50
86Curb, type 7 (609E28000)FT215$50.00$60.00$26.00$67.50
87Special - pavement overlay fabric composite (690E12060)SY2,580$34.00$39.00$36.00$32.75
886" water main polyvinyl chloride pipe and fittings, ASTM SDR 21 (638E00990)FT188$105.00$150.00$175.00$120.00
896" gate valve (638E07480)EACH3$2,500.00$2,000.00$2,200.00$2,000.00
906" gate valve and valve box (638E07800)EACH3$3,000.00$2,200.00$2,800.00$2,300.00
918" X 6" tapping sleeve, valve and valve box (638E09390)EACH3$5,000.00$8,500.00$4,000.00$6,000.00
926" fire hydrant (638E10200)EACH3$7,000.00$7,500.00$7,000.00$12,000
93RPM (621E00100)EACH1,066$40.50$37.50$55.00$45.00
94Ground mounted support, no. 2 post (630E02100)FT183.50$16.00$15.00$16.00$16.00
95Ground mounted support, no. 3 post (630E03100)FT951.80$17.00$15.00$17.00$17.00
96Ground mounted support, no. 3 post, as per plan (630E03101)FT231$18.00$14.25$17.00$17.00
97Sign post reflector (630E08600)EACH12$48.00$40.00$50.00$48.00
98Sign post reflector (630E08600)EACH66$48.00$40.00$50.00$48.00
99Sign post reflector (630E08600)EACH4$48.00$40.00$50.00$48.00
100Overhead sign support, type TC-15.116, design 1 (630E72410)EACH1$80,000$79,450$80,000$81,000
101Overhead sign support, type TC-16.22, design 12 (630E72540)EACH2$20,000$19,750$21,000$21,000
102Overhead sign support, type TC-16.22, design 13 (630E72550)EACH8$27,000$26,950$28,000$28,000
103Overhead sign support, type TC-16.22, design 14 (630E72560)EACH3$28,500$28,200$30,000$30,000
104Span wire sign support, type TC-17.11, design 8 (630E76520)EACH1$23,000$22,450$24,000$24,000
105Sign hanger assembly, span wire (630E79000)EACH10$500.00$400.00$515.00$530.00
106Sign hanger assembly, mast arm (630E79100)EACH110$580.00$500.00$575.00$590.00
107Sign support assembly, pole mounted (630E79500)EACH14$260.00$125.00$250.00$260.00
108Sign, flat sheet (630E80100)SF1,591.20$21.00$27.50$22.00$21.00
109Sign, overhead extrusheet (630E80224)SF64$30.00$112.39$30.00$31.00
110Rigid overhead sign support foundation (630E84510)EACH15$9,000.00$8,820.00$9,200.00$9,400.00
111Span wire sign support foundation (630E84520)EACH2$6,500.00$6,420.00$6,700.00$6,800.00
112Removal of ground mounted sign and disposal (630E84900)EACH82$16.00$15.00$16.00$16.00
113Removal of ground mounted sign and reerection (630E85100)EACH32$75.00$125.00$75.00$75.00
114Removal of ground mounted post support and disposal (630E86002)EACH75$21.00$15.00$25.00$21.00
115Removal of overhead mounted sign and disposal (630E87400)EACH58$100.00$150.00$100.00$100.00
116Removal of pole mounted sign and disposal (630E87500)EACH15$47.00$25.00$50.00$48.00
117Removal of overhead sign support and disposal (630E89702)EACH16$2,600.00$2,530.00$2,700.00$2,700.00
118Signing, misc.:, 12" PVC pipe (630E97700)EACH22$100.00$50.00$55.00$377.00
119Edge line, 6" (646E10010)MI1.28$3,768.00$3,768.00$4,000.00$4,000.00
120Lane line, 6" (646E10110)MI7.05$2,250.00$2,250.00$2,400.00$2,400.00
121Center line (646E10200)MI3.20$4,628.00$4,628.00$5,000.00$4,900.00
122Channelizing line, 12" (646E10310)FT12,571$1.45$1.45$1.50$1.50
123Stop line (646E10400)FT1,190$13.00$13.00$14.00$14.00
124Crosswalk line, 24" (646E10520)FT1,715$13.00$13.00$14.00$14.00
125Transverse/diagonal line (646E10600)FT2,555$10.00$10.00$11.00$11.00
126Island marking (646E10800)SF114$9.00$9.00$10.00$9.00
127Railroad symbol marking (646E20000)EACH6$60.00$600.00$650.00$640.00
128Lane arrow (646E20300)EACH152$150.00$150.00$175.00$160.00
129Dotted line, 6" (646E20504)FT3,085$1.50$1.50$1.75$1.60
130Pavement marking, misc.: U-turn lane arrow (646E98000)EACH8$300.00$300.00$325.00$320.00
131Bracket arm, 15' (625E18200)EACH17$1,428.36$1,350.00$1,000.00$1,440.00
132No. 10 AWG pole and bracket cable (625E23400)FT765$1.85$1.75$3.25$1.90
133Conduit, 2", 725.04 (625E25400)FT24$21.16$20.00$40.00$22.00
134Conduit, 3", 725.04 (625E25500)FT961$37.03$35.00$40.00$37.00
135Conduit, 4", 725.04 (625E25600)FT46$47.61$45.00$65.00$52.00
136Conduit, jacked or drilled, 725.04, 4" (625E25902)FT2,065$79.35$75.00$85.00$78.00
137Luminaire, conventional, solid state (LED), 7000- (625E26252)EACH17$634.83$600.00$650.00$590.00
138Trench (625E29000)FT916$10.58$10.00$20.00$13.00
139Pull box, 725.08, 18" (625E30700)EACH20$1,269.65$1,200.00$950.00$1,400.00
140Pull box, 725.08, 24" (625E30706)EACH14$1,587.06$1,500.00$1,100.00$1,600.00
141Ground rod (625E32000)EACH61$211.61$200.00$250.00$306.00
142Underground warning/marking tape, as per plan (625E36011)FT1,002$0.53$0.50$1.00$0.50
143Vehicular signal head, optically programmed, 3 section, 12" lens, 1-way (632E03200)EACH3$6,877.27$6,500.00$7,800.00$5,400.00
144Vehicular signal head, optically programmed, 5 section, 12" lens, 1-way (632E03204)EACH1$11,638$11,000$13,500$7,200.00
145Vehicular signal head, (LED), 3-section, 12" lens, 1-way, polycarbonate (632E05006)EACH75$1,110.94$1,050.00$1,250.00$1,300.00
146Vehicular signal head, (LED), 5-section, 12" lens, 1-way, polycarbonate (632E05086)EACH22$1,692.87$1,600.00$2,000.00$2,100.00
147Pedestrian signal head (LED), type D2, countdown, as per plan (632E20731)EACH32$687.73$650.00$550.00$790.00
148Covering of vehicular signal head (632E25000)EACH101$10.58$10.00$60.00$50.00
149Covering of pedestrian signal head (632E25010)EACH32$10.58$10.00$45.00$48.00
150Pedestrian pushbutton, as per plan (632E26001)EACH32$317.41$300.00$275.00$310.00
151Signal cable, 5 conductor, no. 14 AWG (632E40500)FT11,510$3.70$3.50$2.75$3.50
152Signal cable, 7 conductor, no. 14 AWG (632E40700)FT13,218$4.23$4.00$3.25$4.00
153Signal support foundation, as per plan (632E64011)EACH29$8,993.36$8,500.00$8,500.00$9,200.00
154Pedestal foundation (632E64020)EACH20$1,587.06$1,500.00$1,100.00$1,600.00
155Test hole performed (632E64950)EACH29$1,058.04$1,000.00$300.00$1,400.00
156Power cable, 2 conductor, no. 6 AWG (632E68200)FT35$6.35$6.00$10.00$7.00
157Service cable, 2 conductor, no. 4 AWG (632E69600)FT17$6.35$6.00$20.00$9.00
158Power service, as per plan (632E70001)EACH7$3,174.13$3,000.00$3,700.00$4,100.00
159Signal support, type TC-81.22, design 4 (632E72110)EACH1$12,697$12,000$16,000$13,000
160Signal support, type TC-81.22, design 12 (632E72130)EACH1$15,342$14,500$20,000$15,000
161Signal support, type TC-81.22, design 13 (632E72140)EACH6$18,093$17,100$23,000$24,000
162Signal support, type TC-81.22, design 14 (632E72150)EACH3$20,103$19,000$26,000$25,000
163Combination signal support, type TC-81.22, design 4 (632E79110)EACH7$13,755$13,000$16,000$13,000
164Combination signal support, type TC-81.22, design 12 (632E79130)EACH1$16,400$15,500$21,000$16,000
165Combination signal support, type TC-81.22, design 13 (632E79140)EACH5$20,367$19,250$25,000$21,000
166Combination signal support, type TC-81.22, design 14 (632E79150)EACH4$21,690$20,500$27,000$23,000
