ODOT contract 250467 bid tabulation
MAH-US 422-03.13 (BRIDGE REPAIR). Let by Ohio DOT on October 9, 2025, MAH. 4 bids received; low bid $2,084,000 by A P O'Horo Company, -29% against the engineer's estimate of $2,950,000.
- Owner
- Ohio DOT
- Letting
- 09 OCT 2025
- Pay items
- 131
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | A P O'Horo Company | $2,084,000 | Low | -29% |
| 2 | Shelly & Sands Inc | $2,580,727 | +24% | -13% |
| 3 | J D Williamson Construction Co Inc | $2,695,318 | +29% | -9.0% |
| 4 | Marucci & Gaffney Excavating Co | $2,925,364 | +40% | -1.0% |
Engineer's estimate: $2,950,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. A P O'Horo Company | 2. Shelly & Sands Inc | 3. J D Williamson Construction Co Inc | 4. Marucci & Gaffney Excavating Co |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $2,000.00 | $4,600.00 | $6,200.00 | $65,000 |
| 2 | Pavement removed (202E23000) | SY | 1,290 | $9.00 | $5.50 | $8.00 | $17.00 |
| 3 | Walk removed (202E30000) | SF | 1,528 | $1.50 | $1.50 | $3.00 | $5.00 |
| 4 | Concrete barrier removed (202E30700) | FT | 60 | $45.00 | $72.00 | $45.00 | $60.00 |
| 5 | Curb removed (202E32000) | FT | 316 | $1.50 | $3.50 | $6.00 | $8.00 |
| 6 | Guardrail removed (202E38000) | FT | 195 | $5.00 | $7.00 | $5.00 | $5.00 |
| 7 | Fence removed (202E75000) | FT | 168 | $5.00 | $12.00 | $2.00 | $5.00 |
| 8 | Excavation (203E10000) | CY | 445 | $25.00 | $33.00 | $42.00 | $25.00 |
| 9 | Embankment (203E20000) | CY | 4 | $100.00 | $46.00 | $21.00 | $50.00 |
| 10 | Subgrade compaction (204E10000) | SY | 1,591 | $2.00 | $3.50 | $7.50 | $5.00 |
| 11 | Excavation of subgrade (204E13000) | CY | 10 | $25.00 | $70.00 | $26.00 | $5.00 |
| 12 | Granular material, type B (204E30010) | CY | 10 | $75.00 | $150.00 | $100.00 | $15.00 |
| 13 | Geotextile fabric (204E50000) | SY | 20 | $1.50 | $26.00 | $3.00 | $2.00 |
| 14 | MGS bridge terminal assembly, type 1 (606E35002) | EACH | 4 | $3,000.00 | $3,200.00 | $3,300.00 | $3,267.00 |
| 15 | Fence, type CLT (607E23000) | FT | 168 | $65.00 | $69.00 | $67.00 | $70.00 |
| 16 | 4" concrete walk (608E10000) | SF | 560 | $10.00 | $11.00 | $13.00 | $15.00 |
| 17 | Curb ramp (608E52000) | SF | 868 | $16.00 | $24.00 | $27.00 | $27.00 |
| 18 | Detectable warning (608E53020) | SF | 110 | $32.00 | $28.00 | $32.00 | $30.00 |
| 19 | Curb, type 6 (609E26000) | FT | 125 | $40.00 | $35.00 | $38.00 | $47.00 |
| 20 | Monument assembly adjusted to grade (623E39500) | EACH | 3 | $500.00 | $175.00 | $820.00 | $872.00 |
| 21 | Ground rod (625E32000) | EACH | 14 | $350.00 | $320.00 | $370.00 | $380.00 |
| 22 | Special - valve box adjusted to grade, city of you (638E20500) | EACH | 7 | $500.00 | $150.00 | $850.00 | $150.00 |
| 23 | Special - as-built construction plans (690E91000) | LS | 1 | $100.00 | $4,000.00 | $10,000 | $5,000.00 |
| 24 | Special - survey control verifcation (690E98400) | LS | 1 | $1,500.00 | $2,100.00 | $3,100.00 | $3,200.00 |
| 25 | Topsoil (659E00300) | CY | 3 | $60.00 | $400.00 | $100.00 | $100.00 |
| 26 | Seeding and mulching (659E10000) | SY | 240 | $3.00 | $23.00 | $4.00 | $5.00 |
| 27 | Commercial fertilizer (659E20000) | TON | 0.01 | $1,000.00 | $540.00 | $450.00 | $400.00 |
| 28 | Lime (659E31000) | ACRE | 0.01 | $1,000.00 | $540.00 | $30.00 | $10.00 |
| 29 | Water (659E35000) | MGAL | 0.14 | $1.00 | $10.00 | $2.00 | $0.00 |
| 30 | Erosion control (832E30000) | EACH | 26,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 31 | Tied concrete block mat with type 1 underlayment (601E21050) | SY | 6 | $200.00 | $220.00 | $165.00 | $300.00 |
| 32 | Concrete masonry (602E20000) | CY | 0.20 | $2,800.00 | $4,400.00 | $3,560.00 | $4,000.00 |
| 33 | 6" shallow pipe underdrains with geotextile fabric (605E11110) | FT | 62 | $20.00 | $35.00 | $19.00 | $30.00 |
| 34 | 6" unclassified pipe underdrains with geotextile fabric (605E13410) | FT | 157 | $18.00 | $35.00 | $26.00 | $25.00 |
| 35 | 6" base pipe underdrains with geotextile fabric (605E14020) | FT | 223 | $16.00 | $31.00 | $19.00 | $25.00 |
| 36 | 6" conduit, type F (611E01500) | FT | 57 | $25.00 | $24.00 | $38.00 | $20.00 |
| 37 | 12" conduit, type B (611E04400) | FT | 60 | $125.00 | $276.00 | $200.00 | $150.00 |
| 38 | 12" conduit, type C (611E04600) | FT | 12 | $95.00 | $184.00 | $125.00 | $190.00 |
| 39 | 12" conduit, type F, as per plan, 707.33 (611E05201) | FT | 37 | $135.00 | $141.00 | $135.00 | $231.00 |
| 40 | Catch basin, no. 3A (611E98180) | EACH | 1 | $4,000.00 | $6,800.00 | $5,900.00 | $4,000.00 |
| 41 | Catch basin, no. 6 (611E98370) | EACH | 1 | $4,000.00 | $6,300.00 | $6,650.00 | $4,500.00 |
| 42 | Catch basin adjusted to grade (611E98630) | EACH | 2 | $900.00 | $1,200.00 | $795.00 | $1,300.00 |
| 43 | Catch basin grate (611E98644) | EACH | 2 | $400.00 | $330.00 | $420.00 | $900.00 |
| 44 | Manhole, no. 3 (611E99574) | EACH | 1 | $4,000.00 | $5,100.00 | $10,150 | $6,000.00 |
| 45 | Manhole adjusted to grade (611E99654) | EACH | 3 | $1,000.00 | $1,130.00 | $675.00 | $2,400.00 |
| 46 | Precast reinforced concrete outlet (611E99710) | EACH | 3 | $215.00 | $575.00 | $385.00 | $350.00 |
| 47 | Special - miscellaneous metal (611E99820) | LB | 400 | $4.00 | $2.00 | $2.00 | $3.00 |
| 48 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 291 | $216.00 | $231.25 | $215.00 | $231.25 |
| 49 | Aggregate base (304E20000) | CY | 266 | $90.00 | $100.00 | $140.00 | $110.00 |
| 50 | Non-tracking tack coat (407E20000) | GAL | 214 | $3.10 | $3.05 | $2.00 | $3.05 |
| 51 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 108 | $348.00 | $315.30 | $330.00 | $315.30 |
| 52 | Connection, fused pull apart (625E00450) | EACH | 2 | $250.00 | $160.00 | $115.00 | $272.00 |
