ODOT contract 250431 bid tabulation
CLA-PAVE-FY26 (B) (FOUR LANE RESURFACING). Let by Ohio DOT on September 25, 2025, CLA. 3 bids received; low bid $4,772,559 by Shelly Company, -9.1% against the engineer's estimate of $5,248,000.
- Owner
- Ohio DOT
- Letting
- 25 SEP 2025
- Pay items
- 78
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Shelly Company | $4,772,559 | Low | -9.0% |
| 2 | John R Jurgensen Company | $5,469,036 | +15% | +4.0% |
| 3 | Barrett Paving Materials Inc | $7,629,200 | +60% | +45% |
Engineer's estimate: $5,248,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Shelly Company | 2. John R Jurgensen Company | 3. Barrett Paving Materials Inc |
|---|---|---|---|---|---|---|
| 1 | Pavement removed (202E23000) | SY | 224 | $20.00 | $33.46 | $30.00 |
| 2 | Walk removed (202E30000) | SF | 48 | $15.00 | $20.00 | $20.00 |
| 3 | Curb and gutter removed (202E32500) | FT | 500 | $18.00 | $30.00 | $30.00 |
| 4 | Pipe removed, 24" and under (202E35100) | FT | 937 | $10.00 | $16.29 | $2.50 |
| 5 | Excavation (203E10000) | CY | 280 | $55.00 | $75.95 | $45.00 |
| 6 | Embankment (203E20000) | CY | 125 | $40.00 | $50.02 | $45.00 |
| 7 | Subgrade compaction (204E10000) | SY | 812 | $2.00 | $4.16 | $4.00 |
| 8 | 4" concrete walk (608E10000) | SF | 48 | $60.00 | $39.41 | $25.00 |
| 9 | Detectable warning (608E53020) | SF | 16 | $60.00 | $60.00 | $60.00 |
| 10 | Special - mailbox removed and reset (690E50350) | EACH | 1 | $350.00 | $485.03 | $280.00 |
| 11 | Topsoil (659E00300) | CY | 70 | $150.00 | $35.31 | $100.00 |
| 12 | Seeding and mulching, class 2 (659E00510) | SY | 950 | $5.00 | $3.20 | $5.00 |
| 13 | Repair seeding and mulching (659E14000) | SY | 35 | $1.00 | $1.00 | $1.00 |
| 14 | Inter-seeding (659E15000) | SY | 35 | $0.01 | $0.50 | $0.01 |
| 15 | Commercial fertilizer (659E20000) | TON | 0.01 | $1,500.00 | $800.00 | $1,500.00 |
| 16 | Lime (659E31000) | ACRE | 0.14 | $200.00 | $10.00 | $200.00 |
| 17 | Water (659E35000) | MGAL | 4 | $1.00 | $5.00 | $1.00 |
| 18 | 4" base pipe underdrains (605E06000) | FT | 937 | $12.00 | $29.53 | $10.00 |
| 19 | Manhole adjusted to grade (611E99654) | EACH | 12 | $1,250.00 | $1,327.00 | $1,200.00 |
| 20 | Partial depth pavement repair (asphalt concrete base), as per plan (251E01041) | SY | 1,850 | $135.00 | $132.53 | $150.00 |
| 21 | Full depth rigid pavement removal and flexible replacement (252E01000) | SY | 200 | $245.00 | $328.87 | $300.00 |
| 22 | Full depth pavement sawing (252E01500) | FT | 500 | $3.00 | $4.00 | $3.00 |
| 23 | Pavement planing, asphalt concrete, 1 1/2" depth (254E01000) | SY | 362,534 | $1.38 | $1.57 | $3.00 |
| 24 | Pavement planing, asphalt concrete, 3 1/4" depth (254E01000) | SY | 675 | $8.45 | $11.79 | $3.00 |
| 25 | Patching planed surface, as per plan (254E01601) | SY | 500 | $10.00 | $4.57 | $10.00 |
| 26 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 151 | $250.00 | $309.72 | $400.00 |
| 27 | Asphalt concrete base, (449), as per plan, PG64-22 (301E56001) | CY | 3 | $800.00 | $1,435.33 | $1,200.00 |
| 28 | Aggregate base (304E20000) | CY | 123 | $150.00 | $148.74 | $130.00 |
| 29 | Non-tracking tack coat (407E20000) | GAL | 30,873 | $3.00 | $5.00 | $2.00 |
| 30 | Asphalt concrete surface course, type 1, (448), PG70-22M (441E50100) | CY | 15,112 | $200.00 | $213.89 | $330.00 |
| 31 | Asphalt concrete intermediate course, type 1, (448) (441E50200) | CY | 74 | $300.00 | $377.34 | $460.00 |
| 32 | Curb, type 4-C (609E24510) | FT | 500 | $44.00 | $52.05 | $45.00 |
| 33 | Compacted aggregate (617E10100) | CY | 906 | $90.00 | $255.94 | $150.00 |
| 34 | Rumble strips, shoulder (asphalt concrete) (618E40600) | MI | 2.48 | $1,400.00 | $1,400.00 | $2,500.00 |
| 35 | Rumble stripes, center line (asphalt concrete) (618E43000) | MI | 2.44 | $1,400.00 | $1,400.00 | $2,500.00 |
| 36 | Longitudinal joint preparation (874E21000) | MI | 2.44 | $1,500.00 | $3,705.65 | $6,000.00 |
