ODOT contract 260380 bid tabulation

CLA-US 40-14.14 (TWO LANE RESURFACING). Let by Ohio DOT on August 27, 2026, CLA. 2 bids received; low bid $1,116,903 by A & B Asphalt Corporation, +1.8% against the engineer's estimate of $1,097,000.

Owner
Ohio DOT
Letting
27 AUG 2026
Pay items
47
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1A & B Asphalt Corporation$1,116,903Low+2.0%
2Barrett Paving Materials Inc$1,364,252+22%+24%
ODOT contract 260380: bids by rank

Engineer's estimate: $1,097,000.

Bid tabulation

LinePay itemUnitQuantity1. A & B Asphalt Corporation2. Barrett Paving Materials Inc
1Pavement removed (202E23000)SY850$27.07$21.00
2Curb removed (202E32000)FT470$26.12$13.00
3Excavation (203E10000)CY152$93.83$58.00
4Subgrade compaction (204E10000)SY903$6.67$2.45
5Seeding and mulching, class 1 (659E00500)SY55$5.00$20.00
64" shallow pipe underdrains (605E05100)FT215$30.05$45.00
74" conduit, type F for underdrain outlet (611E00410)FT20$24.69$100.00
8Manhole adjusted to grade, as per plan (611E99655)EACH45$1,406.00$1,700.00
9Manhole, misc.: manhole casting furnished (611E99690)EACH45$597.23$500.00
10Partial depth pavement repair (asphalt concrete base), as per plan (251E01041)SY1,000$72.26$95.00
11Pavement planing, asphalt concrete, 1 3/4" depth (254E01000)SY32,326$1.95$4.40
12Patching planed surface, as per plan (254E01601)SY100$27.80$13.00
13Aggregate base (304E20000)CY152$138.91$130.00
14Non-tracking tack coat (407E20000)GAL2,757$4.97$4.50
15Asphalt concrete surface course, 12.5 MM, type A (448) (442E20000)CY1,581$296.72$370.00
169" reinforced concrete pavement, class QC 1P (451E14010)SY850$121.43$127.00
17Curb, type 2-A (609E14000)FT235$65.00$12.00
18Curb, type 4-A (609E24000)FT235$65.00$12.00
19Valve box adjusted to grade, as per plan (638E10801)EACH33$850.00$900.00
20Water work, misc.: valve box casting furnished (638E98000)EACH33$222.18$325.00
21Lane line, 4", type 1 (642E00200)MI2.25$785.00$785.00
22Center line, type 1 (642E00300)MI1.49$1,555.00$1,555.00
23Channelizing line, 8" (644E00400)FT550$3.10$3.10
24Stop line (644E00500)FT351$7.20$7.20
25Crosswalk line, 12" (644E00620)FT1,367$3.55$3.55
26Transverse/diagonal line (644E00700)FT332$7.15$7.15
27Lane arrow (644E01300)EACH51$127.73$127.73
28Word on pavement, 72" (644E01400)EACH5$255.43$255.43
29Lane line, 4" (646E10100)MI0.04$11,331$11,331
30Channelizing line, 8" (646E10300)FT50$41.83$41.83
31Lane arrow (646E20300)EACH1$1,000.00$1,000.00
32Word on pavement, 72" (646E20400)EACH1$1,091.88$1,091.88
33Loop detector unit, as per plan (632E27005)EACH3$1,600.00$1,445.00
34Loop detector tie in, as per plan (632E27201)EACH3$100.00$185.00
35Law enforcement officer with patrol car for assistance (614E11110)HR50$75.00$100.00
36Work zone lane line, class III, 4", 642 paint (614E20550)MI4.54$595.00$595.00
37Work zone center line, class III, 642 paint (614E21550)MI2.98$1,786.00$1,786.00
38Work zone channelizing line, class III, 8", 642 paint (614E23680)FT1,150$0.55$0.55
39Work zone transverse/diagonal line, class III, 642 paint (614E25620)FT332$3.35$3.35
40Work zone stop line, class III, 642 paint (614E26610)FT702$3.75$3.75
41Work zone crosswalk line, class III, 12", 642 paint (614E27250)FT1,367$1.85$1.85
42Work zone arrow, class III, 642 paint (614E30650)EACH103$37.00$37.00
43Work zone word on pavement, 72", class III, 642 paint (614E31620)EACH11$52.00$52.00
44Premium for contract performance bond and for payment bond (103E05000)LS1$3,914.44$3,000.00
45Maintaining traffic (614E11000)LS1$54,472$55,000
46Detour signing (614E12420)LS1$5,690.00$5,690.00
47Mobilization (624E10000)LS1$32,594$86,940
ODOT contract 260380: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of August 27, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy