ODOT contract 250451 bid tabulation
ERI-Sheldon Marsh SNP FY2026 (PARKING AREAS). Let by Ohio DOT on September 25, 2025, ERI. 2 bids received; low bid $282,956 by Erie Blacktop Inc, +10% against the engineer's estimate of $257,000.
- Owner
- Ohio DOT
- Letting
- 25 SEP 2025
- Pay items
- 31
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Erie Blacktop Inc | $282,956 | Low | +10% |
| 2 | Gerken Paving Inc | $471,182 | +67% | +83% |
Engineer's estimate: $257,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Erie Blacktop Inc | 2. Gerken Paving Inc |
|---|---|---|---|---|---|
| 1 | Curb removed (202E32000) | FT | 2,020 | $8.50 | $8.00 |
| 2 | Special - parking block removed and reset (202E53010) | EACH | 17 | $185.00 | $110.00 |
| 3 | Curb, type 6 (609E26000) | FT | 2,020 | $18.50 | $17.50 |
| 4 | Special - concrete parking block (690E50500) | EACH | 1 | $425.00 | $400.00 |
| 5 | Soil analysis test (659E00100) | EACH | 1 | $265.00 | $250.00 |
| 6 | Topsoil (659E00300) | CY | 50 | $94.50 | $90.00 |
| 7 | Seeding and mulching (659E10000) | SY | 449 | $3.15 | $3.00 |
| 8 | Repair seeding and mulching (659E14000) | SY | 22 | $5.25 | $5.00 |
| 9 | Inter-seeding (659E15000) | SY | 22 | $5.25 | $5.00 |
| 10 | Commercial fertilizer (659E20000) | TON | 0.06 | $1,575.00 | $1,500.00 |
| 11 | Lime (659E31000) | ACRE | 0.09 | $1,050.00 | $1,000.00 |
| 12 | Water (659E35000) | MGAL | 2.48 | $26.50 | $25.00 |
| 13 | Erosion control (832E30000) | EACH | 500 | $1.00 | $1.00 |
| 14 | Partial depth pavement repair (441) (251E01000) | SY | 400 | $70.00 | $25.00 |
| 15 | Pavement planing, asphalt concrete (1.50") (254E01000) | SY | 7,570 | $5.25 | $13.50 |
| 16 | Tack coat (407E10000) | GAL | 682 | $2.55 | $2.50 |
| 17 | Asphalt concrete surface course, type 1, (448), PG64-22 (441E50000) | CY | 316 | $298.00 | $630.00 |
| 18 | Fog seal (886E11000) | GAL | 817 | $15.00 | $14.00 |
| 19 | Removal of ground mounted sign and reerection (630E85100) | EACH | 2 | $265.00 | $250.00 |
| 20 | Transverse/diagonal line (644E00700) | FT | 62 | $4.20 | $4.00 |
| 21 | Parking lot stall marking (644E01200) | FT | 862 | $4.20 | $4.00 |
| 22 | Lane arrow (644E01300) | EACH | 2 | $105.00 | $100.00 |
| 23 | Lane arrow (644E01300) | EACH | 3 | $105.00 | $100.00 |
| 24 | Handicap symbol marking (644E01600) | EACH | 2 | $240.00 | $225.00 |
| 25 | Removal of pavement marking (644E30000) | FT | 862 | $2.10 | $2.00 |
| 26 | Removal of pavement marking (644E30020) | EACH | 5 | $135.00 | $125.00 |
| 27 | Portable changeable message sign, as per plan (614E18601) | SNMT | 2 | $1,575.00 | $1,500.00 |
| 28 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $2,000.00 | $8,000.00 |
| 29 | Maintaining traffic (614E11000) | LS | 1 | $12,000 | $22,000 |
| 30 | Construction layout stakes and surveying (623E10000) | LS | 1 | $2,500.00 | $2,430.00 |
| 31 | Mobilization (624E10000) | LS | 1 | $14,000 | $43,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of September 25, 2025. Compiled by Mirage Metrics.