| 53 | Connection, unfused pull apart (625E00460) | EACH | 2 | $250.00 | $160.00 | $115.00 | $272.00 |
| 54 | Light pole, conventional, as per plan, 40' height, (625E10491) | EACH | 2 | $5,500.00 | $5,900.00 | $5,170.00 | $5,900.00 |
| 55 | Light pole foundation, 24" X 8' deep, as per plan (625E14101) | EACH | 2 | $3,000.00 | $3,350.00 | $3,850.00 | $3,200.00 |
| 56 | No. 4 AWG 2400 volt distribution cable (625E23200) | FT | 935 | $4.00 | $5.00 | $3.50 | $4.00 |
| 57 | No. 10 AWG pole and bracket cable (625E23400) | FT | 372 | $2.00 | $2.00 | $2.00 | $2.00 |
| 58 | Conduit, 2", 725.052 (625E25410) | FT | 223 | $20.00 | $28.00 | $7.00 | $22.00 |
| 59 | Conduit, 3", 725.052 (625E25506) | FT | 77 | $25.00 | $18.00 | $8.00 | $27.00 |
| 60 | Luminaire, conventional, solid state (LED), asymme (625E26252) | EACH | 2 | $800.00 | $550.00 | $730.00 | $871.00 |
| 61 | Trench, 30" deep (625E29010) | FT | 115 | $20.00 | $22.00 | $10.00 | $22.00 |
| 62 | Barrier junction box, as per plan (625E29941) | EACH | 2 | $4,500.00 | $3,200.00 | $4,460.00 | $4,900.00 |
| 63 | Pull box, 725.08, 18" (625E30700) | EACH | 3 | $2,000.00 | $1,100.00 | $1,180.00 | $2,200.00 |
| 64 | Ground rod (625E32000) | EACH | 7 | $350.00 | $300.00 | $300.00 | $380.00 |
| 65 | Underground warning marking tape (625E36010) | FT | 115 | $3.00 | $3.00 | $1.50 | $3.00 |
| 66 | Special - maintain existing lighting (625E40000) | LS | 1 | $13,000 | $2,200.00 | $7,170.00 | $16,000 |
| 67 | Light pole removed, as per plan (625E75401) | EACH | 6 | $250.00 | $320.00 | $390.00 | $270.00 |
| 68 | Distribution cable removed (625E75550) | FT | 25 | $10.00 | $1.00 | $2.00 | $11.00 |
| 69 | Conduit riser, 2" diameter, as per plan (632E70401) | EACH | 1 | $750.00 | $800.00 | $750.00 | $22.00 |
| 70 | Conduit, 2", 725.052 (625E25410) | FT | 4 | $20.00 | $30.00 | $11.00 | $22.00 |
| 71 | Trench, 30" deep (625E29010) | FT | 4 | $20.00 | $24.00 | $10.00 | $22.00 |
| 72 | Underground warning marking tape (625E36010) | FT | 4 | $3.00 | $2.70 | $1.50 | $3.00 |
| 73 | Ground mounted support, no. 2 post (630E02100) | FT | 18 | $21.46 | $23.00 | $22.00 | $23.00 |
| 74 | Ground mounted support, no. 3 post (630E03100) | FT | 15 | $24.14 | $25.00 | $25.00 | $26.00 |
| 75 | Ground mounted support, no. 4 post (630E04100) | FT | 15 | $34.84 | $37.00 | $36.00 | $37.00 |
| 76 | Sign attachment assembly (630E75000) | EACH | 2 | $575.60 | $617.00 | $600.00 | $630.00 |
| 77 | Sign, flat sheet (630E80100) | SF | 32 | $28.16 | $30.00 | $30.00 | $31.00 |
| 78 | Removal of ground mounted sign and disposal (630E84900) | EACH | 6 | $16.68 | $18.00 | $17.00 | $10.00 |
| 79 | Removal of ground mounted sign and reerection (630E85100) | EACH | 3 | $86.33 | $92.00 | $90.00 | $95.00 |
| 80 | Pedestal foundation (632E64020) | EACH | 1 | $2,000.00 | $1,286.00 | $1,150.00 | $2,200.00 |
| 81 | Signalization, misc.:remove pedestrian signal head (632E90400) | EACH | 1 | $3,000.00 | $1,286.00 | $1,190.00 | $3,300.00 |
| 82 | Lane line, 6" (646E10110) | MI | 0.04 | $44,000 | $47,200 | $46,000 | $47,900 |
| 83 | Center line (646E10200) | MI | 0.05 | $44,000 | $47,200 | $46,000 | $47,900 |
| 84 | Channelizing line, 12" (646E10310) | FT | 255 | $1.55 | $1.75 | $2.00 | $2.00 |
| 85 | Stop line (646E10400) | FT | 140 | $12.00 | $12.00 | $12.00 | $13.00 |
| 86 | Crosswalk line, 12" (646E10510) | FT | 442 | $12.00 | $12.00 | $12.00 | $13.00 |
| 87 | Lane arrow (646E20300) | EACH | 6 | $160.00 | $171.00 | $170.00 | $175.00 |
| 88 | Shared lane marking (646E20650) | EACH | 2 | $120.00 | $129.00 | $125.00 | $131.00 |
| 89 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 120 | $75.00 | $100.00 | $110.00 | $90.00 |
| 90 | Detour signing (614E12420) | LS | 1 | $15,000 | $14,600 | $15,000 | $25,000 |
| 91 | Portable changeable message sign, as per plan (614E18601) | SNMT | 15 | $800.00 | $1,270.00 | $1,320.00 | $1,300.00 |
| 92 | Work zone center line, class I, 740.06, type I (614E21200) | MI | 0.14 | $11,895 | $12,800 | $12,400 | $6,000.00 |
| 93 | Work zone stop line, class I, 740.06, type I (614E26400) | FT | 12 | $6.15 | $7.00 | $7.00 | $15.00 |
| 94 | Water (616E10000) | MGAL | 1 | $1.00 | $485.00 | $5.00 | $0.01 |
| 95 | Portions of structure removed, over 20 foot span, as per plan (202E11203) | LS | 1 | $200,000 | $197,000 | $400,000 | $600,000 |
| 96 | Approach slab removed (202E22900) | SY | 339 | $35.00 | $42.00 | $50.00 | $25.00 |
| 97 | Wearing course removed (202E23500) | SY | 1,201 | $3.00 | $2.50 | $6.00 | $10.00 |
| 98 | Sealing, misc:acrylic stain (409E98000) | SY | 338 | $60.00 | $240.00 | $28.00 | $95.00 |
| 99 | Unclassified excavation (503E21300) | LS | 1 | $10,000 | $15,000 | $30,000 | $25,000 |
| 100 | Epoxy coated steel reinforcement (509E10000) | LB | 133,455 | $1.35 | $1.65 | $1.40 | $1.44 |
| 101 | Dowel holes with nonshrink, nonmetallic grout, as per plan (510E10001) | EACH | 612 | $25.00 | $44.00 | $26.00 | $30.00 |
| 102 | Class QC2 concrete with QC/QA, bridge deck, as per plan (511E34447) | CY | 359 | $900.00 | $1,075.00 | $860.00 | $980.00 |
| 103 | Class QC1 concrete, abutment not including footing (511E44110) | CY | 37 | $1,000.00 | $2,060.00 | $1,510.00 | $900.00 |
| 104 | Class QC1 concrete, footing (511E46510) | CY | 16 | $400.00 | $1,700.00 | $1,050.00 | $700.00 |
| 105 | Sealing of concrete surfaces (non-epoxy) (512E10050) | SY | 560 | $31.00 | $16.00 | $11.00 | $30.00 |
| 106 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 724 | $50.00 | $37.00 | $30.00 | $30.00 |
| 107 | Removal of existing coatings from concrete surfaces (512E74000) | SY | 128 | $225.00 | $53.00 | $36.00 | $40.00 |
