ODOT contract 260364 bid tabulation

KNO-SR 13-10.33 (MINOR RECONSTRUCTION). Let by Ohio DOT on August 13, 2026, KNO. 4 bids received; low bid $6,766,844 by Complete General Construction Company, +10% against the engineer's estimate of $6,148,000.

Owner
Ohio DOT
Letting
13 AUG 2026
Pay items
235
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Complete General Construction Company$6,766,844Low+10%
2Shelly & Sands Inc$6,851,809+1.0%+11%
3Trucco Construction Co Inc$7,605,844+12%+24%
4Ruhlin Company$7,651,536+13%+24%
ODOT contract 260364: bids by rank

Engineer's estimate: $6,148,000.

Bid tabulation

LinePay itemUnitQuantity1. Complete General Construction Company2. Shelly & Sands Inc3. Trucco Construction Co Inc4. Ruhlin Company
1Clearing and grubbing (201E11000)LS1$20,000$32,500$4,000.00$80,550
2Pavement removed, as per plan (202E23001)SY20,325$15.00$12.25$12.00$22.50
3Walk removed (202E30000)SF12,921$4.00$0.75$1.50$3.00
4Curb removed (202E32000)FT2,794$8.00$5.00$6.00$9.75
5Curb and gutter removed (202E32500)FT755$20.00$7.00$8.00$11.50
6Pipe removed, 24" and under (202E35100)FT1,033$37.00$30.00$31.00$19.50
7Guardrail removed (202E38000)FT100$12.40$17.00$15.00$2.00
8Manhole removed (202E58000)EACH5$1,050.00$1,800.00$1,500.00$750.00
9Catch basin removed (202E58100)EACH19$500.00$1,900.00$1,000.00$850.00
10Removal misc.: bench removed (202E98100)EACH1$950.00$425.00$500.00$850.00
11Removal misc.: bollard removed (202E98100)EACH14$195.00$90.00$175.00$800.00
12Removal misc.: ohio historical marker removed and (202E98100)EACH1$2,800.00$1,600.00$1,600.00$25,000
13Removal misc.: trash receptacle removed (202E98100)EACH2$230.00$440.00$200.00$800.00
14Removal misc.: water service box removed (202E98100)EACH2$230.00$800.00$350.00$800.00
15Excavation (203E10000)CY13,054$20.00$32.00$32.00$34.00
16Embankment (203E20000)CY560$10.00$22.00$45.00$28.00
17Subgrade compaction (204E10000)SY3,711$4.00$7.25$6.00$5.50
18Excavation of subgrade (204E13000)CY547$66.00$50.00$52.00$39.00
19Embankment (204E20000)CY397$25.00$15.00$19.00$10.00
20Granular material, type B (204E30010)CY150$105.00$96.00$80.00$88.00
21Proof rolling (204E45000)HR5$380.00$288.00$385.00$510.00
22Geotextile fabric (204E50000)SY300$5.00$1.50$3.50$2.50
23Geogrid (204E51000)SY300$8.00$1.80$7.00$3.00
24Cement (206E10500)TON276$235.00$235.00$242.00$212.00
25Curing coat (206E11000)SY9,127$1.49$1.50$1.20$1.20
26Cement stabilized subgrade, 14 inches deep (206E15020)SY9,127$8.49$6.62$10.25$11.56
27Mixture design for chemically stabilized soils (206E30000)LS1$9,941.43$9,941.00$9,940.00$6,000.00
284" concrete walk, as per plan (608E10001)SF35,649$12.00$10.00$11.00$13.50
29Concrete steps, type B (608E41000)FT8$450.00$365.00$450.00$110.00
30Curb ramp, as per plan (608E52001)SF5,412$19.00$24.00$22.00$17.00
31Monument assembly, type C (623E38500)EACH10$1,215.00$2,300.00$2,100.00$1,100.00
32Right-of-way monument, type B (623E40520)EACH11$850.00$200.00$450.00$850.00
33Special - concrete parking block (690E50500)EACH27$250.00$466.00$300.00$400.00
34Special - bollard (690E50600)EACH3$840.00$1,000.00$1,000.00$1,500.00
35Rock channel protection, type C with filter (601E32200)CY3$280.00$650.00$250.00$600.00
36Topsoil (659E00300)CY1,711$51.00$68.00$80.00$40.00
37Seeding and mulching, class 1 (659E00500)SY13,100$0.75$0.75$0.75$1.40
38Seeding and mulching, class 5B (659E00580)SY2,315$2.23$2.25$2.23$2.00
