ODOT contract 250446 bid tabulation
D03-TSG Radar FY2026 (SIGNALIZATION). Let by Ohio DOT on September 25, 2025, District 3. 6 bids received; low bid $210,145 by Perram Electric Inc, -43% against the engineer's estimate of $370,000.
- Owner
- Ohio DOT
- Letting
- 25 SEP 2025
- Pay items
- 27
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Perram Electric Inc | $210,145 | Low | -43% |
| 2 | Asplundh Construction LLC | $231,000 | +10% | -38% |
| 3 | Miller Cable Company | $259,999 | +24% | -30% |
| 4 | Complete General Construction Company | $266,115 | +27% | -28% |
| 5 | U S Utility Contractor Company | $296,356 | +41% | -20% |
| 6 | Capital Electric Line Builders Inc | $327,618 | +56% | -11% |
Engineer's estimate: $370,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Perram Electric Inc | 2. Asplundh Construction LLC | 3. Miller Cable Company | 4. Complete General Construction Company | 5. U S Utility Contractor Company | 6. Capital Electric Line Builders Inc |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Erosion control (832E30000) | EACH | 2,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 2 | Conduit, 2", 725.04 (625E25400) | FT | 14 | $45.35 | $40.00 | $20.00 | $37.00 | $33.00 | $14.40 |
| 3 | Conduit, 3", 725.04 (625E25500) | FT | 28 | $42.15 | $44.00 | $32.00 | $35.00 | $44.50 | $25.05 |
| 4 | Trench (625E29000) | FT | 42 | $14.95 | $13.00 | $12.00 | $21.00 | $13.20 | $10.03 |
| 5 | Pull box, 725.08, 18" (625E30700) | EACH | 1 | $1,600.00 | $1,394.00 | $1,150.00 | $1,500.00 | $1,115.25 | $1,329.77 |
| 6 | Pull box removed (625E31510) | EACH | 113 | $200.00 | $347.00 | $335.00 | $450.00 | $329.75 | $736.89 |
| 7 | Ground rod (625E32000) | EACH | 1 | $340.00 | $342.00 | $265.00 | $325.00 | $297.50 | $211.19 |
| 8 | Underground warning marking tape (625E36010) | FT | 42 | $1.30 | $2.00 | $2.50 | $2.00 | $2.07 | $1.10 |
| 9 | Vehicular signal head, (LED), 3-section, 12" lens, 1-way, polycarbonate (632E05006) | EACH | 11 | $920.00 | $1,453.00 | $1,325.00 | $1,175.00 | $1,144.00 | $992.13 |
| 10 | Covering of vehicular signal head (632E25000) | EACH | 7 | $10.00 | $130.00 | $40.00 | $38.00 | $18.75 | $6.13 |
| 11 | Signal cable, 5 conductor, no. 14 AWG (632E40500) | FT | 1,660 | $3.52 | $3.00 | $3.50 | $3.05 | $5.14 | $3.45 |
| 12 | Signal cable, 7 conductor, no. 14 AWG (632E40700) | FT | 270 | $3.60 | $4.00 | $3.80 | $3.85 | $5.37 | $3.31 |
| 13 | Signal support foundation (632E64010) | EACH | 1 | $8,460.00 | $6,599.00 | $7,400.00 | $14,000 | $8,062.50 | $11,547 |
| 14 | Pedestal foundation (632E64020) | EACH | 2 | $1,035.00 | $1,759.00 | $1,200.00 | $1,300.00 | $1,488.75 | $2,048.02 |
| 15 | Signal support, type TC-81.22, design 13 (632E72140) | EACH | 1 | $18,400 | $24,000 | $20,100 | $24,000 | $22,550 | $19,748 |
| 16 | Pedestal, 15', transformer base (632E90008) | EACH | 2 | $1,330.00 | $922.00 | $1,100.00 | $2,500.00 | $1,237.50 | $1,778.52 |
| 17 | Removal of miscellaneous traffic signal item for S (632E90020) | EACH | 5 | $545.00 | $437.00 | $475.00 | $625.00 | $672.50 | $401.21 |
| 18 | Removal of traffic signal installation, as per plan (632E90101) | EACH | 13 | $523.00 | $594.00 | $925.00 | $2,050.00 | $1,507.25 | $1,003.02 |
| 19 | Reuse of traffic control item: pull box (632E90104) | EACH | 2 | $320.00 | $322.00 | $500.00 | $260.00 | $307.50 | $862.27 |
| 20 | Signalization, misc.: unlash and relash messenger (632E90500) | FT | 945 | $6.47 | $6.00 | $5.00 | $3.50 | $8.61 | $4.86 |
| 21 | Advance radar detection, as per plan (809E69001) | EACH | 33 | $1,193.00 | $850.00 | $1,425.00 | $1,100.00 | $1,672.50 | $1,003.02 |
| 22 | Stop line radar detection, as per plan (809E69101) | EACH | 36 | $1,113.00 | $850.00 | $1,425.00 | $900.00 | $1,672.50 | $1,003.02 |
| 23 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 192 | $75.00 | $95.00 | $75.00 | $90.00 | $80.50 | $88.00 |
| 24 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $3,997.05 | $1,250.00 | $1,100.00 | $1,500.00 | $4,427.50 | $3,861.00 |
| 25 | Maintaining traffic (614E11000) | LS | 1 | $8,300.00 | $10,070 | $18,523 | $12,000 | $9,225.00 | $9,124.19 |
| 26 | Construction layout stakes and surveying (623E10000) | LS | 1 | $100.00 | $5,506.00 | $3,180.00 | $1,000.00 | $2,875.00 | $4,224.00 |
| 27 | Mobilization (624E10000) | LS | 1 | $10,000 | $16,780 | $7,500.00 | $10,000 | $15,475 | $58,236 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of September 25, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.