| 108 | Structural steel members, level UF (513E10200) | LB | 361 | $33.15 | $36.00 | $35.00 | $36.00 |
| 109 | Welded stud shear connectors (513E20000) | EACH | 5,604 | $4.50 | $4.75 | $5.00 | $4.00 |
| 110 | Structural steel, misc.:tubular steel "Y" (513E95030) | EACH | 4 | $2,500.00 | $5,950.00 | $2,700.00 | $2,500.00 |
| 111 | Structural expansion joint including elastomeric strip seal (516E11210) | FT | 121 | $780.00 | $857.00 | $820.00 | $941.00 |
| 112 | 1" preformed expansion joint filler (516E13600) | SF | 170 | $5.00 | $7.00 | $7.00 | $10.00 |
| 113 | 2" preformed expansion joint filler (516E13900) | SF | 35 | $7.00 | $10.00 | $9.00 | $15.00 |
| 114 | Elastomeric bearing with internal laminates and load plate (516E44200) | EACH | 16 | $1,100.00 | $1,300.00 | $1,085.00 | $1,235.00 |
| 115 | Elastomeric bearing with internal laminates and load plate (516E44200) | EACH | 16 | $1,300.00 | $1,400.00 | $1,315.00 | $1,345.00 |
| 116 | Elastomeric bearing with internal laminates and load plate (516E44200) | EACH | 8 | $1,400.00 | $1,970.00 | $1,315.00 | $2,098.00 |
| 117 | Jacking and temporary support of superstructure, as per plan (516E47001) | LS | 1 | $50,000 | $37,500 | $175,000 | $39,000 |
| 118 | Railing (concrete parapet with twin steel tube railing and vandal protection fence), as per plan (517E75123) | FT | 495 | $240.00 | $380.00 | $195.00 | $150.00 |
| 119 | Porous backfill with geotextile fabric (518E21200) | CY | 53 | $90.00 | $145.00 | $145.00 | $100.00 |
| 120 | Patching concrete structure, as per plan (519E11101) | SF | 95 | $225.00 | $215.00 | $100.00 | $165.00 |
| 121 | Reinforced concrete approach slabs with QC/QA (T=1 (526E15010) | SY | 282 | $325.00 | $470.00 | $455.00 | $450.00 |
| 122 | Type A installation (526E90010) | FT | 133 | $100.00 | $175.00 | $215.00 | $160.00 |
| 123 | Special - structurescheck proposed vertical clearn (530E00200) | LS | 1 | $500.00 | $1,250.00 | $1,600.00 | $1,000.00 |
| 124 | Special - form liner (530E13000) | SF | 3,030 | $12.00 | $3.25 | $12.00 | $10.00 |
| 125 | Vandal protection fence, 8' straight, coated fabric, as per plan (607E39911) | FT | 352 | $148.00 | $158.00 | $200.00 | $160.00 |
| 126 | Special - vandal protection fence (607E40000) | FT | 125 | $128.00 | $137.00 | $182.00 | $139.00 |
| 127 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $32,500 | $14,300 | $27,000 | $15,000 |
| 128 | Maintaining traffic (614E11000) | LS | 1 | $30,000 | $110,000 | $146,000 | $200,000 |
| 129 | Field office, type B (619E16010) | MNTH | 6 | $1,800.00 | $4,900.00 | $1,850.00 | $2,200.00 |
| 130 | Construction layout stakes and surveying (623E10000) | LS | 1 | $3,000.00 | $20,000 | $23,500 | $53,000 |
| 131 | Mobilization (624E10000) | LS | 1 | $100,000 | $128,500 | $135,000 | $130,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of October 9, 2025. Compiled by Mirage Metrics.