39Repair seeding and mulching (659E14000)SY771$0.80$0.80$0.80$1.00
40Commercial fertilizer (659E20000)TON2.08$763.51$765.00$763.51$1,250.00
41Water (659E35000)MGAL83$1.00$1.00$1.00$1.00
42Erosion control mat (671E14000)SY2,000$1.49$1.50$1.49$2.00
43Storm water pollution prevention plan (832E15000)LS1$3,500.00$4,500.00$4,500.00$3,500.00
44Storm water pollution prevention inspections (832E15002)LS1$22,800$16,050$17,150$45,600
45Storm water pollution prevention inspection software (832E15010)LS1$18,400$18,400$27,061$18,330
46Erosion control (832E30000)EACH75,000$1.00$1.00$1.00$1.00
47Concrete masonry (602E20000)CY0.80$3,538.00$5,300.00$6,000.00$5,500.00
484" unclassified pipe underdrains (605E05200)FT345$30.00$20.00$27.00$40.00
494" base pipe underdrains (605E06000)FT4,889$15.00$15.00$9.50$21.00
504" conduit, type F for underdrain outlet (611E00410)FT491$22.00$31.00$29.00$125.00
5112" conduit, type B (611E04400)FT1,075$175.00$115.00$138.00$137.00
5215" conduit, type B (611E05900)FT436$178.00$125.00$165.00$194.00
5315" conduit, type C (611E06100)FT4$340.00$475.00$537.00$880.00
5418" conduit, type B (611E07400)FT264$214.00$150.00$170.00$242.00
5524" conduit, type B (611E10400)FT112$267.00$180.00$239.00$256.00
5624" conduit, type C (611E10600)FT369$155.00$140.00$136.00$145.00
5730" conduit, type B (611E13400)FT4$530.00$900.00$1,052.00$1,600.00
58Catch basin, no. 3 (611E98150)EACH20$5,400.00$5,300.00$8,500.00$6,400.00
59Catch basin, no. 3A (611E98180)EACH10$4,500.00$4,450.00$6,100.00$5,600.00
60Catch basin, no. 2-2B (611E98470)EACH1$3,400.00$3,800.00$4,300.00$4,100.00
61Catch basin adjusted to grade, as per plan (611E98631)EACH1$2,800.00$2,850.00$1,950.00$1,600.00
62Manhole, no. 3 (611E99574)EACH4$4,700.00$4,700.00$6,700.00$10,000
63Manhole, no. 3, as per plan (611E99575)EACH12$6,400.00$7,000.00$8,100.00$11,500
64Manhole, no. 3 with 96" base I.D. and 9" weir (611E99584)EACH1$20,000$18,000$24,000$18,500
65Manhole adjusted to grade (611E99654)EACH1$1,400.00$1,300.00$900.00$1,600.00
66Manhole adjusted to grade, as per plan (611E99655)EACH1$2,900.00$2,800.00$11,000$1,606.00
67Manufactured water quality structure, type 3 (895E10030)EACH1$26,000$45,000$37,500$40,000
68Pavement planing, asphalt concrete, (1.25" depth) (254E01000)SY1,155$12.00$7.00$10.00$10.00
69Asphalt concrete base, PG64-22, (449) (301E56000)CY1,526$218.00$230.00$180.00$180.00
70Aggregate base (304E20000)CY2,201$99.00$85.00$91.00$110.00
71Non-tracking tack coat (407E20000)GAL1,319$4.50$3.50$2.75$2.75
72Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000)CY146$284.00$350.00$314.00$300.00
73Asphalt concrete surface course, type 1, (449), PG70-22M (441E70100)CY276$269.00$285.00$322.00$308.00
74Asphalt concrete intermediate course, type 2, (449) (441E70300)CY534$247.00$225.00$230.00$230.00
75Asphalt concrete surface course, type 1, (449), (driveways) (441E70500)CY9$730.00$650.00$764.00$750.00
76Asphalt concrete intermediate course, type 2, (449), (driveways) (441E70700)CY11$600.00$550.00$700.00$700.00
774" non-reinforced concrete pavement, class QC 1P (452E09010)SY27$143.00$150.00$75.00$150.00
786" non-reinforced concrete pavement, class QC MS (452E10050)SY36$125.00$130.00$102.00$160.00
798" non-reinforced concrete pavement, class QC MS (452E12050)SY378$145.00$130.00$110.00$170.00
80Combination curb and gutter, type 2 (609E12000)FT4,366$37.00$35.00$41.50$50.00
81Curb, type 6 (609E26000)FT1,841$30.00$29.00$49.25$40.00
821-1/2" copper service branch (638E05000)FT141$94.00$135.00$106.00$90.00
836" cutting-in sleeve (638E08704)EACH1$8,600.00$6,400.00$4,200.00$6,000.00
8412" cutting-in sleeve (638E08710)EACH1$8,700.00$9,300.00$6,100.00$6,500.00
85Fire hydrant extended and adjusted to grade (638E10300)EACH2$3,200.00$2,900.00$3,700.00$2,800.00
86Valve box adjusted to grade (638E10800)EACH4$650.00$650.00$450.00$1,975.00
87Valve box adjusted to grade, as per plan (638E10801)EACH4$650.00$1,400.00$1,400.00$1,975.00
88Service box adjusted to grade (638E10900)EACH1$625.00$550.00$375.00$2,305.00
89Water work, misc.: 12" existing water main lowerin (638E98000)EACH2$16,000$16,000$24,000$10,000
90Water work, misc.: 12"X8" cut-in anchor tee, valve (638E98000)EACH1$14,000$8,000.00$10,000$7,000.00
91Water work, misc.: 6" existing water main lowering (638E98000)EACH5$11,000$9,300.00$14,000$4,500.00
92Water work, misc.: 6" fire hydrant (mount vernon) (638E98000)EACH1$16,000$6,100.00$8,000.00$8,000.00
93Water work, misc.: 6" gate valve and valve box (MO (638E98000)EACH2$3,000.00$1,770.00$2,700.00$4,000.00
94Water work, misc.: 8" gate valve and valve box (MO (638E98000)EACH1$3,800.00$2,500.00$3,900.00$6,200.00
95Water work, misc.: abandon existing 1 1/4" water L (638E98000)EACH1$1,600.00$1,000.00$300.00$650.00
96Water work, misc.: abandon existing 6" water line (638E98000)EACH1$1,600.00$2,200.00$1,600.00$3,000.00
97Water work, misc.:1 1/2" water line transfer (638E98000)EACH1$8,500.00$2,700.00$1,200.00$3,100.00
98Water work, misc.:12" water main, ductile iron pip (638E98600)FT10$840.00$370.00$750.00$615.00
99Water work, misc.:6" water main, ductile iron pipe (638E98600)FT45$350.00$270.00$250.00$375.00
100Water work, misc.:8" water main, ductile iron pipe (638E98600)FT381$260.00$135.00$230.00$240.00
1016" conduit, type B (611E00900)FT8$240.00$327.00$225.00$1,800.00
10212" conduit, type B (611E04400)FT169$230.00$150.00$286.00$230.00
10324" conduit, type B (611E10400)FT301$300.00$230.00$395.00$306.00
104Manhole, no. 3, as per plan (611E99575)EACH3$14,000$9,200.00$10,900$8,100.00
105Manhole adjusted to grade (611E99654)EACH3$1,500.00$1,600.00$900.00$1,500.00
106Manhole adjusted to grade, as per plan (611E99655)EACH1$1,600.00$4,000.00$2,000.00$2,000.00
107Manhole reconstructed to grade (611E99660)EACH1$1,900.00$3,500.00$4,000.00$2,600.00
108Manhole reconstructed to grade, as per plan (611E99661)EACH1$2,100.00$6,000.00$5,000.00$2,600.00
109Low strength mortar backfill (613E41200)CY100$200.00$130.00$325.00$184.00
110Special - 8" sanitary lateral, complete (690E98000)EACH2$13,000$15,400$15,100$15,000
111Special - bypass pumping and piping (690E98400)LS1$40,000$125,000$235,000$42,000
112Connection, fused pull apart (625E00450)EACH8$175.00$175.00$175.00$195.00
113Connection, unfused pull apart (625E00460)EACH8$170.00$170.00$170.00$195.00
114Light pole foundation, 24" X 6' deep, as per plan (625E14001)EACH4$2,500.00$2,500.00$2,500.00$1,575.00
115No. 4 AWG 600 volt distribution cable (625E23000)FT931$4.50$4.50$4.50$4.00
116No. 8 AWG 600 volt distribution cable (625E23304)FT1,052$4.00$4.00$4.00$3.50
117No. 10 AWG pole and bracket cable (625E23400)FT310$4.00$4.00$4.00$2.48
118Conduit, 1-1/2", 725.051 (625E25304)FT323$6.50$6.50$6.50$6.50
119Trench (625E29000)FT323$10.00$10.00$10.00$10.00
120Pull box removed (625E31510)EACH3$300.00$300.00$300.00$275.00
121Pull box, misc.: 12" X 12" (625E31600)EACH3$750.00$750.00$750.00$1,265.00
122Ground rod (625E32000)EACH4$275.00$275.00$275.00$275.00
123Underground warning marking tape (625E36010)FT323$2.00$2.00$2.00$1.00
124Special - maintain existing lighting (625E40000)LS1$1,500.00$1,500.00$1,500.00$1.00
125Light pole foundation removed (625E75500)EACH4$350.00$350.00$350.00$250.00
126Lighting, misc.: remove and reerect existing light (625E98000)EACH4$1,500.00$1,500.00$1,500.00$850.00
127Lighting, misc.: remove and reerect gfci electrica (625E98000)EACH2$500.00$500.00$500.00$550.00
128Ground mounted support, no. 2 post (630E02100)FT339.10$16.00$20.00$20.00$20.00
129Ground mounted support, no. 3 post (630E03100)FT275.60$18.00$21.00$21.00$21.00
130Ground mounted support, no. 4 post, as per plan (630E04101)FT43.20$24.00$28.00$28.00$28.00
131Street name sign support, no. 2 post (630E08510)FT25.20$22.00$20.00$20.00$20.00
132Sign post reflector (630E08600)EACH6$45.00$50.00$50.00$50.00
133Sign hanger assembly, mast arm, as per plan (630E79101)EACH20$685.00$1,100.00$1,100.00$1,100.00
134Sign support assembly, pole mounted (630E79500)EACH48$220.00$150.00$150.00$150.00
135Sign, flat sheet (630E80100)SF568.20$22.00$25.00$25.00$25.00
136Sign, flat sheet, as per plan (630E80101)SF119.60$22.50$32.00$32.00$32.00
137Removal of ground mounted sign and disposal (630E84900)EACH60$10.00$25.00$25.00$25.00
138Removal of ground mounted post support and disposal (630E86002)EACH37$18.00$25.00$25.00$25.00
139Removal of overhead mounted sign and disposal (630E87400)EACH32$90.00$215.00$215.00$215.00
140Removal of pole mounted sign and disposal (630E87500)EACH94$45.00$35.00$35.00$35.00
141Removal of pole mounted sign and reerection (630E87520)EACH7$265.00$175.00$175.00$175.00
142Signing, misc.: historic disrict archway (630E97700)EACH1$250,000$170,000$180,000$170,000
143Edge line, 4" (644E00100)MI0.25$6,165.00$6,165.00$6,165.00$6,165.00
144Lane line, 4" (644E00200)MI0.09$2,590.00$2,590.00$2,590.00$2,590.00
145Center line (644E00300)MI0.39$10,300$10,300$10,300$10,300
146Channelizing line, 8" (644E00400)FT793$2.90$2.90$2.90$2.90
147Stop line (644E00500)FT268$9.00$9.00$9.00$9.00
148Crosswalk line, 24", as per plan (644E00631)FT1,070$9.00$9.00$9.00$9.00
149Transverse/diagonal line (644E00700)FT348$9.00$9.00$9.00$9.00
150Island marking (644E00900)SF114$3.00$3.00$3.00$3.00
151Parking lot stall marking (644E01200)FT10$3.00$3.00$3.00$3.00
152Lane arrow (644E01300)EACH17$110.00$110.00$110.00$110.00
153Dotted line, 4" (644E01500)FT158$2.00$2.00$2.00$2.00
154Yield line (644E20800)FT11$15.50$15.50$15.50$15.50
155Conduit, 2", 725.04 (625E25400)FT511$25.00$25.00$25.00$27.50
156Conduit, 3", 725.04 (625E25500)FT138$40.00$40.00$40.00$52.00
157Conduit, 4", 725.04 (625E25600)FT707$50.00$50.00$50.00$60.00
158Trench (625E29000)FT1,086$20.00$20.00$20.00$10.00
159Pull box, 725.08, 18" (625E30700)EACH5$1,100.00$1,100.00$1,100.00$1,340.00
160Pull box, 725.08, 24" (625E30706)EACH6$1,500.00$1,500.00$1,500.00$1,462.00
161Ground rod (625E32000)EACH28$300.00$300.00$300.00$275.00
162Underground warning marking tape (625E36010)FT1,086$1.75$1.75$1.75$1.00
163Arc flash calculations and label, traffic signal C (625E76000)EACH3$3,500.00$3,500.00$3,500.00$1,200.00
164Vehicular signal head, (LED), 3-section, 12" lens, 1-way, polycarbonate (632E05006)EACH18$1,150.00$1,150.00$1,150.00$1,100.00
165Vehicular signal head, (LED), 5-section, 12" lens, 1-way, polycarbonate (632E05086)EACH4$1,850.00$1,850.00$1,850.00$1,800.00
166Pedestrian signal head (LED), type D2, countdown, as per plan (632E20731)EACH20$660.00$660.00$660.00$725.00
167Accessible pedestrian pushbutton, as per plan (632E20751)EACH20$740.00$740.00$740.00$715.00
168Covering of vehicular signal head (632E25000)EACH22$40.00$40.00$40.00$75.00
169Covering of pedestrian signal head (632E25010)EACH20$35.00$35.00$35.00$75.00
170Signal cable, 5 conductor, no. 14 AWG (632E40500)FT2,626$3.25$3.25$3.25$3.60
171Signal cable, 7 conductor, no. 14 AWG (632E40700)FT2,324$4.00$4.00$4.00$4.30
172Signal support foundation, as per plan (632E64011)EACH10$9,500.00$9,500.00$9,500.00$7,000.00
173Pedestal foundation (632E64020)EACH12$2,500.00$2,500.00$2,500.00$900.00
174Test hole performed (632E64950)EACH3$2,500.00$2,500.00$2,500.00$700.00
175Loop detector lead-in cable (632E65200)FT2,546$2.50$2.50$2.50$2.10
176Power cable, 2 conductor, no. 4 AWG (632E69200)FT506$6.50$6.50$6.50$7.00
177Power service, as per plan (632E70001)EACH3$2,500.00$2,500.00$2,500.00$2,495.00
178Conduit riser, 2" diameter (632E70400)EACH2$1,500.00$1,500.00$1,500.00$1,294.65
179Signal support, type TC-12.31 design 6 pole, with mast arms TC-81.22 design 4 and design 4, as per plan (632E71225)EACH1$21,000$21,000$21,000$22,102
180Signal support, type TC-81.22, design 4, as per plan (632E72111)EACH7$13,500$13,500$13,500$13,875
181Signal support, type TC-81.22, design 12, as per plan (632E72131)EACH2$17,000$17,000$17,000$17,430
182Pedestal, 10.7' tall, transformer base, as per plan (632E89921)EACH12$2,500.00$2,500.00$2,500.00$2,725.00
183Removal of traffic signal installation, as per plan (632E90101)EACH2$6,000.00$6,000.00$6,000.00$3,550.00
184Signalization, misc.: accessible pedestrian pushbu (632E90400)EACH3$2,700.00$2,700.00$2,700.00$3,200.00
185Cabinet, type TS-2, as per plan (633E65511)EACH3$19,000$19,000$19,000$17,000
186Cabinet foundation, as per plan (633E67101)EACH3$6,000.00$6,000.00$6,000.00$1,965.00
187Controller work pad, as per plan (633E67201)EACH1$2,500.00$2,500.00$2,500.00$465.00
188Atc controller, as per plan (809E69123)EACH3$6,000.00$6,000.00$6,000.00$7,620.00
190GPS (global positioning system) clock assembly, as per plan (633E45001)EACH3$750.00$750.00$750.00$962.00
192Uninterruptible power supply (UPS), 1000 watt, as per plan (633E75001)EACH3$8,000.00$8,000.00$8,000.00$9,060.00
194Stop line radar detection, as per plan (809E69101)EACH11$9,975.00$9,975.00$9,975.00$9,370.00
195Deciduous shrub, 2' height, ceonanthus americanus (661E20040)EACH43$142.00$141.75$141.75$450.57
196Deciduous shrub, 2' height, cornus racemosa (gray (661E20040)EACH45$149.00$148.50$148.46$426.97
197Deciduous shrub, 2' height, rhus aromatica (fragra (661E20040)EACH36$140.00$140.00$139.83$429.52
198Deciduous tree, 5' height, amelanchier laevis (all (661E40000)EACH10$689.00$688.25$688.26$881.47
199Deciduous tree, 2" caliper, betula nigra (river BI (661E40080)EACH7$681.00$681.00$680.93$855.16
200Deciduous tree, 2" caliper, cercis canadensis 'JN7 (661E40080)EACH5$638.00$638.00$637.18$881.47
201Deciduous tree, 2" caliper, ginkgo biloba 'goldspi (661E40080)EACH15$839.00$839.00$838.43$934.11
202Deciduous tree, 2" caliper, gymnocladus dioicus 'E (661E40080)EACH13$722.00$722.00$721.95$920.95
203Deciduous tree, 2" caliper, malus 'JFS-KW5' (royal (661E40080)EACH44$628.00$628.00$627.24$828.84
204Deciduous tree, 2" caliper, malus domestica 'johnn (661E40080)EACH12$622.00$622.00$621.78$874.89
205Deciduous tree, 2" caliper, plantanus occidentalis (661E40080)EACH6$700.00$700.00$699.76$881.47
206Deciduous tree, 2" caliper, ulmus X 'patriot' (pat (661E40080)EACH19$700.00$700.00$699.56$861.74
207Deciduous tree, 3" caliper, nyssa sylvatica 'david (661E40120)EACH9$977.00$977.00$976.87$1,095.95
208Special - bench (690E98000)EACH11$3,100.00$4,700.00$3,000.00$9,056.46
213Traffic compacted surface, type A or B (410E12000)CY100$75.00$400.00$100.00$85.00
214Law enforcement officer with patrol car for assistance (614E11110)HR96$90.00$115.00$150.00$85.00
215Special - work zone traffic signal (614E11300)EACH1$30,000$30,000$30,000$27,300
216Detour signing (614E12420)LS1$17,000$28,345$55,000$20,000
217Asphalt concrete for maintaining traffic (614E13000)CY100$497.00$280.00$375.00$809.24
218Portable changeable message sign, as per plan (614E18601)SNMT57$1,100.00$550.00$550.00$450.00
219Work zone lane line, class I, 4" (614E20000)MI0.09$650.00$630.00$650.00$650.00
220Work zone lane line, class III, 4", 642 paint (614E20550)MI0.09$650.00$540.00$650.00$650.00
221Work zone center line, class I (614E21000)MI0.44$1,500.00$2,370.00$1,500.00$1,500.00
222Work zone center line, class III, 642 paint (614E21550)MI0.39$1,500.00$1,580.00$1,500.00$1,500.00
223Work zone edge line, class I, 4" (614E22000)MI0.52$950.00$1,380.00$950.00$950.00
224Work zone channelizing line, class I, 8" (614E23000)FT793$1.00$0.80$1.00$1.00
225Work zone channelizing line, class III, 8", 642 paint (614E23680)FT793$1.00$0.65$1.00$1.00
226Work zone dotted line, class I (614E24000)FT218$0.80$0.45$0.80$0.80
227Work zone dotted line, class III, 4", 642 paint (614E24610)FT158$0.80$0.45$0.80$0.80
228Work zone stop line, class I (614E26000)FT268$3.00$3.35$3.00$3.00
229Work zone stop line, class III, 642 paint (614E26610)FT268$3.00$3.00$3.00$3.00
230Work zone crosswalk line, class I, 24" (614E27020)FT1,070$3.00$2.10$3.00$3.00
231Work zone crosswalk line, class III, 24", 642 paint (614E27260)FT1,070$3.00$1.95$3.00$3.00
232Work zone arrow, class I (614E30000)EACH17$75.00$140.00$75.00$75.00
233Work zone arrow, class III, 642 paint (614E30650)EACH17$75.00$135.00$75.00$75.00
234Water (616E10000)MGAL10$1,208.31$120.00$90.00$33.00
235Special - work involving petroleum contaminated soil (690E65016)TON8,500$45.00$55.00$105.00$63.63
236Special - work involving non-regulated water (690E65022)GAL500$3.00$10.00$62.00$32.76
237Special - work involving regulated water (690E65024)GAL500$3.50$11.00$72.00$38.10
238Premium for contract performance bond and for payment bond (103E05000)LS1$35,000$42,511$39,015$44,072
239Maintaining traffic (614E11000)LS1$50,000$150,000$144,500$75,000
240Field office, type C (619E16020)MNTH16$3,000.00$5,000.00$5,000.00$4,775.00
241Construction layout stakes and surveying (623E10000)LS1$112,000$126,000$110,000$105,000
242Mobilization (624E10000)LS1$350,000$375,000$200,000$380,000
ODOT contract 260364: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of August 13, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy