ODOT letting results, January 29, 2026

33 contracts let by Ohio DOT on January 29, 2026, $118,781,408 in low bids, a median of 3 bidders per contract. On the 32 with an engineer's estimate, the low bid came in under it 25 times; median low bid -12% against the estimate.

Owner
Ohio DOT
Contracts
33
Low bids, total
$118,781,408
Data through
12 NOV 2026

Contracts let that day

ContractProjectCountyBidsLow bidderLow bidSecond bidGapAgainst estimateSource
260002HEN-US 6/US 24-11.32/04.62 (MAJOR RECONSTRUCTION)HEN3E S Wagner - Vernon Nagel Joint Venture$58,367,958$59,336,765+2.0%+7.0%ODOT
260001CUY-IR 71-10.07 SW ReplaceCUY3Ruhlin Company$10,971,781$13,286,572+21%ODOT
260045CAR-SR 39-23.34 (MINOR RECONSTRUCTION)CAR3Shelly Company$5,386,146$5,514,583+2.0%-5.0%ODOT
260064POR-SR 14/VAR-01.74/VAR (PART 1) (MINOR RECONSTRUCTION)POR2Karvo Companies Inc$5,243,877$6,283,380+20%-10%ODOT
260055LAK-IR 90-08.77 VSL Signs (SIGNALIZATION)LAK2Perram Electric Inc$4,123,000$4,799,760+16%+26%ODOT
260070D03-PM FY2026 (PAVEMENT MARKING)District 33Alpha Space Control LLC$3,885,838$4,200,000+8.0%-21%ODOT
260050CLI-IR 71-04.23 (FOUR LANE RESURFACING)CLI2John R Jurgensen Company$3,294,350$3,557,341+8.0%+10%ODOT
260048CLE-SR 125-08.95 (FOUR LANE RESURFACING)CLE2John R Jurgensen Company$2,820,429$3,057,046+8.0%+5.0%ODOT
260066PRE-MR 112-00.99 N Maple Ph 2 (MINOR RECONSTRUCTION)PRE6Brumbaugh Construction Inc$2,438,718$2,526,468+4.0%-19%ODOT
260063PIK-SR 32-09.27/09.96 (Safety) (INTERSECTION)PIK4Shelly & Sands Inc$2,231,803$2,470,683+11%-12%ODOT
260067WAS-IR 77-09.58 (MISCELLANEOUS)WAS4Shelly & Sands Inc$2,209,192$2,559,458+16%-16%ODOT
260068WAS-SR 7-52.79 (BRIDGE REPAIR)WAS2Shelly & Sands Inc$1,892,916$1,946,495+3.0%-10%ODOT
260042ATH-SR 56-00.90 (MINOR RECONSTRUCTION)ATH6Alan Stone Co Inc$1,732,297$1,781,877+3.0%-19%ODOT
260056LAK-SR 174-00.00 (TWO LANE RESURFACING)LAK8Karvo Companies Inc$1,727,326$1,729,8670.0%-7.0%ODOT
260058LAW-SR 775-08.77 (SLIDE REPAIR)LAW2Axis Civil Construction LLC$1,185,492$1,353,953+14%+25%ODOT
260057LAK-SR 84/VAR-18.21/VAR (TWO LANE RESURFACING)LAK7Geauga Highway Co$1,126,236$1,269,234+13%-32%ODOT
260074HOL-SR 179-03.89 (BRIDGE REPAIR)HOL5V O Menuez & Son Inc$1,079,430$1,360,160+26%-37%ODOT
260060MOE-TR 2214-00.06 (BRIDGE REPLACEMENT (1 BRIDGE))MOE5Shelly & Sands Inc$921,024$965,863+5.0%0.0%ODOT
260073D09-GR-FY2026 (GUARDRAIL REBUILDING)District 93PDK Construction Inc$915,499$1,024,725+12%-7.0%ODOT
260059MER-FT RECOVERY SIDEWALKS SA22 (SIDEWALK)MER4Jutte Excavating Inc$888,655$1,012,635+14%-11%ODOT
260043BUT-SR 73-16.05 (TWO LANE RESURFACING)BUT3Fillmore Construction$878,414$917,530+4.0%-13%ODOT
260061MOT-IR 75-10.44 & 10.78 (BRIDGE REPAIR)MOT4Ram Construction Services of Michigan, Inc$817,615$1,044,044+28%-32%ODOT
264003WIL-SR 34-27.22 Bridge Repair (BRIDGE REPAIR)WIL2Vernon Nagel Inc$576,218$602,207+5.0%-8.0%ODOT
260049CLE-SR 132-12.64 (BRIDGE REPAIR)CLE5Complete General Construction Company$568,754$583,081+3.0%-17%ODOT
260062PER-MR 56-00.13 (Buckeye Street) (BRIDGE REPLACEMENT (1 BRIDGE))PER7J & J Bridge Company Inc$559,634$563,136+1.0%-10%ODOT
260054JEF-US 22-06.99 (SLIDE REPAIR)JEF8Tucson Inc$507,909$544,820+7.0%-12%ODOT
260044BUT-/HAM CS FY2026 (CRACK SEALING)BUT3Scodeller Construction Inc$474,792$627,200+32%-37%ODOT
260071D06-RPM-FY2026 (RAISED PAVEMENT MARKERS)District 63W L Markers Inc$463,597$502,354+8.0%-14%ODOT
260046CHP-SR 55-15.02 (TWO LANE RESURFACING)CHP3A & B Asphalt Corporation$461,961$474,400+3.0%-13%ODOT
260072D09-PM FY2026 (A) (PAVEMENT MARKING)District 94The Aero-Mark Company LLC$376,000$438,847+17%-32%ODOT
260051CUY-Greenhurst Drive Bridge Demo (MISCELLANEOUS)CUY5Daniel R Schmoldt Enterprises Inc$333,889$343,565+3.0%-14%ODOT
260069ASD-Mohican State Park FY2026 (BRIDGE REPAIR)ASD3Ohio Concrete Maintenance LLC$246,052$249,331+1.0%-14%ODOT
260075LIC-IR 70-01.95 (NOISE WALLS)LIC5Axis Civil Construction LLC$74,605$76,408+2.0%+17%ODOT
ODOT contracts let on January 29, 2026, largest low bid first

Gap is the second bid over the low bid. Where a contract shows fewer bids than ODOT received, the others did not match their published totals and are left out. Each contract number opens its full bid tabulation.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy