ODOT contract 254024 bid tabulation
GRE-CLI Culverts FY26 (CULVERT REPLACEMENT). Let by Ohio DOT on September 25, 2025, GRE. 2 bids received; low bid $382,916 by Axis Civil Construction LLC, +7.0% against the engineer's estimate of $358,000.
- Owner
- Ohio DOT
- Letting
- 25 SEP 2025
- Pay items
- 26
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Axis Civil Construction LLC | $382,916 | Low | +7.0% |
| 2 | Madex Construction Co | $486,307 | +27% | +36% |
Engineer's estimate: $358,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Axis Civil Construction LLC | 2. Madex Construction Co |
|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $15,000 | $8,874.22 |
| 2 | Special - pipe cleanout over 48" (202E70130) | FT | 98 | $150.00 | $81.90 |
| 3 | Cofferdams and excavation bracing, as per plan (503E11101) | LS | 1 | $6,500.00 | $12,718 |
| 4 | Cofferdams and excavation bracing, as per plan (503E11101) | LS | 1 | $6,500.00 | $28,015 |
| 5 | Cofferdams and excavation bracing, as per plan (503E11101) | LS | 1 | $6,500.00 | $16,426 |
| 6 | Fence removed and rebuilt (607E35000) | FT | 50 | $33.46 | $130.41 |
| 7 | Rock channel protection, type B with filter (601E32100) | CY | 9 | $355.00 | $548.79 |
| 8 | Topsoil (659E00300) | CY | 305 | $30.00 | $40.53 |
| 9 | Repair seeding and mulching (659E14000) | SY | 2,750 | $2.50 | $4.05 |
| 10 | Commercial fertilizer (659E20000) | TON | 0.37 | $1,250.00 | $2,315.78 |
| 11 | Lime (659E31000) | ACRE | 0.57 | $150.00 | $1,157.89 |
| 12 | Water (659E35000) | MGAL | 14.90 | $1.00 | $11.58 |
| 13 | Erosion control (832E30000) | EACH | 3,000 | $1.00 | $1.00 |
| 14 | Uncoated steel reinforcement (509E25000) | LB | 283 | $20.00 | $7.45 |
| 15 | Field paving of existing pipe, as per plan, 105" C (611E96551) | FT | 43 | $250.00 | $760.56 |
| 16 | Field paving of existing pipe, as per plan, 60" CM (611E96551) | FT | 228 | $150.00 | $449.11 |
| 17 | Special - grouting voids around corrugated metal pipes (611E96650) | CY | 10 | $1,950.00 | $1,457.38 |
| 18 | Conduit, misc.: CMP repair method A (611E97700) | SF | 225 | $145.00 | $86.84 |
| 19 | Conduit, misc.: CMP repair method B (611E97700) | SF | 20 | $320.00 | $318.42 |
| 20 | Conduit, misc.: CMP repair method C (611E97700) | SF | 25 | $395.00 | $376.32 |
| 21 | Cured-in-place pipe liner, 54" X 36" CMP arch (899E10000) | FT | 55 | $1,850.00 | $1,736.84 |
| 22 | Patching concrete structure (519E11100) | SF | 50 | $235.00 | $231.58 |
| 23 | Patching concrete structures with trowelable mortar (843E50000) | SF | 50 | $235.00 | $243.16 |
| 24 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $5,000.00 | $10,421 |
| 25 | Maintaining traffic (614E11000) | LS | 1 | $20,000 | $24,549 |
| 26 | Mobilization (624E10000) | LS | 1 | $40,000 | $31,268 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of September 25, 2025. Compiled by Mirage Metrics.