ODOT contract 250503 bid tabulation
MRG-SR 555-23.05 (BRIDGE REPLACEMENT (1 BRIDGE)). Let by Ohio DOT on October 23, 2025, MRG. 4 bids received; low bid $1,381,825 by Black Horse Bridge Construction Inc, -11% against the engineer's estimate of $1,550,000.
- Owner
- Ohio DOT
- Letting
- 23 OCT 2025
- Pay items
- 68
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Black Horse Bridge Construction Inc | $1,381,825 | Low | -11% |
| 2 | Shelly & Sands Inc | $1,451,279 | +5.0% | -6.0% |
| 3 | George J Igel & Co Inc | $1,499,994 | +9.0% | -3.0% |
| 4 | Complete General Construction Company | $1,750,199 | +27% | +13% |
Engineer's estimate: $1,550,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Black Horse Bridge Construction Inc | 2. Shelly & Sands Inc | 3. George J Igel & Co Inc | 4. Complete General Construction Company |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $8,800.00 | $2,000.00 | $5,000.00 | $7,000.00 |
| 2 | Guardrail removed (202E38000) | FT | 158 | $2.00 | $7.00 | $5.00 | $10.00 |
| 3 | Removal misc.: test and cap gas lines (202E98100) | EACH | 2 | $3,400.00 | $2,500.00 | $1,500.00 | $3,000.00 |
| 4 | Excavation (203E10000) | CY | 571 | $46.00 | $30.00 | $30.00 | $40.00 |
| 5 | Embankment (203E20000) | CY | 40 | $36.00 | $21.00 | $42.00 | $10.00 |
| 6 | Subgrade compaction (204E10000) | SY | 509 | $4.50 | $8.00 | $5.00 | $9.00 |
| 7 | Preparing subgrade for shoulder paving (209E72000) | STA | 9 | $850.00 | $350.00 | $195.00 | $300.00 |
| 8 | Guardrail, type MGS (606E15050) | FT | 237.50 | $44.00 | $21.50 | $22.00 | $41.38 |
| 9 | Anchor assembly, MGS type A (606E25550) | EACH | 3 | $1,750.00 | $1,500.00 | $1,650.00 | $1,700.00 |
| 10 | Anchor assembly, MGS type T (606E26550) | EACH | 1 | $1,150.00 | $1,200.00 | $1,400.00 | $1,050.00 |
| 11 | MGS bridge terminal assembly, type TST-2 (606E34600) | EACH | 4 | $2,250.00 | $2,600.00 | $2,750.00 | $2,100.00 |
| 12 | Rock channel protection, type B with filter (601E32100) | CY | 372 | $110.00 | $55.00 | $90.00 | $95.00 |
| 13 | Seeding and mulching (659E10000) | SY | 1,503 | $4.00 | $1.70 | $4.50 | $1.70 |
| 14 | Commercial fertilizer (659E20000) | TON | 0.14 | $900.00 | $1,250.00 | $1,250.00 | $1,250.00 |
| 15 | Lime (659E31000) | ACRE | 0.31 | $200.00 | $150.00 | $150.00 | $150.00 |
| 16 | Water (659E35000) | MGAL | 4 | $1.00 | $1.00 | $1.00 | $1.00 |
| 17 | Erosion control (832E30000) | EACH | 2,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 18 | Aggregate drains (605E31100) | FT | 137 | $28.00 | $20.00 | $55.00 | $15.00 |
| 19 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 72 | $495.00 | $610.00 | $696.00 | $495.00 |
| 20 | Aggregate base (304E20000) | CY | 109 | $120.00 | $140.00 | $95.00 | $95.00 |
| 21 | Non-tracking tack coat (407E20000) | GAL | 138 | $4.50 | $3.30 | $3.89 | $4.50 |
| 22 | Prime coat (408E10000) | GAL | 81 | $7.00 | $8.04 | $23.95 | $7.00 |
| 23 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 68 | $435.00 | $725.00 | $629.20 | $435.00 |
| 24 | Compacted aggregate (617E10100) | CY | 14 | $134.00 | $108.00 | $325.00 | $150.00 |
| 25 | Raised pavement marker removed (621E54000) | EACH | 7 | $200.00 | $14.00 | $50.00 | $50.00 |
| 26 | Barrier reflector, type 2 (bidirectional) (626E00110) | EACH | 9 | $11.00 | $12.00 | $25.00 | $11.00 |
| 27 | Sign, flat sheet (630E80100) | SF | 1 | $40.00 | $50.00 | $305.00 | $40.00 |
| 28 | Removal of ground mounted sign and disposal (630E84900) | EACH | 1 | $15.00 | $25.00 | $140.00 | $15.00 |
| 29 | Removal of ground mounted sign and reerection (630E85100) | EACH | 6 | $50.00 | $100.00 | $95.00 | $50.00 |
| 30 | Removal of ground mounted post support and reerection (630E86010) | EACH | 7 | $50.00 | $225.00 | $125.00 | $50.00 |
| 31 | Edge line, 6", type 1 (642E00104) | MI | 0.24 | $4,025.00 | $4,025.00 | $4,025.00 | $4,025.00 |
| 32 | Center line, type 1 (642E00300) | MI | 0.12 | $7,550.00 | $7,550.00 | $7,550.00 | $7,550.00 |
| 33 | Work zone impact attenuator, 24" wide hazards, (bidirectional) (614E12384) | EACH | 4 | $2,000.00 | $2,200.00 | $2,800.00 | $2,520.00 |
| 34 | Work zone lighting system (614E12740) | EACH | 1 | $32,000 | $31,000 | $2,000.00 | $50,000 |
| 35 | Barrier reflector, type 1 (bidirectional) (614E13310) | EACH | 30 | $15.00 | $9.00 | $40.00 | $36.00 |
| 36 | Object marker, two way (614E13360) | EACH | 30 | $20.00 | $17.00 | $42.00 | $38.00 |
| 37 | Work zone edge line, class I, 4" (614E22000) | MI | 0.44 | $10,550 | $4,250.00 | $4,250.00 | $4,250.00 |
| 38 | Work zone stop line, class I (614E26000) | FT | 20 | $14.00 | $14.00 | $14.00 | $14.00 |
| 39 | Roads for maintaining traffic (615E10000) | LS | 1 | $3,000.00 | $4,700.00 | $9,000.00 | $18,000 |
| 40 | Pavement for maintaining traffic, class A, as per plan (615E20001) | SY | 180 | $175.00 | $231.00 | $180.00 | $135.00 |
| 41 | Portable barrier, unanchored (622E41100) | FT | 600 | $39.00 | $19.00 | $28.00 | $33.75 |
| 42 | Portable barrier, anchored (622E41110) | FT | 96 | $43.00 | $60.00 | $57.00 | $40.00 |
| 43 | Structure removed, over 20 foot span, as per plan (202E11003) | LS | 1 | $64,860 | $85,600 | $85,000 | $165,000 |
| 44 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $31,600 | $54,000 | $41,575 | $80,000 |
| 45 | Unclassified excavation (503E21300) | LS | 1 | $30,800 | $40,000 | $45,000 | $65,000 |
| 46 | Steel piles HP10X42, furnished (507E00100) | FT | 240 | $40.00 | $28.76 | $55.00 | $35.00 |
| 47 | Steel piles HP12X53, furnished (507E00200) | FT | 420 | $46.00 | $35.48 | $67.00 | $40.00 |
| 48 | Special - pile encasement (507E71200) | FT | 142 | $200.00 | $230.00 | $165.00 | $195.00 |
| 49 | Prebored holes, as per plan (507E92201) | FT | 507 | $160.00 | $165.00 | $225.00 | $175.00 |
| 50 | Epoxy coated steel reinforcement (509E10000) | LB | 55,617 | $2.00 | $1.97 | $2.00 | $2.00 |
| 51 | Class QC2 concrete, superstructure (511E33310) | CY | 203 | $1,475.00 | $1,398.00 | $1,405.00 | $1,750.00 |
| 52 | Class QC1 concrete, abutment including footing (511E43510) | CY | 60 | $1,050.00 | $1,650.00 | $1,105.00 | $1,500.00 |
| 53 | Sealing of concrete surfaces (non-epoxy) (512E10050) | SY | 99 | $50.00 | $20.00 | $20.00 | $20.00 |
| 54 | 1/2" preformed expansion joint filler (516E13200) | SF | 55 | $10.00 | $4.00 | $9.00 | $15.00 |
| 55 | 1" preformed expansion joint filler (516E13600) | SF | 80 | $14.00 | $6.00 | $10.00 | $20.00 |
| 56 | Nylon reinforced neoprene sheeting (516E25000) | SF | 374 | $15.00 | $18.00 | $13.00 | $18.00 |
| 57 | Railing (three steel tube bridge railing) (517E70100) | FT | 208 | $476.00 | $445.00 | $465.00 | $455.00 |
| 58 | Porous backfill with geotextile fabric (518E21200) | CY | 51 | $120.00 | $170.00 | $175.00 | $175.00 |
| 59 | Special - steel drip strip (518E22300) | FT | 226.58 | $25.00 | $16.00 | $18.00 | $16.00 |
| 60 | 6" perforated corrugated plastic pipe (518E40000) | FT | 102 | $14.00 | $7.00 | $12.00 | $12.00 |
| 61 | 6" non-perforated corrugated plastic pipe, including specials (518E40010) | FT | 76 | $18.00 | $7.00 | $28.00 | $15.00 |
| 62 | Reinforced concrete approach slabs (T=15"), as per plan (526E25001) | SY | 167 | $525.00 | $480.00 | $485.00 | $495.00 |
| 63 | Type A installation (526E90010) | FT | 66 | $210.00 | $185.00 | $330.00 | $350.00 |
| 64 | Polymer modified asphalt expansion joint system (846E00110) | CF | 28 | $600.00 | $765.00 | $616.45 | $616.45 |
| 65 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $11,000 | $8,115.00 | $7,500.00 | $12,000 |
| 66 | Maintaining traffic (614E11000) | LS | 1 | $9,500.00 | $7,095.00 | $47,500 | $60,000 |
| 67 | Construction layout stakes and surveying (623E10000) | LS | 1 | $12,000 | $20,000 | $20,000 | $15,000 |
| 68 | Mobilization (624E10000) | LS | 1 | $40,000 | $72,606 | $70,000 | $87,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of October 23, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.