ODOT contract 254027 bid tabulation
CUY-IR 480-21.61 Ramp Slope (SLIDE REPAIR). Let by Ohio DOT on October 9, 2025, CUY. 2 bids received; low bid $752,957 by Shook Company LLC, +25% against the engineer's estimate of $601,000.
- Owner
- Ohio DOT
- Letting
- 09 OCT 2025
- Pay items
- 65
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Shook Company LLC | $752,957 | Low | +25% |
| 2 | Madex Construction Co | $829,816 | +10% | +38% |
Engineer's estimate: $601,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Shook Company LLC | 2. Madex Construction Co |
|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $40,000 | $26,201 |
| 2 | Headwall removed (202E20010) | EACH | 1 | $500.00 | $813.32 |
| 3 | Pavement removed (202E23000) | SY | 1,200 | $4.00 | $2.50 |
| 4 | Pipe removed, 24" and under (202E35100) | FT | 44 | $20.00 | $52.07 |
| 5 | Guardrail removed (202E38000) | FT | 737.50 | $10.00 | $3.48 |
| 6 | Fence removed (202E75000) | FT | 648 | $15.00 | $5.79 |
| 7 | Excavation (203E10000) | CY | 5,009 | $25.00 | $27.56 |
| 8 | Embankment (203E20000) | CY | 4,749 | $25.00 | $29.28 |
| 9 | Subgrade compaction (204E10000) | SY | 200 | $15.00 | $4.63 |
| 10 | Reshaping under guardrail, as per plan (209E15001) | STA | 8 | $250.00 | $472.66 |
| 11 | Guardrail, type MGS (606E15050) | FT | 737.50 | $35.00 | $26.63 |
| 12 | Fence, type CLT (607E23000) | FT | 651 | $30.00 | $42.84 |
| 13 | Rock channel protection, type A with geotextile fabric (601E32004) | CY | 260 | $200.00 | $205.65 |
| 14 | Rock channel protection, type B with geotextile fabric (601E32104) | CY | 194 | $175.00 | $203.20 |
| 15 | Water (616E10000) | MGAL | 12 | $1.00 | $1.16 |
| 16 | Soil analysis test (659E00100) | EACH | 1 | $25.00 | $89.47 |
| 17 | Topsoil (659E00300) | CY | 234 | $50.00 | $86.84 |
| 18 | Seeding and mulching, class 5B (659E00580) | SY | 2,107 | $3.00 | $4.63 |
| 19 | Repair seeding and mulching (659E14000) | SY | 105 | $0.25 | $1.16 |
| 20 | Inter-seeding (659E15000) | SY | 105 | $0.25 | $1.16 |
| 21 | Commercial fertilizer (659E20000) | TON | 0.28 | $500.00 | $1,157.89 |
| 22 | Lime (659E31000) | ACRE | 0.44 | $500.00 | $289.89 |
| 23 | Water (659E35000) | MGAL | 372 | $1.00 | $0.50 |
| 24 | Slope erosion protection (670E00500) | SY | 2,215 | $5.00 | $4.63 |
| 25 | Erosion control (832E30000) | EACH | 12,000 | $1.00 | $1.00 |
| 26 | Class QC1 concrete, headwall (511E46610) | CY | 0.40 | $3,750.00 | $5,797.62 |
| 27 | 21" conduit, type F (611E09700) | FT | 40 | $200.00 | $190.06 |
| 28 | Pavement planing, asphalt concrete, (T = 3.0") (254E01000) | SY | 2,800 | $1.00 | $2.00 |
| 29 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 49 | $270.00 | $521.05 |
| 30 | Aggregate base (304E20000) | CY | 33 | $250.00 | $151.43 |
| 31 | Non-tracking tack coat (407E20000) | GAL | 518 | $3.00 | $9.26 |
| 32 | Asphalt concrete intermediate course, type 1, (449), (under guardrail), as per plan (441E70801) | CY | 10 | $1,100.00 | $1,418.42 |
| 33 | Asphalt concrete surface course, 12.5 MM, type A (449), as per plan (442E22101) | CY | 37 | $830.90 | $1,418.42 |
| 34 | Connection, fused pull apart (625E00450) | EACH | 4 | $200.00 | $127.37 |
| 35 | Connection, unfused pull apart (625E00460) | EACH | 4 | $200.00 | $127.37 |
| 36 | Light pole, conventional, AT18B43 (625E10490) | EACH | 2 | $5,500.00 | $6,368.42 |
| 37 | Light pole foundation, 24" X 10' deep (625E14200) | EACH | 2 | $5,000.00 | $3,473.68 |
| 38 | 1-1/2" duct cable with two no. 4 AWG 2400 volt cables (625E24100) | FT | 776 | $10.00 | $11.00 |
| 39 | Removal of luminaire and reerection (625E27520) | EACH | 2 | $250.00 | $115.79 |
| 40 | Trench, 24" deep (625E29002) | FT | 746 | $10.00 | $9.26 |
| 41 | Ground rod (625E32000) | EACH | 2 | $350.00 | $289.47 |
| 42 | Light pole removed (625E75400) | EACH | 2 | $500.00 | $231.58 |
| 43 | Light pole foundation removed (625E75500) | EACH | 2 | $500.00 | $231.58 |
| 44 | Ground mounted support, no. 3 post (630E03100) | FT | 108.50 | $25.00 | $28.95 |
| 45 | Sign, flat sheet (630E80100) | SF | 47.75 | $27.00 | $30.87 |
| 46 | Removal of ground mounted sign and disposal (630E84900) | EACH | 4 | $17.00 | $28.95 |
| 47 | Removal of ground mounted post support and disposal (630E86002) | EACH | 6 | $23.00 | $34.74 |
| 48 | Edge line, 6" (646E10010) | MI | 0.23 | $8,700.00 | $10,421 |
| 49 | Lane line, 6" (646E10110) | MI | 0.16 | $5,200.00 | $6,368.44 |
| 50 | Channelizing line, 12" (646E10310) | FT | 1,162 | $1.50 | $1.74 |
| 51 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 24 | $85.00 | $115.79 |
| 52 | Work zone impact attenuator, 24" wide hazards, (unidirectional) (614E12380) | EACH | 1 | $3,000.00 | $2,663.16 |
| 53 | Barrier reflector, type 1, one-way (614E13310) | EACH | 9 | $12.75 | $17.37 |
| 54 | Object marker, one way (614E13350) | EACH | 7 | $20.80 | $27.79 |
| 55 | Portable changeable message sign, as per plan (614E18601) | SNMT | 4 | $1,225.00 | $1,447.37 |
| 56 | Work zone edge line, class I, 6" (614E22010) | MI | 0.40 | $2,500.00 | $2,894.75 |
| 57 | Work zone dotted line, class I (614E24000) | FT | 587 | $1.50 | $1.74 |
| 58 | Portable barrier, unanchored (622E41100) | FT | 690 | $43.00 | $52.11 |
| 59 | Signing, misc.: additional signs, ground mounted, (630E97900) | FT | 150 | $32.60 | $1.00 |
| 60 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $22,000 | $15,053 |
| 61 | Maintaining traffic (614E11000) | LS | 1 | $22,000 | $23,158 |
| 62 | Field office, type B, as per plan (619E16011) | MNTH | 6 | $1,500.00 | $539.57 |
| 63 | Construction layout stakes and surveying (623E10000) | LS | 1 | $10,000 | $8,789.47 |
| 64 | Preconstruction survey monument verification and report (623E50000) | LS | 1 | $1,000.00 | $2,894.74 |
| 65 | Mobilization (624E10000) | LS | 1 | $30,000 | $46,879 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of October 9, 2025. Compiled by Mirage Metrics.