ODOT contract 250458 bid tabulation

CLI-Culverts FY26 (CULVERT REPLACEMENT). Let by Ohio DOT on October 9, 2025, CLI. 2 bids received; low bid $479,556 by Madex Construction Co, +29% against the engineer's estimate of $371,000.

Owner
Ohio DOT
Letting
09 OCT 2025
Pay items
22
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Madex Construction Co$479,556Low+29%
2Axis Civil Construction LLC$582,173+21%+57%
ODOT contract 250458: bids by rank

Engineer's estimate: $371,000.

Bid tabulation

LinePay itemUnitQuantity1. Madex Construction Co2. Axis Civil Construction LLC
1Clearing and grubbing (201E11000)LS1$7,562.52$15,000
2Special - pipe cleanout over 48" (202E70130)FT186$71.37$300.00
3Cofferdams and excavation bracing, as per plan (503E11101)LS1$10,365$7,500.00
4Cofferdams and excavation bracing, as per plan (503E11101)LS1$10,365$8,500.00
5Right-of-way monument, type B (623E40520)EACH4$868.42$400.00
6Rock channel protection, type B with filter (601E32100)CY20$430.48$275.00
7Topsoil (659E00300)CY86$86.84$65.00
8Seeding and mulching (659E10000)SY775$5.79$6.00
9Commercial fertilizer (659E20000)TON0.10$1,157.90$800.00
10Lime (659E31000)ACRE0.16$289.50$500.00
11Water (659E35000)MGAL4.20$1.13$1.00
12Erosion control (832E30000)EACH5,000$1.00$1.00
13Concrete masonry (602E20000)CY2.66$2,509.77$4,900.00
14Field paving of existing pipe, 92" X 66" CMP (611E96550)FT46$434.82$380.00
15Special - grouting voids around corrugated metal pipes (611E96650)CY2$4,631.58$12,000
16Conduit, misc.: CMP repair method A (611E97700)SF125$115.79$175.00
17Cured-in-place pipe liner, 49" X 33" (899E10000)FT102$1,100.00$1,050.00
18Cured-in-place pipe liner, 54" (899E10000)FT42$1,435.79$1,610.00
19Cured-in-place pipe liner, 58" X 36" (899E10000)FT84$1,157.89$1,390.00
20Premium for contract performance bond and for payment bond (103E05000)LS1$10,653$5,000.00
21Maintaining traffic (614E11000)LS1$27,331$50,000
22Mobilization (624E10000)LS1$50,619$50,000
ODOT contract 250458: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of October 9, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy