Digioia-Suburban Excavating LLC: ODOT bid record
Digioia-Suburban Excavating LLC submitted 45 bids on Ohio DOT contracts in the data, from 23 JAN 2020 to 11 JUL 2024, and was the low bidder on 6 of them (13%). When it was not low, its total sat a median +16% above the low bid.
- Owner
- Ohio DOT
- Low bid volume
- $8,223,273
- Latest bid
- 11 JUL 2024
- Data through
- 12 NOV 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2020 | 4 | 1 | 25% |
| 2021 | 7 | 1 | 14% |
| 2022 | 15 | 2 | 13% |
| 2023 | 12 | 2 | 17% |
| 2024 | 7 | 0 | 0% |
By county
| County | Bids | Low bids | Win rate |
|---|---|---|---|
| MED | 7 | 2 | 29% |
| CUY | 5 | 0 | 0% |
| STA | 5 | 1 | 20% |
| ASD | 4 | 0 | 0% |
| SUM | 3 | 0 | 0% |
| POR | 3 | 0 | 0% |
| GEA | 2 | 0 | 0% |
| HOL | 2 | 0 | 0% |
| District 4 | 2 | 0 | 0% |
| COL | 2 | 0 | 0% |
| WAY | 2 | 1 | 50% |
| MAH | 2 | 0 | 0% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Erosion control | 832E30000 | EACH | 46 | 46 (100%) | $1.00 | $1.00 |
| Aggregate base | 304E20000 | CY | 42 | 18 (43%) | $75.00 | $90.00 |
| Commercial fertilizer | 659E20000 | TON | 48 | 17 (35%) | $877.50 | $850.00 |
| Embankment | 203E20000 | CY | 48 | 13 (27%) | $23.00 | $25.00 |
| Repair seeding and mulching | 659E14000 | SY | 41 | 13 (32%) | $1.00 | $1.25 |
| Lime | 659E31000 | ACRE | 46 | 12 (26%) | $200.00 | $150.00 |
| Inspection well | 611E99720 | EACH | 15 | 10 (67%) | $300.00 | $1,000.00 |
| Excavation | 203E10000 | CY | 49 | 9 (18%) | $25.00 | $27.00 |
| Inter-seeding | 659E15000 | SY | 26 | 8 (31%) | $0.93 | $1.00 |
| Embankment, as per plan | 203E20001 | CY | 16 | 8 (50%) | $17.50 | $47.49 |
| Pavement removed | 202E23000 | SY | 39 | 7 (18%) | $14.50 | $17.00 |
| Removal of ground mounted post support and disposal | 630E86002 | EACH | 30 | 7 (23%) | $30.00 | $23.50 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Eclipse Co LLC | 28 | 16 of 28 |
| Shelly & Sands Inc | 23 | 14 of 23 |
| S E T Inc | 19 | 6 of 19 |
| Karvo Companies Inc | 14 | 8 of 14 |
| Lockhart Concrete Co | 12 | 0 of 12 |
| Marucci & Gaffney Excavating Co | 9 | 5 of 9 |
| Tri-Mor Corp | 8 | 1 of 8 |
| Adena Corporation | 8 | 7 of 8 |
| Fabrizi Trucking & Paving Co Inc | 8 | 2 of 8 |
| Rudzik Excavating Inc | 7 | 4 of 7 |
Latest bids
| Let | Contract | County | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 11 JUL 2024 | 240366 | WAY | WAY-SR 57-06.73 (CULVERT REPLACEMENT) | 5 of 6 | $334,194 | +20% |
| 18 APR 2024 | 240257 | MED | MED-SR 57/SR 94-09.78/18.84 (CULVERT REPLACEMENT) | 3 of 7 | $607,712 | +10% |
| 04 APR 2024 | 240209 | GEA | GEA-West Woods Road Replace (CULVERT REPLACEMENT) | 2 of 3 | $785,597 | +2.0% |
| 21 MAR 2024 | 240187 | SUM | SUM-SR 91-14.49 (CULVERT REPLACEMENT) | 2 of 2 | $907,715 | +15% |
| 21 MAR 2024 | 240199 | MAH | MAH-/POR Culverts FY2024 (CULVERT REPLACEMENT) | 3 of 4 | $780,533 | +13% |
| 22 FEB 2024 | 240124 | ASD | ASD-US 42-14.77 (PART 1 AND PART 2) (INTERSECTION) | 6 of 6 | $4,495,344 | +8.0% |
| 08 FEB 2024 | 240108 | TUS | TUS-Towpath Trail Improvements (BIKEWAYS) | 11 of 14 | $1,103,792 | +54% |
| 28 SEP 2023 | 230472 | MAH | MAH-SR 170-04.35 (MINOR RECONSTRUCTION) | 2 of 6 | $8,235,392 | +3.0% |
| 25 MAY 2023 | 230329 | District 4 | D04-Culverts FY2023 (East) (CULVERT REPLACEMENT) | 4 of 5 | $1,395,602 | +28% |
| 25 MAY 2023 | 230344 | MED | MED-SR 301-05.48 (CULVERT REPLACEMENT) | 3 of 4 | $374,505 | +18% |
| 25 MAY 2023 | 230345 | POR | POR-/STA Culverts FY2023 (CULVERT REPLACEMENT) | 5 of 6 | $963,680 | +25% |
| 27 APR 2023 | 230272 | TRU | TRU-SR 46-01.05 (MISCELLANEOUS) | 1 of 5 | $1,860,662 | Low, 6.0% under the second |
| 09 MAR 2023 | 230144 | CUY | CUY-Wolf Road Intersection (INTERSECTION) | 2 of 4 | $392,388 | +19% |
| 09 MAR 2023 | 230165 | WAY | WAY-US 250-28.64 (CULVERT REPLACEMENT) | 1 of 2 | $120,540 | Low, 82% under the second |
| 23 FEB 2023 | 230131 | SUM | SUM-Wooster Rd/State St (PART 1 AND PART 2) (MINOR RECONSTRUCTION) | 4 of 4 | $3,596,455 | +21% |
| 09 FEB 2023 | 230081 | CUY | CUY-SR 175 Multi-Purpose Trail (SIDEWALK) | 4 of 8 | $755,872 | +9.0% |
| 09 FEB 2023 | 230083 | CUY | CUY-SRTS FY2023 Bay Village (SIDEWALK) | 3 of 5 | $310,995 | +24% |
| 26 JAN 2023 | 230047 | ERI | ERI-SR 4-04.65 (INTERSECTION) | 2 of 4 | $3,217,752 | +34% |
| 12 JAN 2023 | 230029 | CUY | CUY-US 20-03.49 Replace (CULVERT REPLACEMENT) | 5 of 7 | $1,786,052 | +4.0% |
| 15 DEC 2022 | 220653 | COL | COL-East Lincoln St Conn Trail (BIKEWAYS) | 4 of 5 | $1,269,466 | +20% |
| 15 DEC 2022 | 220654 | COL | COL-SR 14-01.42 (CULVERT REPLACEMENT) | 3 of 6 | $496,413 | +6.0% |
| 15 DEC 2022 | 220663 | HOL | HOL-SR 39/SR 754-11.17/00.16,TUS-SR 93-10.80 (CULVERT REPLACEMENT) | 7 of 8 | $2,060,301 | +30% |
| 15 DEC 2022 | 220672 | POR | POR-US 224-09.07 (INTERSECTION) | 4 of 6 | $2,687,853 | +37% |
| 01 DEC 2022 | 220643 | STA | STA-SR 43-20.20 (MINOR RECONSTRUCTION) | 4 of 7 | $1,407,350 | +15% |
| 13 OCT 2022 | 220529 | POR | POR-SR 43-18.65 (MINOR RECONSTRUCTION) | 3 of 7 | $6,448,279 | +9.0% |
How this record was read
ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
- Every bid counted here matched its published total to within one dollar; ODOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.