| 37 | RPM (621E00100) | EACH | 1,558 | $32.50 | $32.50 | $32.50 |
| 38 | Raised pavement marker removed (621E54000) | EACH | 1,558 | $4.00 | $11.66 | $5.00 |
| 39 | Edge line, 6", type 1 (642E00104) | MI | 19.51 | $870.00 | $870.00 | $870.00 |
| 40 | Center line, type 1 (642E00300) | MI | 9.73 | $1,130.00 | $1,130.00 | $1,130.00 |
| 41 | Edge line, 6" (644E00104) | MI | 13.47 | $3,500.00 | $3,500.00 | $3,500.00 |
| 42 | Lane line, 6" (644E00204) | MI | 5.93 | $1,175.00 | $1,175.00 | $1,175.00 |
| 43 | Center line (644E00300) | MI | 1.47 | $3,985.00 | $3,985.00 | $3,985.00 |
| 44 | Channelizing line, 8" (644E00400) | FT | 1,831 | $2.60 | $2.60 | $2.60 |
| 45 | Channelizing line, 12" (644E00404) | FT | 5,514 | $2.80 | $2.80 | $2.80 |
| 46 | Stop line (644E00500) | FT | 1,109 | $8.00 | $8.00 | $8.00 |
| 47 | Crosswalk line, 12" (644E00620) | FT | 496 | $4.50 | $4.50 | $4.50 |
| 48 | Crosswalk line, 24" (644E00630) | FT | 80 | $8.00 | $8.00 | $8.00 |
| 49 | Transverse/diagonal line (644E00700) | FT | 1,792 | $8.00 | $8.00 | $8.00 |
| 50 | Island marking (644E00900) | SF | 1,465 | $4.00 | $4.00 | $4.00 |
| 51 | School symbol marking, 96" (644E01110) | EACH | 2 | $800.00 | $800.00 | $800.00 |
| 52 | Lane arrow (644E01300) | EACH | 40 | $95.00 | $95.00 | $95.00 |
| 53 | Wrong way arrow (644E01360) | EACH | 1 | $200.00 | $200.00 | $200.00 |
| 54 | Word on pavement, 96" (644E01410) | EACH | 2 | $500.00 | $500.00 | $200.00 |
| 55 | Dotted line, 6" (644E01510) | FT | 2,526 | $2.00 | $2.00 | $2.00 |
| 56 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 160 | $85.00 | $124.37 | $80.00 |
| 57 | Work zone marking sign (614E12460) | EACH | 78 | $115.00 | $91.80 | $91.80 |
| 58 | Work zone lane line, class III, 6", 642 paint (614E20560) | MI | 11.86 | $510.00 | $510.00 | $510.00 |
| 59 | Work zone center line, class I, 642 paint (614E21100) | MI | 22.30 | $915.00 | $915.00 | $915.00 |
| 60 | Work zone edge line, class I, 6", 642 paint (614E22110) | MI | 24.14 | $660.00 | $660.00 | $660.00 |
| 61 | Work zone channelizing line, class III, 8", 642 paint (614E23680) | FT | 3,598 | $1.30 | $1.30 | $1.30 |
| 62 | Work zone channelizing line, class III, 12", 642 paint (614E23690) | FT | 11,028 | $1.50 | $1.50 | $1.50 |
| 63 | Work zone stop line, class III, 642 paint (614E26610) | FT | 2,220 | $4.50 | $4.50 | $4.50 |
| 64 | Work zone crosswalk line, class III, 12", 642 paint (614E27250) | FT | 160 | $3.50 | $3.50 | $3.50 |
| 65 | Work zone arrow, class III, 642 paint (614E30650) | EACH | 76 | $75.00 | $75.00 | $75.00 |
| 66 | Work zone school symbol marking, 96", class III, 6 (614E31750) | EACH | 4 | $300.00 | $300.00 | $300.00 |
| 67 | Joint sealer, as per plan (516E31001) | FT | 193 | $22.50 | $22.50 | $22.50 |
| 68 | Joint sealer, as per plan (516E31001) | FT | 256 | $22.50 | $22.50 | $22.50 |
| 69 | Patching concrete bridge deck - type B (519E12300) | SY | 5 | $1,350.00 | $1,350.00 | $1,350.00 |
| 70 | Patching concrete bridge deck - type B (519E12300) | SY | 1 | $1,800.00 | $1,800.00 | $1,800.00 |
| 71 | Patching concrete bridge deck - type B (519E12300) | SY | 1 | $1,800.00 | $1,800.00 | $1,800.00 |
| 72 | Joint sealer, as per plan (516E31001) | FT | 47 | $22.50 | $22.50 | $22.50 |
| 73 | Joint sealer, as per plan (516E31001) | FT | 114 | $22.50 | $22.50 | $22.50 |
| 74 | Joint sealer, as per plan (516E31001) | FT | 233 | $22.50 | $22.50 | $22.50 |
| 75 | Premium on railroads' protective public liability and property damage liability insurance (100E00300) | LS | 1 | $2,500.00 | $5,000.00 | $10,000 |
| 76 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $20,000 | $3,768.45 | $25,070 |
| 77 | Maintaining traffic (614E11000) | LS | 1 | $136,000 | $79,989 | $288,000 |
| 78 | Mobilization (624E10000) | LS | 1 | $60,000 | $250,000 | $100,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of September 25, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.