ODOT contract 254026 bid tabulation

SAN-SR 523-03.07 Brdg Rehab (BRIDGE REPAIR). Let by Ohio DOT on September 25, 2025, SAN. 4 bids received; low bid $691,224 by Great Lakes Demolition Company, -6.1% against the engineer's estimate of $736,000.

Owner
Ohio DOT
Letting
25 SEP 2025
Pay items
54
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Great Lakes Demolition Company$691,224Low-6.0%
2Crawford Construction Company Inc$771,018+12%+5.0%
3Vernon Nagel Inc$786,337+14%+7.0%
4BCC Ohio Inc$893,369+29%+21%
ODOT contract 254026: bids by rank

Engineer's estimate: $736,000.

Bid tabulation

LinePay itemUnitQuantity1. Great Lakes Demolition Company2. Crawford Construction Company Inc3. Vernon Nagel Inc4. BCC Ohio Inc
1Clearing and grubbing, as per plan (201E11001)LS1$2,000.00$6,000.00$5,000.00$1,548.00
2Pavement removed (202E23000)SY657$20.00$11.00$15.00$8.41
3Guardrail removed for storage, as per plan (202E38101)FT160$4.00$4.60$3.60$3.78
4Anchor assembly removed for storage, type E, as per plan (202E42813)EACH4$200.00$225.00$195.00$204.75
5Bridge terminal assembly removed for storage (202E47100)EACH4$175.00$173.00$150.00$157.50
6Excavation (203E10000)CY161$25.00$46.00$20.00$24.92
7Embankment (203E20000)CY49$20.00$137.00$20.00$25.80
8Subgrade compaction (204E10000)SY1,031$2.00$2.00$1.00$3.19
9Reshaping under guardrail (209E15000)STA8$565.00$52.00$45.00$47.25
10Linear grading (209E60200)STA8$485.00$100.00$100.00$180.60
11Tied concrete block mat with type 2 underlayment (601E21060)SY80$60.00$73.00$100.00$117.41
12Guardrail, type MGS (606E15050)FT225$22.00$24.00$20.40$21.42
13Anchor assembly, MGS type E (606E26150)EACH4$2,600.00$2,800.00$2,435.00$2,556.75
14MGS bridge terminal assembly, type TST-2 (606E34600)EACH4$2,650.00$2,960.00$2,575.00$2,703.75
15Signing, misc.:bridge identification sign (630E95000)LS1$300.00$305.00$265.00$198.45
16Seeding and mulching (659E10000)SY566$5.00$6.35$5.30$5.78
17Commercial fertilizer (659E20000)TON0.06$1,000.00$3,100.00$850.00$997.50
18Erosion control (832E30000)EACH2,000$1.00$1.00$1.00$1.00
19Pavement planing, asphalt CONCRETE1-1/2" (254E01000)SY200$18.00$18.00$7.00$47.25
20Asphalt concrete base, PG64-22, (449) (301E56000)CY125$280.00$317.00$235.00$260.40
21Aggregate base (304E20000)CY173$65.00$84.00$80.00$129.64
22Non-tracking tack coat (407E20000)GAL88$5.00$5.75$1.00$2.68
23Asphalt concrete surface course, type 1, (448), PG64-22 (441E50000)CY81$350.00$397.00$290.00$372.75
24Raised pavement marker removed (621E54000)EACH18$50.00$60.00$12.00$20.84
25Barrier reflector, type 5UNIDIRECTIONAL (626E00116)EACH14$14.00$16.00$13.50$14.18
26Portions of structure removed, as per plan (202E11201)LS1$30,000$74,300$100,000$99,450
27Approach slab removed (202E22900)SY156$50.00$50.00$50.00$94.23
28Wearing course removed (202E23500)SY372$12.00$13.00$10.00$33.60
29Cofferdams and excavation bracing (503E11100)LS1$200.00$2,500.00$1,500.00$8,844.00
30Unclassified excavation, as per plan (503E21301)LS1$8,500.00$8,000.00$6,000.00$5,496.00
31Epoxy coated steel reinforcement (509E10000)LB10,861$1.75$1.80$1.96$1.92
32Dowel holes with nonshrink, nonmetallic grout (510E10000)EACH156$70.00$42.00$29.00$31.49
33Class QC2 concrete, superstructure (511E31610)CY45$1,120.00$1,046.00$1,300.00$1,723.44
34Class QC1 concrete, abutment (511E45710)CY26$825.00$1,050.00$75.00$1,802.34
35Sealing of concrete surfaces (non-epoxy) (512E10050)SY93$20.00$30.00$14.00$19.11
36Prestressed concrete composite box beam bridge members, level 1, CB27-48 (515E12070)EACH7$22,550$24,500$32,200$23,824
371" preformed expansion joint filler (516E13600)SF40$25.00$12.00$12.00$15.75
38Semi-integral abutment expansion joint seal (516E14020)FT66$40.00$43.00$50.00$73.36
39Joint sealer (516E31000)FT66$20.00$26.00$18.00$25.32
40Elastomeric bearing with internal laminates only (neoprene) (516E43100)EACH28$120.00$135.00$130.00$204.75
41Railing (three steel tube bridge railing) (517E70100)FT140$450.00$487.00$444.00$466.20
42Porous backfill with geotextile fabric (518E21200)CY30$70.00$106.00$100.00$142.95
43Special - steel drip strip (518E22300)FT140$15.00$22.00$14.00$32.79
446" perforated corrugated plastic pipe (518E40000)FT100$12.00$13.40$10.00$14.70
456" non-perforated corrugated plastic pipe, including specials, as per plan (518E40011)FT24$20.00$13.40$10.00$20.20
46Patching concrete structure (519E11100)SF156$130.00$75.00$125.00$127.83
47Reinforced concrete approach slabs (T=15") (526E25000)SY156$150.00$391.00$325.00$540.55
48Type A installation (526E90010)FT66$350.00$196.00$260.00$367.50
49Crushed aggregate slope protection (601E20000)SY8$100.00$142.00$35.00$108.56
50Rock channel protection, type C with filter (601E32200)CY35$125.00$127.00$100.00$181.84
51Premium for contract performance bond and for payment bond (103E05000)LS1$6,000.00$9,750.00$9,000.00$11,029
52Maintaining traffic (614E11000)LS1$6,500.00$5,900.00$4,500.00$3,121.80
53Construction layout stakes and surveying (623E10000)LS1$8,500.00$5,400.00$5,000.00$3,390.00
54Mobilization (624E10000)LS1$60,200$36,600$38,000$35,649
ODOT contract 254026: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of September 25, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy