Class QC1 concrete, retaining/wingwall not including footing, ODOT 511E46010
Low bidders on ODOT contracts carried a median of $1,500.00 per CY for this item, over the 24 months to 12 NOV 2026, across 76 low bids. Half of all 299 bids fell between $1,187.01 and $2,128.29.
- Owner
- Ohio DOT
- Item
- 511E46010
- Unit
- CY
- Data through
- 12 NOV 2026
ODOT prints this item as “CLASS QC1 CONCRETE, RETAINING/WINGWALL NOT INCLUDI”.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 28 | 29 | $1,000.00 | 176 | $1,296.11 |
| 2021 | 27 | 33 | $900.00 | 182 | $1,300.00 |
| 2022 | 39 | 44 | $950.00 | 193 | $1,400.00 |
| 2023 | 30 | 34 | $1,413.30 | 136 | $1,500.00 |
| 2024 | 38 | 44 | $1,483.28 | 197 | $1,500.00 |
| 2025 | 31 | 39 | $1,525.00 | 153 | $1,750.00 |
| 2026 | 29 | 34 | $1,358.00 | 134 | $1,412.50 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| DEL | 4 | $1,550.00 | 21 | $1,575.00 |
| RIC | 3 | $1,638.25 | 18 | $1,767.55 |
| WAY | 5 | $1,875.00 | 16 | $1,701.75 |
| PUT | 3 | $1,750.00 | 15 | $1,366.43 |
| ATB | 4 | $1,100.00 | 14 | $1,485.00 |
| HEN | 4 | $1,075.01 | 12 | $1,079.28 |
| LAW | 3 | $2,550.00 | 10 | $2,425.00 |
| FRA | 5 | $2,550.00 | 7 | $2,315.00 |
| District 12 | 3 | $3,699.35 | 4 | $3,520.80 |
Countys with at least three low bids, over the last 24 months.
By quantity
| Quantity (CY) | Low bids | Low-bid median |
|---|---|---|
| 2 to 8 | 19 | $2,550.00 |
| 9 to 15 | 19 | $1,690.00 |
| 15 to 30 | 19 | $1,200.00 |
| 30 to 158 | 19 | $1,100.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| R C Construction Company and Son Inc | 42 | 29 (69%) |
| Parker Corporation | 26 | 18 (69%) |
| D G M Inc | 39 | 13 (33%) |
| Great Lakes Demolition Company | 15 | 10 (67%) |
| Karvo Companies Inc | 12 | 10 (83%) |
| Adena Corporation | 17 | 9 (53%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 12 NOV 2026 | 260505 | LOR | 16 | $1,316.00 | $1,704.94 | 7 | Crawford Construction Company Inc | ODOT |
| 12 NOV 2026 | 260508 | RIC | 11 | $875.00 | $1,255.00 | 8 | Great Lakes Demolition Company | ODOT |
| 12 NOV 2026 | 260509 | SCI | 8 | $2,800.00 | $2,300.00 | 5 | Axis Civil Construction LLC | ODOT |
| 01 OCT 2026 | 260419 | BEL | 46 | $1,885.00 | $1,950.00 | 3 | Marucci & Gaffney Excavating Co | ODOT |
| 01 OCT 2026 | 260427 | LAW | 10 | $3,512.00 | $2,450.00 | 4 | Allard Excavation LLC | ODOT |
| 01 OCT 2026 | 260433 | PUT | 27 | $1,750.00 | $1,333.22 | 6 | Fenson Contracting LLC | ODOT |
| 01 OCT 2026 | 260433 | PUT | 34 | $1,750.00 | $1,336.24 | 6 | Fenson Contracting LLC | ODOT |
| 01 OCT 2026 | 268018 | DEL | 48 | $1,100.00 | $1,157.00 | 4 | Double Z Construction Company | ODOT |
| 17 SEP 2026 | 260416 | WIL | 19 | $1,150.00 | $1,300.00 | 3 | Geddis Paving & Excavating Inc | ODOT |
| 27 AUG 2026 | 264020 | CAR | 6 | $3,000.00 | $3,559.34 | 2 | Bog Construction Inc | ODOT |
| 13 AUG 2026 | 260361 | GAL | 9 | $1,900.00 | $1,250.00 | 4 | Axis Civil Construction LLC | ODOT |
| 16 JUL 2026 | 264017 | CRA | 15 | $850.00 | $1,325.00 | 4 | Great Lakes Demolition Company | ODOT |
| 11 JUN 2026 | 260282 | ATB | 30 | $1,100.00 | $1,365.00 | 4 | A P O'Horo Company | ODOT |
| 11 JUN 2026 | 260282 | ATB | 20 | $1,100.00 | $1,785.00 | 4 | A P O'Horo Company | ODOT |
| 11 JUN 2026 | 260282 | ATB | 36 | $1,100.00 | $1,470.00 | 4 | A P O'Horo Company | ODOT |
Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.
How these prices were read
ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the ODOT letting of 12 NOV 2026 and was rebuilt on 26 NOV 2026.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.