ODOT letting results, January 29, 2026
33 contracts let by Ohio DOT on January 29, 2026, $118,781,408 in low bids, a median of 3 bidders per contract. On the 32 with an engineer's estimate, the low bid came in under it 25 times; median low bid -12% against the estimate.
- Owner
- Ohio DOT
- Contracts
- 33
- Low bids, total
- $118,781,408
- Data through
- 12 NOV 2026
Contracts let that day
| Contract | Project | County | Bids | Low bidder | Low bid | Second bid | Gap | Against estimate | Source |
|---|---|---|---|---|---|---|---|---|---|
| 260002 | HEN-US 6/US 24-11.32/04.62 (MAJOR RECONSTRUCTION) | HEN | 3 | E S Wagner - Vernon Nagel Joint Venture | $58,367,958 | $59,336,765 | +2.0% | +7.0% | ODOT |
| 260001 | CUY-IR 71-10.07 SW Replace | CUY | 3 | Ruhlin Company | $10,971,781 | $13,286,572 | +21% | ODOT | |
| 260045 | CAR-SR 39-23.34 (MINOR RECONSTRUCTION) | CAR | 3 | Shelly Company | $5,386,146 | $5,514,583 | +2.0% | -5.0% | ODOT |
| 260064 | POR-SR 14/VAR-01.74/VAR (PART 1) (MINOR RECONSTRUCTION) | POR | 2 | Karvo Companies Inc | $5,243,877 | $6,283,380 | +20% | -10% | ODOT |
| 260055 | LAK-IR 90-08.77 VSL Signs (SIGNALIZATION) | LAK | 2 | Perram Electric Inc | $4,123,000 | $4,799,760 | +16% | +26% | ODOT |
| 260070 | D03-PM FY2026 (PAVEMENT MARKING) | District 3 | 3 | Alpha Space Control LLC | $3,885,838 | $4,200,000 | +8.0% | -21% | ODOT |
| 260050 | CLI-IR 71-04.23 (FOUR LANE RESURFACING) | CLI | 2 | John R Jurgensen Company | $3,294,350 | $3,557,341 | +8.0% | +10% | ODOT |
| 260048 | CLE-SR 125-08.95 (FOUR LANE RESURFACING) | CLE | 2 | John R Jurgensen Company | $2,820,429 | $3,057,046 | +8.0% | +5.0% | ODOT |
| 260066 | PRE-MR 112-00.99 N Maple Ph 2 (MINOR RECONSTRUCTION) | PRE | 6 | Brumbaugh Construction Inc | $2,438,718 | $2,526,468 | +4.0% | -19% | ODOT |
| 260063 | PIK-SR 32-09.27/09.96 (Safety) (INTERSECTION) | PIK | 4 | Shelly & Sands Inc | $2,231,803 | $2,470,683 | +11% | -12% | ODOT |
| 260067 | WAS-IR 77-09.58 (MISCELLANEOUS) | WAS | 4 | Shelly & Sands Inc | $2,209,192 | $2,559,458 | +16% | -16% | ODOT |
| 260068 | WAS-SR 7-52.79 (BRIDGE REPAIR) | WAS | 2 | Shelly & Sands Inc | $1,892,916 | $1,946,495 | +3.0% | -10% | ODOT |
| 260042 | ATH-SR 56-00.90 (MINOR RECONSTRUCTION) | ATH | 6 | Alan Stone Co Inc | $1,732,297 | $1,781,877 | +3.0% | -19% | ODOT |
| 260056 | LAK-SR 174-00.00 (TWO LANE RESURFACING) | LAK | 8 | Karvo Companies Inc | $1,727,326 | $1,729,867 | 0.0% | -7.0% | ODOT |
| 260058 | LAW-SR 775-08.77 (SLIDE REPAIR) | LAW | 2 | Axis Civil Construction LLC | $1,185,492 | $1,353,953 | +14% | +25% | ODOT |
| 260057 | LAK-SR 84/VAR-18.21/VAR (TWO LANE RESURFACING) | LAK | 7 | Geauga Highway Co | $1,126,236 | $1,269,234 | +13% | -32% | ODOT |
| 260074 | HOL-SR 179-03.89 (BRIDGE REPAIR) | HOL | 5 | V O Menuez & Son Inc | $1,079,430 | $1,360,160 | +26% | -37% | ODOT |
| 260060 | MOE-TR 2214-00.06 (BRIDGE REPLACEMENT (1 BRIDGE)) | MOE | 5 | Shelly & Sands Inc | $921,024 | $965,863 | +5.0% | 0.0% | ODOT |
| 260073 | D09-GR-FY2026 (GUARDRAIL REBUILDING) | District 9 | 3 | PDK Construction Inc | $915,499 | $1,024,725 | +12% | -7.0% | ODOT |
| 260059 | MER-FT RECOVERY SIDEWALKS SA22 (SIDEWALK) | MER | 4 | Jutte Excavating Inc | $888,655 | $1,012,635 | +14% | -11% | ODOT |
| 260043 | BUT-SR 73-16.05 (TWO LANE RESURFACING) | BUT | 3 | Fillmore Construction | $878,414 | $917,530 | +4.0% | -13% | ODOT |
| 260061 | MOT-IR 75-10.44 & 10.78 (BRIDGE REPAIR) | MOT | 4 | Ram Construction Services of Michigan, Inc | $817,615 | $1,044,044 | +28% | -32% | ODOT |
| 264003 | WIL-SR 34-27.22 Bridge Repair (BRIDGE REPAIR) | WIL | 2 | Vernon Nagel Inc | $576,218 | $602,207 | +5.0% | -8.0% | ODOT |
| 260049 | CLE-SR 132-12.64 (BRIDGE REPAIR) | CLE | 5 | Complete General Construction Company | $568,754 | $583,081 | +3.0% | -17% | ODOT |
| 260062 | PER-MR 56-00.13 (Buckeye Street) (BRIDGE REPLACEMENT (1 BRIDGE)) | PER | 7 | J & J Bridge Company Inc | $559,634 | $563,136 | +1.0% | -10% | ODOT |
| 260054 | JEF-US 22-06.99 (SLIDE REPAIR) | JEF | 8 | Tucson Inc | $507,909 | $544,820 | +7.0% | -12% | ODOT |
| 260044 | BUT-/HAM CS FY2026 (CRACK SEALING) | BUT | 3 | Scodeller Construction Inc | $474,792 | $627,200 | +32% | -37% | ODOT |
| 260071 | D06-RPM-FY2026 (RAISED PAVEMENT MARKERS) | District 6 | 3 | W L Markers Inc | $463,597 | $502,354 | +8.0% | -14% | ODOT |
| 260046 | CHP-SR 55-15.02 (TWO LANE RESURFACING) | CHP | 3 | A & B Asphalt Corporation | $461,961 | $474,400 | +3.0% | -13% | ODOT |
| 260072 | D09-PM FY2026 (A) (PAVEMENT MARKING) | District 9 | 4 | The Aero-Mark Company LLC | $376,000 | $438,847 | +17% | -32% | ODOT |
| 260051 | CUY-Greenhurst Drive Bridge Demo (MISCELLANEOUS) | CUY | 5 | Daniel R Schmoldt Enterprises Inc | $333,889 | $343,565 | +3.0% | -14% | ODOT |
| 260069 | ASD-Mohican State Park FY2026 (BRIDGE REPAIR) | ASD | 3 | Ohio Concrete Maintenance LLC | $246,052 | $249,331 | +1.0% | -14% | ODOT |
| 260075 | LIC-IR 70-01.95 (NOISE WALLS) | LIC | 5 | Axis Civil Construction LLC | $74,605 | $76,408 | +2.0% | +17% | ODOT |
Gap is the second bid over the low bid. Where a contract shows fewer bids than ODOT received, the others did not match their published totals and are left out. Each contract number opens its full bid tabulation.