ODOT contract 250432 bid tabulation
CLI-Davids Drive Reconstruction (TWO LANE RESURFACING). Let by Ohio DOT on September 25, 2025, CLI. 3 bids received; low bid $1,578,400 by Fillmore Construction, -15% against the engineer's estimate of $1,860,000.
- Owner
- Ohio DOT
- Letting
- 25 SEP 2025
- Pay items
- 77
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Fillmore Construction | $1,578,400 | Low | -15% |
| 2 | Performance Site Development | $1,893,720 | +20% | +2.0% |
| 3 | John R Jurgensen Company | $1,971,593 | +25% | +6.0% |
Engineer's estimate: $1,860,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Fillmore Construction | 2. Performance Site Development | 3. John R Jurgensen Company |
|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $2,500.00 | $29,950 | $500.00 |
| 2 | Pavement removed (202E23000) | SY | 269 | $10.00 | $11.80 | $53.08 |
| 3 | Curb and gutter removed (202E32500) | FT | 675 | $10.00 | $11.00 | $20.92 |
| 4 | Catch basin removed (202E58100) | EACH | 33 | $500.00 | $420.00 | $828.28 |
| 5 | Excavation (203E10000) | CY | 364 | $50.00 | $41.50 | $77.48 |
| 6 | Embankment (203E20000) | CY | 4 | $100.00 | $80.00 | $100.13 |
| 7 | Subgrade compaction (204E10000) | SY | 631 | $3.00 | $5.00 | $5.62 |
| 8 | Excavation of subgrade (204E13000) | CY | 211 | $50.00 | $34.00 | $54.31 |
| 9 | Granular material, type B (204E30010) | CY | 211 | $60.00 | $72.00 | $83.30 |
| 10 | Proof rolling (204E45000) | HR | 1 | $100.00 | $450.00 | $230.81 |
| 11 | Geotextile fabric (204E50000) | SY | 631 | $2.00 | $3.00 | $4.64 |
| 12 | Curb ramp (608E52000) | SF | 457 | $30.00 | $22.00 | $24.82 |
| 13 | Special - consultant for concrete quality control (690E98400) | LS | 1 | $5,000.00 | $12,750 | $9,450.00 |
| 14 | Tied concrete block mat with type 1 underlayment (601E21050) | SY | 4 | $200.00 | $95.00 | $279.57 |
| 15 | Soil analysis test (659E00100) | EACH | 2 | $200.00 | $78.90 | $200.00 |
| 16 | Topsoil (659E00300) | CY | 316 | $30.00 | $68.30 | $35.84 |
| 17 | Seeding and mulching (659E10000) | SY | 2,846 | $1.45 | $2.65 | $1.75 |
| 18 | Repair seeding and mulching (659E14000) | SY | 142 | $2.20 | $2.65 | $1.00 |
| 19 | Inter-seeding (659E15000) | SY | 142 | $2.20 | $2.65 | $0.01 |
| 20 | Commercial fertilizer (659E20000) | TON | 0.41 | $1,400.00 | $800.00 | $1,500.00 |
| 21 | Lime (659E31000) | ACRE | 0.59 | $450.00 | $31.51 | $200.00 |
| 22 | Water (659E35000) | MGAL | 16 | $10.00 | $31.55 | $1.00 |
| 23 | Slope erosion protection (670E00500) | SY | 2,709 | $2.00 | $3.70 | $2.35 |
| 24 | Storm water pollution prevention plan (832E15000) | LS | 1 | $2,500.00 | $3,400.00 | $2,435.00 |
| 25 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $15,000 | $7,750.00 | $2,910.00 |
| 26 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $12,500 | $9,950.00 | $12,362 |
| 27 | Erosion control (832E30000) | EACH | 20,000 | $1.00 | $1.00 | $1.00 |
| 28 | 6" unclassified pipe underdrains (605E13300) | FT | 20 | $20.00 | $36.00 | $36.97 |
| 29 | 6" base pipe underdrains (605E14000) | FT | 366 | $15.00 | $27.00 | $40.78 |
| 30 | 6" conduit, type F for underdrain outlets (611E00510) | FT | 74 | $30.00 | $35.00 | $39.24 |
| 31 | 12" conduit, type B (611E04400) | FT | 130 | $200.00 | $144.00 | $265.77 |
| 32 | 12" conduit, type C (611E04600) | FT | 114 | $100.00 | $110.00 | $225.48 |
| 33 | 18" conduit, type B (611E07400) | FT | 24 | $200.00 | $165.00 | $612.50 |
| 34 | 18" conduit, type C (611E07600) | FT | 40 | $150.00 | $155.00 | $330.91 |
| 35 | 24" conduit, type B (611E10400) | FT | 4 | $300.00 | $320.00 | $559.65 |
| 36 | 24" conduit, type C (611E10600) | FT | 8 | $200.00 | $320.00 | $450.19 |
| 37 | Catch basin, no. 3 (611E98150) | EACH | 11 | $6,000.00 | $3,950.00 | $4,234.44 |
| 38 | Catch basin, no. 3A (611E98180) | EACH | 23 | $4,000.00 | $2,995.00 | $2,985.04 |
| 39 | Manhole, no. 3 (611E99574) | EACH | 1 | $7,500.00 | $3,215.00 | $2,834.66 |
| 40 | Manhole adjusted to grade (611E99654) | EACH | 4 | $1,500.00 | $1,550.00 | $1,391.61 |
| 41 | Precast reinforced concrete outlet (611E99710) | EACH | 2 | $350.00 | $500.00 | $683.32 |
| 42 | Pavement repair (253E02000) | CY | 900 | $200.00 | $375.00 | $477.39 |
| 43 | Pavement planing, asphalt concrete, 3" (254E01000) | SY | 29,978 | $2.00 | $1.75 | $3.23 |
| 44 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 129 | $180.00 | $503.00 | $522.90 |
| 45 | Aggregate base (304E20000) | CY | 174 | $60.00 | $75.00 | $199.11 |
| 46 | Non-tracking tack coat (407E20000) | GAL | 4,612 | $3.00 | $5.30 | $5.00 |
| 47 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 1,068 | $194.00 | $233.00 | $227.87 |
| 48 | Asphalt concrete intermediate course, type 2, (449) (441E70300) | CY | 1,495 | $188.00 | $205.00 | $202.64 |
| 49 | Combination curb and gutter, type 2, as per plan (609E12001) | FT | 727 | $45.00 | $39.00 | $58.38 |
| 50 | Special - 8" water main polyvinyl chloride pipe and fittings (638E20420) | FT | 137 | $230.75 | $155.00 | $281.29 |
| 51 | Special - valve box adjusted to grade (city of wil (638E20500) | EACH | 1 | $50.00 | $500.00 | $1,044.99 |
| 52 | Special - 8" gate valve with valve box (city of WI (638E20554) | EACH | 1 | $1,654.00 | $2,950.00 | $4,673.28 |
| 53 | Special - 12" X 8" tapping sleeve, valve and valve box (638E20708) | EACH | 1 | $6,673.50 | $8,950.00 | $7,733.65 |
| 54 | Special - 6" fire hydrant (city of wilmington spec (638E20750) | EACH | 1 | $7,731.50 | $12,955 | $11,969 |
| 55 | Special - fire hydrant removed and disposed of(cit (638E20760) | EACH | 2 | $75.00 | $1,250.00 | $691.17 |
| 56 | Water work, misc.:8" waterline abandoned (638E98600) | FT | 2,082 | $0.50 | $2.00 | $10.24 |
| 57 | Ground mounted support, no. 3 post (630E03100) | FT | 119.60 | $20.33 | $25.25 | $20.33 |
| 58 | Sign, flat sheet (630E80100) | SF | 52.80 | $23.71 | $33.65 | $23.71 |
| 59 | Removal of ground mounted sign and disposal (630E84900) | EACH | 5 | $16.56 | $10.55 | $16.56 |
| 60 | Removal of ground mounted post support and disposal (630E86002) | EACH | 5 | $22.08 | $15.80 | $22.08 |
| 61 | Center line (644E00300) | MI | 2.49 | $5,055.00 | $4,946.00 | $5,055.00 |
| 62 | Channelizing line, 12" (644E00404) | FT | 936 | $1.70 | $2.65 | $1.70 |
| 63 | Stop line (644E00500) | FT | 56 | $5.85 | $10.55 | $5.85 |
| 64 | Crosswalk line, 12" (644E00620) | FT | 290 | $5.25 | $5.30 | $5.25 |
| 65 | Lane arrow (644E01300) | EACH | 29 | $125.00 | $85.00 | $125.00 |
| 66 | Detour signing (614E12420) | LS | 1 | $5,787.45 | $6,077.00 | $5,787.45 |
| 67 | Portable changeable message sign, as per plan (614E18601) | SNMT | 6 | $1,245.49 | $4,150.00 | $1,245.49 |
| 68 | Work zone center line, class III, 642 paint (614E21550) | MI | 2.75 | $1,515.00 | $2,264.00 | $1,515.00 |
| 69 | Water (616E10000) | MGAL | 1 | $10.00 | $500.00 | $157.43 |
| 70 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $40,000 | $49,985 | $6,386.98 |
| 71 | Maintaining traffic (614E11000) | LS | 1 | $100,000 | $91,500 | $30,427 |
| 72 | Construction layout stakes and surveying (623E10000) | LS | 1 | $20,000 | $34,450 | $5,092.03 |
| 73 | Mobilization (624E10000) | LS | 1 | $100,000 | $112,000 | $87,500 |
| 100 | Pipe removed, 24" and under (202E35100) | FT | 310 | $20.00 | $29.00 | $44.29 |
| 101 | Work zone center line, class I, 642 paint (614E21100) | MI | 2.75 | $2,050.00 | $2,264.00 | $2,050.00 |
| 102 | Work zone edge line, class I, 4", 642 paint (614E22100) | MI | 2.10 | $1,230.00 | $2,277.00 | $1,230.00 |
| 103 | Work zone edge line, class I, 4", 740.06, type I (614E22200) | MI | 1.02 | $10,106 | $10,200 | $10,106 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of September 25, 2025. Compiled by Mirage Metrics.