ODOT contract 250427 bid tabulation
ALL-/HAN-IR 75-00.00/14.10 (MICROSURFACING). Let by Ohio DOT on September 25, 2025, ALL. 2 bids received; low bid $3,185,151 by Pavement Maintenance Systems LLC, +9.9% against the engineer's estimate of $2,898,000.
- Owner
- Ohio DOT
- Letting
- 25 SEP 2025
- Pay items
- 30
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Pavement Maintenance Systems LLC | $3,185,151 | Low | +10% |
| 2 | Strawser Construction Inc | $5,874,364 | +84% | +103% |
Engineer's estimate: $2,898,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Pavement Maintenance Systems LLC | 2. Strawser Construction Inc |
|---|---|---|---|---|---|
| 1 | Microsurfacing, surface course, as per plan (421E10011) | SY | 439,581 | $3.15 | $5.50 |
| 2 | Microsurfacing, leveling course, as per plan (421E10021) | SY | 223,725 | $2.68 | $3.00 |
| 3 | RPM (621E00100) | EACH | 1,636 | $36.00 | $45.00 |
| 4 | Raised pavement marker removed (621E54000) | EACH | 1,636 | $23.80 | $65.00 |
| 5 | Removal of pavement marking (643E30000) | FT | 30,783 | $2.70 | $2.70 |
| 6 | Removal of pavement marking (643E30020) | EACH | 3 | $100.00 | $100.00 |
| 7 | Removal of pavement marking (643E30030) | MI | 48.73 | $1,100.00 | $1,100.00 |
| 8 | Lane reduction arrow (644E01350) | EACH | 3 | $175.00 | $175.00 |
| 9 | Wet reflective traffic paint, edge line, 6" (807E10010) | MI | 38.03 | $4,400.00 | $4,400.00 |
| 10 | Wet reflective traffic paint, lane line, 6" (807E10110) | MI | 22.14 | $1,900.00 | $1,900.00 |
| 11 | Wet reflective traffic paint, channelizing line, 1 (807E10310) | FT | 17,915 | $2.50 | $2.50 |
| 12 | Wet reflective traffic paint, dotted line, 6" (807E10410) | FT | 16,195 | $1.00 | $1.00 |
| 13 | Interstate elongated route shield symbol marking, type B125 (814E00010) | EACH | 8 | $4,700.00 | $4,700.00 |
| 14 | Grooving for 6" recessed pavement marking, (asphalt), as per plan (850E10011) | MI | 53.58 | $1,900.00 | $1,900.00 |
| 15 | Grooving for 6" recessed pavement marking, (asphalt) (850E10110) | FT | 16,195 | $0.75 | $0.75 |
| 16 | Grooving for 12" recessed pavement marking, (asphalt) (850E10130) | FT | 17,915 | $1.25 | $1.25 |
| 17 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 120 | $90.00 | $105.00 |
| 18 | Work zone marking sign (614E12460) | EACH | 18 | $106.00 | $105.00 |
| 19 | Work zone increased penalties sign (614E12484) | EACH | 14 | $250.00 | $250.00 |
| 20 | Replacement sign (614E12500) | EACH | 5 | $240.00 | $240.00 |
| 21 | Replacement drum (614E12600) | EACH | 50 | $55.00 | $55.00 |
| 22 | Portable changeable message sign (614E18600) | SNMT | 6 | $1,050.00 | $1,050.00 |
| 23 | Work zone lane line, class I, 6" (614E20010) | MI | 59.28 | $1,400.00 | $1,400.00 |
| 24 | Work zone edge line, class I, 6" (614E22010) | MI | 101.16 | $1,100.00 | $1,100.00 |
| 26 | Work zone channelizing line, class I, 12" (614E23010) | FT | 53,745 | $1.25 | $1.25 |
| 27 | Digital speed limit (DSL) sign assembly (808E18700) | SNMT | 36 | $600.00 | $600.00 |
| 28 | Premium for contract performance bond, payment bond and maintenance bond (103E06000) | LS | 1 | $11,860 | $40,000 |
| 29 | Maintaining traffic (614E11000) | LS | 1 | $136,683 | $870,000 |
| 30 | Mobilization (624E10000) | LS | 1 | $56,300 | $795,540 |
| 100 | Grooving for 6" recessed pavement marking, (concrete) (850E20010) | MI | 2.28 | $3,000.00 | $3,000.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of September 25, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.