167Pedestal, 10.7' tall, transformer base (632E89920)EACH19$2,645.10$2,500.00$1,800.00$3,400.00
168Pedestal, 14.4' tall, transformer base (632E89930)EACH1$2,750.91$2,600.00$2,000.00$4,500.00
169Removal of traffic signal installation, as per plan (632E90101)EACH8$5,290.21$5,000.00$5,000.00$3,200.00
170Cabinet, type TS-2, as per plan (633E65511)EACH7$17,987$17,000$21,000$21,000
171Cabinet foundation, as per plan (633E67101)EACH7$2,645.10$2,500.00$2,600.00$3,200.00
172Controller work pad, as per plan (633E67201)EACH7$1,587.06$1,500.00$525.00$4,200.00
173Uninterruptible power supply (UPS), 1000 watt, as per plan (633E75001)EACH7$6,877.27$6,500.00$7,300.00$7,500.00
174Special -railroad blankout cable, 7 conductor, no. (690E98100)FT278$4.23$4.00$4.00$13.00
175Special -railroad preempt cable, conductor, no. 14 (690E98100)FT117$4.23$4.00$3.00$15.00
176ITS device, misc.: reuse communications device (809E65990)EACH6$1,058.04$1,000.00$950.00$4,000.00
177Advance radar detection, as per plan (809E69001)EACH20$10,580$10,000$12,000$7,000.00
178Stop line radar detection, as per plan (809E69101)EACH28$10,051$9,500.00$11,000$7,400.00
179Atc controller, as per plan (809E69123)EACH7$529.02$500.00$950.00$4,800.00
180Railroad preemption interface, as per plan, US 224 (819E10001)EACH1$10,580$10,000$12,000$13,000
181Law enforcement officer with patrol car for assistance (614E11110)HR240$85.00$150.00$100.00$101.00
182Special - work zone traffic signal (614E11300)EACH3$16,000$15,000$4,500.00$16,000
183Detour signing (614E12420)LS1$20,000$25,000$22,000$21,000
184Portable changeable message sign (614E18600)SNMT96$850.00$1,000.00$900.00$1,200.00
185Work zone lane line, class I, 6" (614E20010)MI10.22$700.00$700.00$725.00$750.00
186Work zone lane line, class III, 6", 642 paint (614E20560)MI7.03$650.00$650.00$700.00$700.00
187Work zone center line, class I (614E21000)MI7.84$1,250.00$1,250.00$1,300.00$1,300.00
188Work zone center line, class III, 642 paint (614E21550)MI3.18$1,175.00$1,175.00$1,250.00$1,250.00
189Work zone edge line, class I, 6" (614E22010)MI5.78$800.00$800.00$850.00$850.00
190Work zone edge line, class III, 6", 642 paint (614E22360)MI1.25$700.00$700.00$750.00$750.00
191Work zone channelizing line, class I, 8" (614E23000)FT21,476$0.70$0.70$1.00$0.70
192Work zone channelizing line, class III, 8", 642 paint (614E23680)FT12,570$0.66$0.66$1.00$0.70
193Work zone dotted line, class I (614E24000)FT4,268$0.88$0.88$1.00$0.90
194Work zone transverse/diagonal line, class I (614E25000)FT4,718$2.00$2.00$2.50$2.00
195Work zone stop line, class I (614E26000)FT2,379$3.00$3.00$3.00$3.00
196Work zone stop line, class III, 642 paint (614E26610)FT1,207$3.00$3.00$3.00$3.00
197Work zone crosswalk line, class I, 12" (614E27010)FT1,625$1.75$1.75$2.00$1.80
198Work zone arrow, class I (614E30000)EACH95$55.00$55.00$60.00$59.00
199Water (616E10000)MGAL5$1.00$128.90$150.00$195.00
200Longitudinal channelizing device, as per plan (831E00101)FT3,380$85.00$115.00$88.00$90.00
201Longitudinal channelizing device, as per plan (831E00101)FT1,892$85.00$115.00$88.00$90.00
202Pavement removed, as per plan (202E23001)SY1,196$19.00$20.00$28.00$30.00
203Walk removed (202E30000)SF80$5.00$10.00$20.00$35.00
204Excavation (203E10000)CY25$40.00$35.00$50.00$90.00
205Granular material, type B (203E35110)CY25$70.00$125.00$100.00$170.00
206Subgrade compaction (204E10000)SY1,196$2.00$1.00$3.00$13.00
207Geotextile fabric (204E50000)SY75$7.00$5.00$6.00$1.00
208Temporary asphalt concrete walk (608E21200)SF80$25.00$5.00$20.00$80.00
209Special - as-built construction plans (690E20010)LS1$7,500.00$20,000$5,500.00$5,000.00
210Erosion control (832E30000)EACH14,545$1.00$1.00$1.00$1.00
211Asphalt concrete base, PG64-22, (449) (301E56000)CY301$320.00$300.00$295.00$300.00
212Aggregate base (304E20000)CY212$115.00$175.00$90.00$200.00
213Non-tracking tack coat (407E20000)GAL183$3.05$3.50$4.00$3.05
214Asphalt concrete intermediate course, 12.5 MM, type A (449) (442E22300)CY119$325.00$335.00$310.00$322.00
215Pipe removed, 24" and under (202E35100)FT5$100.00$165.00$340.00$250.00
216Special - fill and plug existing conduit (202E70000)FT3,017$12.00$4.00$22.00$15.00
217Abandon misc.: water valve box (202E98600)EACH9$100.00$200.00$800.00$900.00
218Special - 8" water main dip class 52 push on joints and fittings (638E20086)FT2,075$200.00$150.00$160.00$250.00
219Special - 8" gate valve with valve box, city of YO (638E20554)EACH7$4,500.00$2,000.00$3,500.00$2,500.00
220Special - 8" inserting valve with valve box, city (638E20558)EACH3$15,000$12,000$18,000$12,000
221Special - 8" X 8" tapping sleeve, valve and valve box (638E20694)EACH1$9,500.00$8,500.00$9,000.00$6,000.00
222Special - 6" fire hydrant, city of youngstown (638E20750)EACH5$12,000$11,000$13,000$18,000
223Special - fire hydrant removed and disposed of, CI (638E20760)EACH4$500.00$1,000.00$1,800.00$1,600.00
224Special - retap and reconnect water service connection (638E20786)FT309$85.00$125.00$90.00$140.00
225Water work, misc.: 6" class 52 dip service branch, (638E98600)FT14$600.00$575.00$400.00$650.00
226Water work, misc.: 6" fire suppression line, compl (638E98600)FT42$450.00$600.00$350.00$450.00
227Water work, misc.: 8" class 52 dip service BR (638E98600)FT19$700.00$1,000.00$425.00$650.00
228Water work, misc.: 8" fire suppression line, (638E98600)FT198$460.00$250.00$360.00$500.00
229Premium on railroads' protective public liability and property damage liability insurance (100E00300)LS1$16,000$25,000$3,500.00$10,000
230Premium for contract performance bond and for payment bond (103E05000)LS1$70,000$100,000$100,000$100,000
231CPM progress schedule (108E10000)LS1$25,000$75,000$7,500.00$15,000
232Maintaining traffic (614E11000)LS1$863,000$1,250,000$2,005,534$1,265,000
233Field office, type C, as per plan (619E16021)MNTH24$3,500.00$4,000.00$6,500.00$7,000.00
234Construction layout stakes and surveying (623E10000)LS1$240,000$250,000$200,000$350,000
235Mobilization (624E10000)LS1$700,000$750,000$400,000$828,000
3008" conduit, type B (611E01800)FT10$275.00$300.00$120.00$170.00
301Special - cut and plug existing 8" water lineend C (638E20880)EACH2$2,500.00$1,250.00$1,500.00$2,300.00
302Asphalt concrete intermediate course, 12.5 MM, type A (448) (442E20170)CY317$322.00$350.00$285.00$322.00
303Asphalt concrete intermediate course, 12.5 MM, type A (448) (442E20170)CY69$322.00$425.00$360.00$322.00
304Special - fill and plug existing conduit (202E70000)FT15$100.00$100.00$100.00$60.00
305Removal misc.:trench drain removed (202E98200)FT14$100.00$125.00$150.00$60.00
ODOT contract 260354: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of July 30, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy