Black Horse Bridge Construction Inc: ODOT bid record

Black Horse Bridge Construction Inc submitted 71 bids on Ohio DOT contracts in the data, from 23 JAN 2020 to 13 AUG 2026, and was the low bidder on 24 of them (34%). When it was not low, its total sat a median +13% above the low bid.

Owner
Ohio DOT
Low bid volume
$31,430,270
Latest bid
13 AUG 2026
Data through
12 NOV 2026
71Bids
24Low bids
34Win rate, percent
+13%Median gap to the low bid when not low, 47 bids

By year

YearBidsLow bidsWin rate
202014429%
202112433%
202213538%
202311545%
20243267%
20259222%
20269222%
Black Horse Bridge Construction Inc, ODOT: bids and low bids by year of letting

By county

CountyBidsLow bidsWin rate
MED9333%
NOB8225%
ASD6467%
MOE6233%
STA6117%
CUY6467%
CAR300%
WAY3267%
TUS3267%
HOL300%
GUE2150%
MRG2150%
Black Horse Bridge Construction Inc, ODOT: bids and low bids by county

Pay items where it is most often lowest

Pay itemCodeUnitLines bidLowest on the lineIts median priceAll bidders' median
Erosion control832E30000EACH7070 (100%)$1.00$1.00
Water659E35000MGAL6858 (85%)$1.00$1.00
Commercial fertilizer659E20000TON6630 (45%)$767.50$850.00
Seeding and mulching659E10000SY5925 (42%)$3.00$2.60
Porous backfill with geotextile fabric518E21200CY5822 (38%)$122.00$125.00
Lime659E31000ACRE6521 (32%)$160.00$150.00
Guardrail, type MGS606E15050FT4421 (48%)$20.60$22.73
Guardrail removed202E38000FT4820 (42%)$2.00$2.50
Tack coat407E10000GAL3719 (51%)$3.30$3.25
Anchor assembly, MGS type T606E26550EACH3419 (56%)$1,330.00$1,260.00
Asphalt concrete base, PG64-22, (449)301E56000CY2419 (79%)$280.00$300.00
Field office, type B619E16010MNTH3518 (51%)$1,000.00$2,000.00
Black Horse Bridge Construction Inc, ODOT: pay items where its unit price was the lowest on the line

A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.

Who it meets most

Black Horse Bridge Construction Inc, ODOT: the firms on the same contracts most often

Latest bids

LetContractCountyProjectRankIts bidAgainst the low bid
13 AUG 2026260371SUMSUM-SR 21-01.07 (BRIDGE REPAIR)6 of 9$2,347,540+25%
09 APR 2026260183STASTA-Sippo Valley Trail Bridge 8 (BRIDGE REPLACEMENT (1 BRIDGE))4 of 5$864,336+16%
12 MAR 2026260098SUMSUM-SR 91-07.89 (BRIDGE REPAIR)1 of 3$2,188,488Low, 13% under the second
19 FEB 2026260099TUSTUS-W. 3rd Street Bridge (BRIDGE REPAIR)1 of 4$1,626,062Low, 17% under the second
19 FEB 2026264006WAYWAY-CULVERT FY2026 (CULVERT REPLACEMENT)2 of 3$1,114,791+27%
29 JAN 2026260060MOEMOE-TR 2214-00.06 (BRIDGE REPLACEMENT (1 BRIDGE))3 of 5$1,012,581+10%
29 JAN 2026260074HOLHOL-SR 179-03.89 (BRIDGE REPAIR)2 of 5$1,360,160+26%
15 JAN 2026264001CUYCUY-SR 82-00.93 (CULVERT REPLACEMENT)3 of 5$682,628+1.0%
15 JAN 2026264002HOLHOL-SR 39-00.25 (CULVERT REPLACEMENT)6 of 7$542,540+52%
18 DEC 2025250593MOEMOE-TR 1004-02.27 (BRIDGE REPLACEMENT (1 BRIDGE))2 of 6$1,315,052+9.0%
04 DEC 2025250563MEDMED-US 42-09.45 (BRIDGE REPAIR)3 of 8$818,448+3.0%
13 NOV 2025250532NOBNOB-SR 78-01.08 / NOB-SR 83-00.02 (BRIDGE REPAIR)5 of 7$1,911,546+15%
23 OCT 2025250503MRGMRG-SR 555-23.05 (BRIDGE REPLACEMENT (1 BRIDGE))1 of 4$1,381,825Low, 5.0% under the second
25 SEP 2025250441PORPOR-SR 305-02.43/02.58 (BRIDGE REPAIR)6 of 9$1,349,493+11%
25 SEP 2025254025NOBNOB-SR 147-16.82 (CULVERT REPLACEMENT)3 of 4$612,365+7.0%
24 APR 2025250227STASTA-Minerva Bridge (BIKEWAYS)1 of 3$738,873Low, 2.0% under the second
10 APR 2025250196NOBNOB-Mill St.-00.07 (BRIDGE REPLACEMENT (1 BRIDGE))2 of 6$888,470+15%
10 APR 2025250200STASTA-Sippo Valley Trail Bridge 11 (CULVERT REPLACEMENT)3 of 5$383,785+16%
14 NOV 2024240510CUYCUY-SR 14-12.12E (PART 1 AND PART 2) (BRIDGE REPLACEMENT (1 BRIDGE))1 of 2$4,861,699Low, 9.0% under the second
22 FEB 2024240148NOBNOB-SR 513-09.17 (BRIDGE REPLACEMENT (1 BRIDGE))1 of 4$1,381,825Low, 5.0% under the second
11 JAN 2024244001CUYCUY-US 422-09.59 Culvert (CULVERT REPLACEMENT)4 of 4$1,199,794+14%
26 OCT 2023230480WAYWAY-US 250-17.27 (BRIDGE REPLACEMENT (1 BRIDGE))1 of 2$1,678,081Low, 8.0% under the second
26 OCT 2023234024TRUTRU-SR 5-11.95 Slide (SLIDE REPAIR)2 of 2$556,739+7.0%
12 OCT 2023230483ASDASD-US 42-12.46 (BRIDGE REPAIR)1 of 4$967,353Low, 2.0% under the second
28 SEP 2023230479RICRIC-SR 96-16.58 (BRIDGE REPLACEMENT (1 BRIDGE))1 of 8$2,354,986Low, 7.0% under the second
Black Horse Bridge Construction Inc: latest ODOT bids in the data

How this record was read

ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

  • Every bid counted here matched its published total to within one dollar; ODOT's rank decides who was low.
  • The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
  • A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.

A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy