ODOT letting results, February 23, 2023
29 contracts let by Ohio DOT on February 23, 2023, $126,171,676 in low bids, a median of 3 bidders per contract. On the 29 with an engineer's estimate, the low bid came in under it 18 times; median low bid -3.0% against the estimate.
- Owner
- Ohio DOT
- Contracts
- 29
- Low bids, total
- $126,171,676
- Data through
- 12 NOV 2026
Contracts let that day
| Contract | Project | County | Bids | Low bidder | Low bid | Second bid | Gap | Against estimate | Source |
|---|---|---|---|---|---|---|---|---|---|
| 230039 | MOT-IR 75-14.74 (MAJOR RECONSTRUCTION) | MOT | 2 | John R Jurgensen Company | $51,744,782 | $53,599,000 | +4.0% | +24% | ODOT |
| 230112 | ATH-US 50-17.50 (FOUR LANE RESURFACING) | ATH | 1 | Shelly & Sands Inc | $19,614,464 | +8.0% | ODOT | ||
| 230127 | MOT-SR 4-17.79/18.03 (BRIDGE REPAIR) | MOT | 1 | Complete General Construction Company | $6,664,872 | -10% | ODOT | ||
| 230111 | ATH-US 33-04.38 and Various (MICROSURFACING) | ATH | 1 | Strawser Construction Inc | $4,753,457 | +31% | ODOT | ||
| 230129 | RIC-US 30-00.00 (FOUR LANE RESURFACING) | RIC | 2 | Shelly & Sands Inc | $4,743,992 | $5,823,998 | +23% | -16% | ODOT |
| 230124 | LIC-CR 804-01.73 (BRIDGE REPLACEMENT (1 BRIDGE)) | LIC | 4 | George J Igel & Co Inc | $4,070,982 | $4,269,348 | +5.0% | -4.0% | ODOT |
| 230097 | LAW-SR 93-01.36 Safety (INTERSECTION) | LAW | 2 | Allard Excavation LLC | $3,972,779 | $4,185,677 | +5.0% | +9.0% | ODOT |
| 230134 | D06-PMF FY23 (PAVEMENT MARKING) | District 6 | 2 | The Aero-Mark Company LLC | $3,869,000 | $4,757,294 | +23% | 0.0% | ODOT |
| 230138 | LOR-US 20-13.54 (FOUR LANE RESURFACING) | LOR | 2 | Kokosing Construction Company Inc | $3,859,273 | $4,048,000 | +5.0% | -1.0% | ODOT |
| 230131 | SUM-Wooster Rd/State St (PART 1 AND PART 2) (MINOR RECONSTRUCTION) | SUM | 4 | Kenmore Construction Co Inc | $2,961,921 | $3,122,302 | +5.0% | -18% | ODOT |
| 230119 | FRA-SR 665-09.20 (TWO LANE RESURFACING) | FRA | 3 | Kokosing Construction Company Inc | $2,908,487 | $3,040,324 | +5.0% | -8.0% | ODOT |
| 230125 | MED-SR 94/SR 162-05.36/12.90 (TWO LANE RESURFACING) | MED | 3 | Karvo Companies Inc | $2,576,002 | $2,715,473 | +5.0% | -7.0% | ODOT |
| 233001 | ATB-SR 534-12.06 (BRIDGE REPLACEMENT (1 BRIDGE)) | ATB | 3 | A P O'Horo Company | $1,833,000 | $1,881,073 | +3.0% | -5.0% | ODOT |
| 230118 | D11-CHIP-FY2023 (CHIP SEAL) | District 11 | 3 | Melway Paving Co Inc | $1,767,255 | $2,037,618 | +15% | -1.0% | ODOT |
| 230136 | LOG-SR 287/SR 347-10.99/00.00 (TWO LANE RESURFACING) | LOG | 1 | Shelly Company | $1,691,629 | +6.0% | ODOT | ||
| 230122 | HIG-SR 73/CR 7-00.50/12.11 (PART 1 AND PART 2) (RELOCATION) | HIG | 4 | KT Supply LTD | $1,341,861 | $1,371,510 | +2.0% | -5.0% | ODOT |
| 234007 | CUY-SR 87-15.12 (CULVERT REPLACEMENT) | CUY | 2 | Black Horse Bridge Construction Inc | $1,296,769 | $1,361,351 | +5.0% | +17% | ODOT |
| 234008 | WOO-SR 281-09.37 (BRIDGE REPAIR) | WOO | 1 | BCC Ohio Inc | $1,059,099 | +11% | ODOT | ||
| 230130 | ROS-SR 327-02.47 (CULVERT REPLACEMENT) | ROS | 7 | R C Construction Company and Son Inc | $934,193 | $943,158 | +1.0% | -3.0% | ODOT |
| 230114 | COL-SR 39-20.81 (CULVERT REPLACEMENT) | COL | 3 | Ohio-West Virginia Excavating Co | $798,225 | $853,813 | +7.0% | 0.0% | ODOT |
| 234006 | COS-SR 60-07.62 (BRIDGE REPAIR) | COS | 3 | Buds Inc | $742,992 | $875,484 | +18% | +9.0% | ODOT |
| 230117 | D04-CHIP FY2023 (CHIP SEAL) | District 4 | 3 | Ronyak Paving Inc | $720,780 | $768,472 | +7.0% | 0.0% | ODOT |
| 230133 | D05-CS FY2023 (CRACK SEALING) | District 5 | 5 of 7 | Scodeller Construction Inc | $508,753 | $645,718 | +27% | -23% | ODOT |
| 230126 | MEG-CR 27-03.969 (BRIDGE REPLACEMENT (1 BRIDGE)) | MEG | 4 | Axis Civil Construction LLC | $439,312 | $458,171 | +4.0% | -7.0% | ODOT |
| 234005 | ATH-SR 329-01.00 (SLIDE REPAIR) | ATH | 4 | Alan Stone Co Inc | $421,606 | $447,362 | +6.0% | -20% | ODOT |
| 230135 | D07-GR FY 2023 (GUARDRAIL REBUILDING) | District 7 | 3 | Cuyahoga Fence LLC | $420,031 | $468,532 | +12% | -25% | ODOT |
| 230128 | NOB-SR 821-18.71 (CULVERT REPLACEMENT) | NOB | 8 | Parker Corporation | $195,618 | $211,168 | +8.0% | -23% | ODOT |
| 230132 | D03-LG FY2023(A) (LIGHTING) | District 3 | 2 | Miller Cable Company | $132,800 | $174,975 | +32% | -15% | ODOT |
| 230113 | CLA-Recreational Trl Maintenance (CRACK SEALING) | CLA | 1 | Asphalt Systems Inc | $127,741 | -1.0% | ODOT |
Gap is the second bid over the low bid. Where a contract shows fewer bids than ODOT received, the others did not match their published totals and are left out.