Lockhart Concrete Co: ODOT bid record

Lockhart Concrete Co submitted 69 bids on Ohio DOT contracts in the data, from 23 JAN 2020 to 18 APR 2024, and was the low bidder on 2 of them (3%). When it was not low, its total sat a median +31% above the low bid.

Owner
Ohio DOT
Low bid volume
$2,425,884
Latest bid
18 APR 2024
Data through
12 NOV 2026
69Bids
2Low bids
3Win rate, percent
+31%Median gap to the low bid when not low, 66 bids

By year

YearBidsLow bidsWin rate
20204025%
20211700%
2022700%
2023300%
2024200%
Lockhart Concrete Co, ODOT: bids and low bids by year of letting

By county

CountyBidsLow bidsWin rate
MED1100%
STA1100%
CUY800%
HUR3133%
SUM300%
COL300%
TRU300%
JEF300%
HOL300%
POR300%
GEA2150%
LOR200%
Lockhart Concrete Co, ODOT: bids and low bids by county

Pay items where it is most often lowest

Pay itemCodeUnitLines bidLowest on the lineIts median priceAll bidders' median
Erosion control832E30000EACH6666 (100%)$1.00$1.00
Aggregate base304E20000CY4431 (70%)$52.50$90.00
Law enforcement officer with patrol car for assistance614E11110HR3322 (67%)$55.00$80.00
Field office, type B619E16010MNTH3720 (54%)$650.00$2,000.00
Concrete masonry602E20000CY3619 (53%)$1,200.00$2,300.00
Epoxy coated steel reinforcement509E10000LB2218 (82%)$1.00$1.75
Sealing of concrete surfaces (epoxy-urethane)512E10100SY1918 (95%)$13.00$34.00
Seeding and mulching659E10000SY4917 (35%)$2.00$2.60
Porous backfill with geotextile fabric518E21200CY2117 (81%)$50.00$125.00
Excavation203E10000CY5815 (26%)$20.00$27.00
Asphalt concrete base, PG64-22301E46000CY4313 (30%)$225.00$235.00
RPM621E00100EACH2813 (46%)$207.50$52.92
Lockhart Concrete Co, ODOT: pay items where its unit price was the lowest on the line

A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.

Who it meets most

Lockhart Concrete Co, ODOT: the firms on the same contracts most often

Latest bids

LetContractCountyProjectRankIts bidAgainst the low bid
18 APR 2024240257MEDMED-SR 57/SR 94-09.78/18.84 (CULVERT REPLACEMENT)7 of 7$1,100,007+98%
11 JAN 2024240018MAHMAH-SR 11-13.30 Noise Wall (NOISE WALLS)3 of 5$2,074,426+5.0%
09 NOV 2023230545MAHMAH-IR 76-03.03 Noise Wall (NOISE WALLS)7 of 7$1,611,737+40%
25 MAY 2023230344MEDMED-SR 301-05.48 (CULVERT REPLACEMENT)4 of 4$457,777+44%
12 JAN 2023230009CUYCUY-IR 480-18.26 Slope (SLIDE REPAIR)4 of 5$407,000+50%
15 DEC 2022220654COLCOL-SR 14-01.42 (CULVERT REPLACEMENT)6 of 6$647,000+39%
26 MAY 2022220340District 4D04-Culverts FY2022 (PART 1 AND PART 2) (CULVERT REPLACEMENT)5 of 6$2,174,070+41%
17 MAR 2022220185STASTA-TR 211-01.97 (Fulton Dr) (BIKEWAYS)2 of 4$2,103,000+2.0%
10 MAR 2022220147MEDMED-SR 57-01.36 (PART 1 AND PART 2) (MINOR RECONSTRUCTION)4 of 4$3,911,789+8.0%
17 FEB 2022220126MEDMED-IR 271 BH FY2022 (BRIDGE REPAIR)4 of 4$245,549+81%
27 JAN 2022220042CUYCUY-Ashton Lane Bridge (BRIDGE REPLACEMENT (1 BRIDGE))3 of 6$748,383+9.0%
27 JAN 2022220060STASTA-SR 43-09.08 Drainage (CULVERT REPLACEMENT)5 of 7$424,220+26%
16 DEC 2021210590STASTA-US 62-24.14 (MAJOR RECONSTRUCTION)8 of 9$16,176,218+18%
16 DEC 2021210666STASTA-SR 172-10.86 (MINOR RECONSTRUCTION)5 of 6$2,384,087+17%
30 SEP 2021210511HOLHOL-SR 520-11.80/12.91 (SLIDE REPAIR)12 of 14$1,595,000+29%
16 SEP 2021210496STASTA-SR 687-03.03 (INTERSECTION)4 of 7$1,289,546+12%
12 AUG 2021210472MEDMED-SR 57-17.65 (CULVERT REPLACEMENT)2 of 11$1,239,237-7.0%
29 JUL 2021210443PORPOR-SR 82-05.84 (INTERSECTION)6 of 6$2,440,000+25%
27 MAY 2021210346MEDMED-SR 94-07.66 (BRIDGE REPLACEMENT (1 BRIDGE))6 of 7$769,700+12%
13 MAY 2021210296CUYCUY-SR 175-07.97 (SPOT PATCHING / PAVEMENT REPAIR)5 of 6$769,000+32%
29 APR 2021210240MEDMED-SR 3-09.04 (INTERSECTION)8 of 8$1,499,027+38%
29 APR 2021214012STASTA-/POR Culverts FY2021 (CULVERT REPLACEMENT)2 of 4$707,601+11%
15 APR 2021210244STASTA-SR 241-09.71 (MINOR RECONSTRUCTION)7 of 7$9,020,425+25%
01 APR 2021210212STASTA-IR 77-01.27 (SLIDE REPAIR)7 of 8$608,286+57%
01 APR 2021210213SUMSUM-IR 77-31.97 (MISCELLANEOUS)7 of 7$849,131+169%
Lockhart Concrete Co: latest ODOT bids in the data

How this record was read

ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

  • Every bid counted here matched its published total to within one dollar; ODOT's rank decides who was low.
  • The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
  • A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.

A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy