ODOT contract 260067 bid tabulation
WAS-IR 77-09.58 (MISCELLANEOUS). Let by Ohio DOT on January 29, 2026, WAS. 4 bids received; low bid $2,209,192 by Shelly & Sands Inc, -16% against the engineer's estimate of $2,622,000.
- Owner
- Ohio DOT
- Letting
- 29 JAN 2026
- Pay items
- 59
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Shelly & Sands Inc | $2,209,192 | Low | -16% |
| 2 | Alan Stone Co Inc | $2,559,458 | +16% | -2.0% |
| 3 | Rietschlin Construction Inc | $2,842,742 | +29% | +8.0% |
| 4 | Complete General Construction Company | $2,912,876 | +32% | +11% |
Engineer's estimate: $2,622,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Shelly & Sands Inc | 2. Alan Stone Co Inc | 3. Rietschlin Construction Inc | 4. Complete General Construction Company |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $55,500 | $65,000 | $250,000 | $28,000 |
| 2 | Gutter removed (202E32700) | SY | 43 | $8.50 | $30.00 | $38.00 | $50.00 |
| 3 | Pipe removed, over 24" diameter (202E35200) | FT | 242 | $13.00 | $20.00 | $40.00 | $75.00 |
| 4 | Special - pipe cleanout, 27" to 48" (202E70120) | FT | 560 | $11.00 | $30.00 | $21.00 | $40.00 |
| 5 | Excavation (203E10000) | CY | 12,129 | $30.00 | $19.00 | $25.00 | $38.00 |
| 6 | Embankment (203E20000) | CY | 44 | $12.00 | $16.00 | $37.00 | $28.00 |
| 7 | Embankment, as per plan (203E20001) | CY | 12,085 | $7.50 | $29.00 | $9.00 | $15.00 |
| 8 | Roadway, misc.: waste area as built survey (203E98500) | LS | 1 | $4,500.00 | $6,000.00 | $3,600.00 | $9,000.00 |
| 9 | Rock channel protection, type A with filter (601E32000) | CY | 213 | $100.00 | $120.00 | $112.00 | $120.00 |
| 10 | Rock channel protection, type B with filter (601E32100) | CY | 146 | $113.00 | $130.00 | $116.00 | $125.00 |
| 11 | Topsoil (659E00300) | CY | 164 | $10.00 | $40.00 | $70.00 | $45.00 |
| 12 | Seeding and mulching (659E10000) | SY | 6,960 | $1.10 | $1.50 | $4.25 | $1.10 |
| 13 | Commercial fertilizer (659E20000) | TON | 0.62 | $885.00 | $640.00 | $1,300.00 | $1,250.00 |
| 14 | Lime (659E31000) | ACRE | 1.43 | $161.00 | $920.00 | $150.00 | $150.00 |
| 15 | Water (659E35000) | MGAL | 19 | $1.00 | $110.00 | $10.00 | $1.00 |
| 16 | Slope erosion protection (670E00500) | SY | 1,473 | $1.50 | $2.00 | $4.50 | $2.50 |
| 17 | Storm water pollution prevention plan (832E15000) | LS | 1 | $3,500.00 | $3,500.00 | $4,000.00 | $2,500.00 |
| 18 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $7,500.00 | $13,000 | $10,000 | $8,550.00 |
| 19 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $10,500 | $12,000 | $12,000 | $11,000 |
| 20 | Erosion control (832E30000) | EACH | 50,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 21 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $3,200.00 | $20,000 | $50,000 | $45,000 |
| 22 | Concrete masonry (602E20000) | CY | 1.10 | $2,800.00 | $8,000.00 | $3,800.00 | $1,800.00 |
| 23 | Liner pipe 30" conduit, type A, 707.33, 707.34, 70 (837E10000) | FT | 560 | $290.00 | $300.00 | $250.00 | $320.00 |
| 24 | Backfill for liner pipe (837E21000) | FT | 560 | $115.00 | $180.00 | $170.00 | $115.00 |
| 25 | Lane line, 6", type 1 (642E00204) | MI | 0.41 | $1,775.00 | $2,000.00 | $2,100.00 | $1,775.00 |
| 26 | Work zone edge line, class I, 6" (614E22010) | MI | 0.41 | $10,325 | $12,000 | $11,900 | $16,700 |
| 27 | Work zone dotted line, class I (614E24000) | FT | 840 | $2.00 | $2.50 | $2.30 | $3.25 |
| 28 | Unclassified excavation (503E21300) | LS | 1 | $29,500 | $20,000 | $65,000 | $30,000 |
| 29 | Steel piles, misc.: HP14X89 soldier pile (507E00400) | FT | 1,206 | $125.00 | $160.00 | $133.00 | $140.00 |
| 30 | Epoxy coated steel reinforcement (509E10000) | LB | 19,696 | $2.00 | $2.50 | $2.00 | $3.00 |
| 31 | Class QC1 concrete, retaining/wingwall not including footing (511E46010) | CY | 158 | $1,300.00 | $730.00 | $1,120.00 | $1,800.00 |
| 32 | Sealing of concrete surfaces (non-epoxy) (512E10050) | SY | 242 | $16.00 | $40.00 | $19.00 | $16.00 |
| 33 | Welded stud shear connectors, as per plan (513E20001) | EACH | 2,586 | $7.50 | $10.00 | $11.00 | $7.35 |
| 34 | 1" preformed expansion joint filler (516E13600) | SF | 44 | $7.00 | $1.50 | $23.00 | $11.00 |
| 35 | Nylon reinforced neoprene sheeting (516E25000) | SF | 284 | $22.00 | $20.00 | $16.00 | $14.00 |
| 36 | Prefabricated geocomposite drain (518E20000) | SY | 200 | $28.00 | $20.00 | $52.00 | $38.00 |
| 37 | Porous backfill with geotextile fabric (518E21200) | CY | 26 | $240.00 | $660.00 | $165.00 | $100.00 |
| 38 | Drilled shafts, 30" diameter, above bedrock, as per plan (524E94603) | FT | 647 | $135.00 | $70.00 | $160.00 | $210.00 |
| 39 | Drilled shafts, 30" diameter into bedrock, as per plan (524E94605) | FT | 115 | $195.00 | $160.00 | $160.00 | $250.00 |
| 40 | Special - retaining wall, timber lagging (530E51020) | SF | 2,242 | $25.00 | $12.00 | $25.00 | $19.00 |
| 41 | Paved gutter, type 1-2, as per plan (601E37501) | FT | 139 | $130.00 | $130.00 | $94.00 | $110.00 |
| 42 | 6" conduit, type C (611E01100) | FT | 55 | $52.00 | $100.00 | $120.00 | $90.00 |
| 43 | 12" conduit, type C (611E04600) | FT | 152 | $100.00 | $120.00 | $120.00 | $110.00 |
| 44 | Low strength mortar backfill (613E41200) | CY | 81 | $168.00 | $190.00 | $181.00 | $250.00 |
| 45 | Ground anchor, 114 kip max test load (866E00100) | EACH | 6 | $8,900.00 | $12,000 | $11,200 | $12,000 |
| 46 | Ground anchor, 126 kip max test load (866E00100) | EACH | 6 | $8,900.00 | $12,000 | $11,200 | $12,000 |
| 47 | Ground anchor, 146 kip max test load (866E00100) | EACH | 9 | $8,900.00 | $12,000 | $11,200 | $12,000 |
| 48 | Ground anchor, 179 kip max test load (866E00100) | EACH | 9 | $8,900.00 | $13,000 | $11,200 | $12,000 |
| 49 | Ground anchor, 190 kip max test load (866E00100) | EACH | 6 | $8,900.00 | $13,000 | $11,200 | $12,000 |
| 50 | Ground anchor, 193 kip max test load (866E00100) | EACH | 6 | $8,900.00 | $13,000 | $11,200 | $12,000 |
| 51 | Ground anchor, 195 kip max test load (866E00100) | EACH | 2 | $8,900.00 | $13,000 | $11,200 | $12,000 |
| 52 | Ground anchor, 239 kip max test load (866E00100) | EACH | 2 | $8,900.00 | $13,500 | $11,200 | $12,000 |
| 53 | Investigative anchor pullout tests (866E00300) | LS | 1 | $40,000 | $17,000 | $45,200 | $40,000 |
| 54 | Performance test (866E00400) | EACH | 3 | $3,500.00 | $2,300.00 | $3,955.00 | $3,500.00 |
| 55 | Extended creep test (866E00500) | EACH | 3 | $3,500.00 | $15,000 | $3,955.00 | $3,500.00 |
| 56 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $14,500 | $20,000 | $45,000 | $16,000 |
| 57 | Maintaining traffic (614E11000) | LS | 1 | $23,500 | $32,000 | $25,000 | $85,000 |
| 58 | Construction layout stakes and surveying (623E10000) | LS | 1 | $32,500 | $40,000 | $20,000 | $45,000 |
| 59 | Mobilization (624E10000) | LS | 1 | $100,000 | $105,000 | $290,000 | $150,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of January 29, 2026. Compiled by Mirage Metrics.