ODOT contract 250453 bid tabulation
BEL-SR 7-18.24 (BRIDGE REPAIR). Let by Ohio DOT on September 25, 2025, BEL. 2 bids received; low bid $789,515 by Evers Steel Construction LLC, +58% against the engineer's estimate of $500,000.
- Owner
- Ohio DOT
- Letting
- 25 SEP 2025
- Pay items
- 20
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Evers Steel Construction LLC | $789,515 | Low | +58% |
| 2 | Vimas Painting Company Inc | $829,994 | +5.0% | +66% |
Engineer's estimate: $500,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Evers Steel Construction LLC | 2. Vimas Painting Company Inc |
|---|---|---|---|---|---|
| 1 | Erosion control (832E30000) | EACH | 1,000 | $1.00 | $1.00 |
| 2 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 240 | $115.00 | $60.00 |
| 3 | Detour signing (614E12420) | LS | 1 | $19,955 | $10,000 |
| 4 | Asphalt concrete for maintaining traffic (614E13000) | CY | 15 | $2,000.00 | $100.00 |
| 5 | Portable changeable message sign, as per plan (614E18601) | SNMT | 12 | $1,214.00 | $500.00 |
| 6 | Portions of structure removed, as per plan (main M (202E11401) | LB | 1,316 | $7.45 | $28.00 |
| 7 | Portions of structure removed, as per plan (second (202E11501) | EACH | 6 | $2,677.00 | $835.00 |
| 8 | Structural steel members, level UF, as per plan (513E10201) | LB | 2,698 | $15.00 | $32.00 |
| 9 | Structural steel, misc.: repair of damaged main ME (513E95000) | FT | 40 | $1,200.00 | $2,000.00 |
| 10 | Structural steel, misc.: repair of damaged seconda (513E95000) | FT | 121 | $96.00 | $800.00 |
| 11 | Field painting of damaged structural steel, as per plan (514E20001) | SF | 424 | $155.00 | $900.00 |
| 12 | Jacking and temporary support of superstructure, as per plan (516E47001) | LS | 1 | $60,000 | $10,000 |
| 13 | Damage assessment (849E10000) | LS | 1 | $15,500 | $5,000.00 |
| 14 | Surface preparation (849E10500) | LS | 1 | $5,500.00 | $10,000 |
| 15 | Repairing damaged members by grinding (849E10600) | HR | 10 | $225.00 | $200.00 |
| 16 | Straightening damaged members (849E10700) | LS | 1 | $138,000 | $10,000 |
| 17 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $21,750 | $12,000 |
| 18 | Maintaining traffic, as per plan (614E11001) | LS | 1 | $109,750 | $20,000 |
| 19 | Field office, type B (619E16010) | MNTH | 3 | $4,500.00 | $500.00 |
| 20 | Mobilization (624E10000) | LS | 1 | $138,470 | $40,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of September 25, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.