ODOT contract 250478 bid tabulation
D06-ELEC FY26 (LIGHTING). Let by Ohio DOT on October 9, 2025, District 6. 4 bids received; low bid $489,159 by Perram Electric Inc, -4.6% against the engineer's estimate of $513,000.
- Owner
- Ohio DOT
- Letting
- 09 OCT 2025
- Pay items
- 93
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Perram Electric Inc | $489,159 | Low | -5.0% |
| 2 | Complete General Construction Company | $583,070 | +19% | +14% |
| 3 | Capital Electric Line Builders Inc | $650,535 | +33% | +27% |
| 4 | Danbert Electrical Corp | $655,363 | +34% | +28% |
Engineer's estimate: $513,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Perram Electric Inc | 2. Complete General Construction Company | 3. Capital Electric Line Builders Inc | 4. Danbert Electrical Corp |
|---|---|---|---|---|---|---|---|
| 1 | Erosion control (832E30000) | EACH | 1,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 2 | Connection, fused pull apart (625E00450) | EACH | 32 | $170.00 | $115.00 | $102.19 | $157.00 |
| 3 | Connection, unfused pull apart (625E00460) | EACH | 32 | $150.00 | $115.00 | $97.21 | $145.00 |
| 4 | Connection, unfused permanent (625E00480) | EACH | 10 | $150.00 | $110.00 | $71.79 | $133.00 |
| 5 | Transformer base, type at-A (625E02500) | EACH | 10 | $790.00 | $675.00 | $913.36 | $777.00 |
| 6 | Transformer base, type at-C (625E02600) | EACH | 4 | $920.00 | $750.00 | $1,068.31 | $939.00 |
| 7 | Transformer base, misc.: install only, as per plan (625E02803) | EACH | 10 | $280.00 | $175.00 | $315.36 | $165.00 |
| 8 | Light pole, conventional, as per plan, AT15B41.7 (625E10491) | EACH | 10 | $4,030.00 | $3,850.00 | $2,820.95 | $4,750.00 |
| 9 | Light pole, conventional, as per plan, AT15BB32.5 (625E10491) | EACH | 1 | $5,335.00 | $4,750.00 | $3,577.65 | $6,148.00 |
| 10 | Light pole, conventional, as per plan, AT20B41.7 (625E10491) | EACH | 1 | $4,680.00 | $5,000.00 | $3,026.80 | $5,530.00 |
| 11 | Light pole, low mast, ATLM50 (625E10494) | EACH | 2 | $5,060.00 | $4,750.00 | $3,783.50 | $5,986.00 |
| 12 | Light pole, low mast, LM50 (625E10494) | EACH | 2 | $5,220.00 | $4,750.00 | $4,540.36 | $6,178.00 |
| 13 | Light pole (installation only), as per plan (625E10503) | EACH | 5 | $700.00 | $575.00 | $756.86 | $580.00 |
| 14 | Erecting reusable downed light pole (625E10504) | EACH | 15 | $560.00 | $400.00 | $785.61 | $440.00 |
| 15 | Light pole foundation repair, as per plan (625E14401) | EACH | 1 | $925.00 | $1,500.00 | $1,124.15 | $1,838.00 |
| 16 | Light pole foundation (625E14500) | EACH | 1 | $1,820.00 | $1,850.00 | $3,053.30 | $2,406.00 |
| 17 | Bracket arm, 15', as per plan (625E18201) | EACH | 2 | $1,015.00 | $1,200.00 | $1,072.06 | $1,102.00 |
| 18 | Bracket arm, 20', as per plan (625E18401) | EACH | 1 | $1,390.00 | $1,575.00 | $1,103.11 | $1,662.00 |
| 19 | Bracket arm, misc.: install only (625E18600) | EACH | 1 | $420.00 | $475.00 | $378.43 | $440.00 |
| 20 | No. 4 AWG 2400 volt distribution cable, as per plan (625E23201) | FT | 1,000 | $3.75 | $4.50 | $3.62 | $5.61 |
| 21 | No. 2 AWG 2400 volt distribution cable, as per plan (625E23301) | FT | 1,000 | $4.15 | $5.00 | $4.08 | $6.93 |
| 22 | No. 10 AWG pole and bracket cable (625E23400) | FT | 2,000 | $1.65 | $1.50 | $2.56 | $1.78 |
| 23 | 1-1/2" duct cable with three no. 4 AWG 2400 volt cables (625E24320) | FT | 300 | $12.80 | $15.00 | $18.44 | $18.70 |
| 24 | 1-1/2" duct cable with three no. 2 AWG 2400 volt cables (625E24330) | FT | 300 | $15.80 | $20.00 | $116.99 | $21.10 |
| 25 | Conduit, 2", 725.04 (625E25400) | FT | 200 | $16.00 | $25.00 | $15.28 | $26.92 |
| 26 | Conduit, 3", 725.04 (625E25500) | FT | 200 | $27.40 | $37.00 | $26.94 | $50.76 |
| 27 | Conduit, jacked or drilled, under pavement, 3" (625E25900) | FT | 50 | $79.20 | $42.00 | $84.19 | $89.12 |
| 28 | Luminaire, conventional, solid state (LED), as per plan (625E26253) | EACH | 10 | $210.00 | $190.00 | $31.54 | $165.00 |
| 29 | Luminaire, conventional, solid state (LED), as per plan (625E26253) | EACH | 10 | $400.00 | $450.00 | $164.71 | $477.00 |
| 30 | Luminaire, conventional, solid state (LED), as per plan (625E26253) | EACH | 16 | $360.00 | $400.00 | $164.71 | $429.00 |
| 31 | Luminaire, high mast, solid state (LED), as per plan (625E26263) | EACH | 1 | $280.00 | $230.00 | $63.07 | $440.00 |
| 32 | Luminaire, low mast, solid state (LED), as per plan (625E26273) | EACH | 1 | $280.00 | $350.00 | $63.07 | $330.00 |
| 33 | Luminaire, misc.: group luminaire replacement, con (625E27600) | EACH | 128 | $468.00 | $375.00 | $164.71 | $429.00 |
| 34 | Trench (625E29000) | FT | 200 | $8.00 | $10.00 | $10.21 | $11.00 |
| 35 | Pull box, 725.08, 18" (625E30700) | EACH | 1 | $1,250.00 | $1,300.00 | $1,584.15 | $1,332.00 |
| 36 | Pull box, 725.08, 24" (625E30706) | EACH | 1 | $1,300.00 | $1,475.00 | $1,699.15 | $1,452.00 |
| 37 | Pull box removed and replaced, as per plan (625E31507) | EACH | 1 | $1,440.00 | $1,500.00 | $1,699.15 | $1,552.00 |
| 38 | Pull box removed (625E31510) | EACH | 1 | $140.00 | $250.00 | $1,044.36 | $354.00 |
| 39 | Ground rod, as per plan (625E32001) | EACH | 1 | $270.00 | $300.00 | $235.57 | $436.00 |
| 40 | Circuit breaker, tower lighting, as per plan (625E33101) | EACH | 3 | $840.00 | $600.00 | $753.07 | $765.00 |
| 41 | Power service, as per plan (625E34001) | EACH | 1 | $13,920 | $11,000 | $13,237 | $10,480 |
| 42 | Power service refurbished, as per plan (625E34011) | EACH | 1 | $12,980 | $9,000.00 | $13,237 | $14,100 |
| 43 | Control center cabinet, complete, as per plan (625E34451) | EACH | 1 | $6,640.00 | $9,200.00 | $7,122.87 | $12,250 |
| 44 | Repair integral luminaire lowering mechanism of tower lighting fixture, as per plan (625E50401) | EACH | 8 | $5,300.00 | $14,350 | $17,377 | $18,255 |
| 45 | Secondary surge protector, as per plan (625E50451) | EACH | 1 | $540.00 | $275.00 | $60.29 | $525.00 |
| 46 | Lighting contactor, as per plan (625E70001) | EACH | 2 | $640.00 | $850.00 | $1,276.14 | $1,030.00 |
| 47 | Light pole removed (625E75400) | EACH | 2 | $280.00 | $400.00 | $504.57 | $440.00 |
| 48 | Portion of light pole foundation removed (625E75502) | EACH | 4 | $560.00 | $600.00 | $871.86 | $560.00 |
| 49 | Distribution cable removed (625E75550) | FT | 1,000 | $1.40 | $0.75 | $1.26 | $0.88 |
| 50 | Lighting, misc.: fuse (KTK-10, 10 amp lighting fus (625E98000) | EACH | 20 | $84.00 | $30.00 | $42.75 | $70.00 |
| 51 | Lighting, misc.: photocell (for control center or (625E98000) | EACH | 1 | $240.00 | $300.00 | $55.74 | $310.00 |
| 52 | Lighting, misc.: test plug, as per plan (625E98000) | EACH | 5 | $240.00 | $350.00 | $178.07 | $1,000.00 |
| 53 | Lighting, misc.: troubleshooting (includes 2 men A (625E98700) | HR | 20 | $210.00 | $400.00 | $252.29 | $450.00 |
| 54 | Vehicular signal head, (LED), 3-section, 12" lens, 1-way, polycarbonate (632E05006) | EACH | 18 | $940.00 | $1,100.00 | $1,204.92 | $1,612.00 |
| 55 | Vehicular signal head, (LED), 5-section, 12" lens, 1-way, polycarbonate (632E05086) | EACH | 10 | $1,520.00 | $1,900.00 | $2,022.22 | $2,332.00 |
| 56 | Pedestrian signal head (LED), type D2, countdown (632E20730) | EACH | 2 | $460.00 | $800.00 | $843.03 | $926.00 |
| 57 | Accessible pedestrian pushbutton (632E20750) | EACH | 4 | $1,020.00 | $920.00 | $1,193.42 | $940.00 |
| 58 | Covering of vehicular signal head (632E25000) | EACH | 1 | $20.00 | $40.00 | $68.82 | $183.00 |
| 59 | Covering of pedestrian signal head (632E25010) | EACH | 2 | $20.00 | $35.00 | $68.82 | $122.00 |
| 60 | Pedestrian pushbutton (632E26000) | EACH | 4 | $250.00 | $450.00 | $382.24 | $358.00 |
| 61 | Detector loop (632E26500) | EACH | 1 | $1,340.00 | $3,900.00 | $3,270.37 | $5,502.00 |
| 62 | Loop detector tie in (632E27200) | EACH | 1 | $220.00 | $110.00 | $183.64 | $164.00 |
| 63 | Messenger wire, 7 strand, 3/8" diameter with accessories (632E30200) | FT | 500 | $10.00 | $14.00 | $24.20 | $15.88 |
| 64 | Tether wire, with accessories, as per plan (632E30601) | FT | 500 | $13.50 | $21.00 | $24.20 | $15.36 |
| 65 | Signal cable, 7 conductor, no. 14 AWG, as per plan (632E40701) | FT | 2,000 | $3.35 | $3.50 | $2.99 | $4.62 |
| 66 | Pedestal foundation (632E64020) | EACH | 1 | $1,010.00 | $1,100.00 | $2,446.65 | $2,020.00 |
| 67 | Loop detector lead-in cable (632E65200) | FT | 1,000 | $2.55 | $2.00 | $1.81 | $3.27 |
| 68 | Power cable, 1 conductor, no. 8 AWG (632E67190) | FT | 100 | $2.20 | $2.50 | $2.03 | $3.52 |
| 69 | Service cable, 3 conductor, no. 6 AWG (632E69800) | FT | 100 | $5.80 | $5.50 | $4.02 | $5.92 |
| 70 | Power service (632E70000) | EACH | 1 | $2,820.00 | $2,400.00 | $6,911.59 | $2,516.00 |
| 71 | Conduit riser, 2" diameter (632E70400) | EACH | 1 | $680.00 | $1,100.00 | $734.57 | $2,224.00 |
| 72 | Wood pole (632E89300) | EACH | 1 | $1,840.00 | $1,325.00 | $2,159.15 | $1,660.00 |
| 73 | Down guy (632E89400) | EACH | 1 | $580.00 | $1,050.00 | $1,584.15 | $2,440.00 |
| 74 | Pedestal, 8', transformer base (632E89900) | EACH | 1 | $640.00 | $1,100.00 | $907.43 | $1,376.00 |
| 75 | Removal of miscellaneous traffic signal item: cont (632E90020) | EACH | 1 | $280.00 | $550.00 | $2,018.30 | $1,100.00 |
| 76 | Removal of miscellaneous traffic signal item: stra (632E90020) | EACH | 1 | $280.00 | $1,325.00 | $2,018.30 | $660.00 |
| 77 | Removal of miscellaneous traffic signal item: stra (632E90020) | EACH | 1 | $700.00 | $1,075.00 | $2,133.30 | $1,000.00 |
| 78 | Removal of miscellaneous traffic signal item: vehi (632E90020) | EACH | 1 | $140.00 | $190.00 | $504.57 | $550.00 |
| 79 | Removal of miscellaneous traffic signal item: over (632E90030) | FT | 500 | $1.40 | $2.00 | $8.07 | $2.20 |
| 80 | Reuse of vehicular signal head (632E90200) | EACH | 8 | $280.00 | $375.00 | $510.32 | $1,340.00 |
| 81 | Signalization, misc.: traffic signal cable, instal (632E90500) | FT | 500 | $1.95 | $2.75 | $1.26 | $2.64 |
| 82 | Signalization, misc.: unlash and relash messenger (632E90500) | FT | 1,000 | $1.70 | $8.00 | $5.05 | $1.76 |
| 83 | Signalization, misc.: wavetronix cable (632E90500) | FT | 500 | $2.70 | $4.00 | $1.84 | $3.56 |
| 84 | Controller item, misc.: anchor bolt installation (633E99000) | EACH | 1 | $170.00 | $165.00 | $964.57 | $560.00 |
| 85 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 60 | $100.00 | $100.00 | $92.00 | $120.00 |
| 86 | Maintenance of traffic, one lane closure on A two lane highway (614E13600) | EACH | 5 | $860.00 | $1,450.00 | $3,698.68 | $1,180.00 |
| 87 | Maintenance of traffic, one lane closure on A four lane undivided highway (614E13700) | EACH | 5 | $580.00 | $2,000.00 | $5,588.51 | $1,180.00 |
| 88 | Maintenance of traffic, one lane closure on A 4 lane or greater divided highway (614E13800) | EACH | 5 | $580.00 | $2,000.00 | $6,585.58 | $1,180.00 |
| 89 | Maintenance of traffic for shoulder closure (614E13900) | EACH | 30 | $140.00 | $650.00 | $328.96 | $464.00 |
| 90 | Maintaining traffic, misc.: new cabinet installati (614E18000) | EACH | 1 | $2,440.00 | $2,800.00 | $4,822.87 | $1,760.00 |
| 91 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $19,270 | $3,500.00 | $6,541.60 | $3,500.00 |
| 92 | Construction layout stakes and surveying (623E10000) | LS | 1 | $500.00 | $4,500.00 | $5,034.15 | $3,000.00 |
| 93 | Mobilization, as per plan (624E15001) | EACH | 17 | $2,940.00 | $2,500.00 | $1,548.94 | $1,320.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of October 9, 2025. Compiled by Mirage Metrics.