| 1 | Clearing and grubbing (201E11000) | LS | 1 | $6,000.00 | $18,761 |
| 2 | Structure removed (202E11000) | LS | 1 | $65,000 | $17,472 |
| 3 | Pavement removed (202E23000) | SY | 549 | $40.00 | $18.79 |
| 4 | Steps removed (202E30200) | FT | 40 | $10.00 | $90.00 |
| 5 | Curb and gutter removed (202E32500) | FT | 160 | $25.00 | $24.19 |
| 6 | Pipe removed, over 24" diameter (202E35200) | FT | 67 | $100.00 | $136.37 |
| 7 | Guardrail removed (202E38000) | FT | 961 | $3.00 | $5.15 |
| 8 | Fence removed (202E75000) | FT | 84 | $10.00 | $15.98 |
| 9 | Excavation (203E10000) | CY | 430 | $15.00 | $40.36 |
| 10 | Embankment (203E20000) | CY | 889 | $20.00 | $49.50 |
| 11 | Subgrade compaction (204E10000) | SY | 676 | $4.00 | $5.20 |
| 12 | Guardrail, type MGS with long posts, as per plan (606E15101) | FT | 150 | $49.00 | $42.40 |
| 13 | Anchor assembly, MGS type T (606E26550) | EACH | 2 | $1,800.00 | $1,520.00 |
| 14 | Special - mailbox removed and reset (690E50350) | EACH | 1 | $500.00 | $1,110.00 |
| 15 | Rock channel protection, type B with aggregate filter (601E32110) | CY | 35 | $95.00 | $252.87 |
| 16 | Rock channel protection, type C with geotextile fabric (601E32204) | CY | 2 | $200.00 | $1,571.30 |
| 17 | Soil analysis test (659E00100) | EACH | 6 | $40.00 | $281.88 |
| 18 | Topsoil (659E00300) | CY | 222 | $40.00 | $67.36 |
| 19 | Seeding and mulching (659E10000) | SY | 2,001 | $4.00 | $4.42 |
| 20 | Repair seeding and mulching (659E14000) | SY | 101 | $1.00 | $60.01 |
| 21 | Commercial fertilizer (659E20000) | TON | 0.27 | $1,000.00 | $1,368.70 |
| 22 | Lime (659E31000) | ACRE | 0.41 | $100.00 | $1,218.10 |
| 23 | Water (659E35000) | MGAL | 15 | $1.00 | $10.00 |
| 24 | Erosion control (832E30000) | EACH | 10,000 | $1.00 | $1.00 |
| 25 | Seeding and erosion control with turf reinforcing mat, type 1 (836E10000) | SY | 160 | $12.00 | $14.56 |
| 26 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $5,000.00 | $20,835 |
| 27 | Unclassified excavation (503E21100) | CY | 180 | $15.00 | $73.19 |
| 28 | Epoxy coated steel reinforcement (509E10000) | LB | 2,608 | $3.00 | $3.83 |
| 29 | Class QC1 concrete, retaining/wingwall not including footing (511E46010) | CY | 6 | $3,000.00 | $4,118.67 |
| 30 | Class QC1 concrete, footing (511E46510) | CY | 21 | $400.00 | $851.38 |
| 31 | Class QC1 concrete, headwall (511E46610) | CY | 1 | $2,500.00 | $7,801.50 |
| 32 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 40 | $35.00 | $63.63 |
| 33 | Type 2 waterproofing (512E33000) | SY | 203 | $30.00 | $30.37 |
| 34 | 1" preformed expansion joint filler (516E13600) | SF | 26 | $15.00 | $24.19 |
| 35 | Porous backfill with geotextile fabric (518E21200) | CY | 6 | $300.00 | $484.54 |
| 36 | Concrete masonry (602E20000) | CY | 1 | $3,000.00 | $3,445.00 |
| 37 | Aggregate drains (605E31100) | FT | 96 | $20.00 | $37.56 |
| 38 | 12" conduit, type B (611E04400) | FT | 37 | $135.00 | $166.15 |
| 39 | 36" conduit, type A (611E16200) | FT | 78 | $350.00 | $396.42 |
| 40 | 8' X 4' conduit, type A, 706.05, as per plan (611E94801) | FT | 84 | $900.00 | $1,542.85 |
| 41 | Catch basin, no. 3A (611E98180) | EACH | 1 | $5,250.00 | $5,313.00 |
| 42 | Manhole, no. 3 (611E99574) | EACH | 1 | $6,500.00 | $10,937 |
| 43 | Low strength mortar backfill (613E41200) | CY | 155 | $140.00 | $237.99 |
| 44 | Pavement planing, asphalt concrete (1 1/4") (254E01000) | SY | 99 | $50.00 | $46.00 |
| 45 | Pavement planing, asphalt concrete (2") (254E01000) | SY | 35 | $60.00 | $46.00 |
| 46 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 96 | $581.00 | $396.00 |
| 47 | Aggregate base (304E20000) | CY | 168 | $145.00 | $129.78 |
| 48 | Tack coat (407E10000) | GAL | 73 | $6.00 | $4.00 |
| 49 | Prime coat, as per plan (408E10001) | GAL | 110 | $45.00 | $43.00 |
| 50 | Asphalt concrete surface course, type 1, (449), PG70-22M (441E70100) | CY | 26 | $1,172.00 | $969.77 |
| 51 | Asphalt concrete intermediate course, type 2, (449) (441E70300) | CY | 27 | $987.00 | $764.00 |
| 52 | Combination curb and gutter, type 2, as per plan (609E12001) | FT | 162 | $246.00 | $238.91 |
| 53 | RPM (621E00100) | EACH | 15 | $400.00 | $495.78 |
| 54 | Raised pavement marker removed (621E54000) | EACH | 15 | $50.00 | $26.67 |
| 55 | Barrier reflector, type 2 (bidirectional) (626E00110) | EACH | 5 | $25.00 | $12.38 |
| 56 | Ground mounted support, no. 2 post (630E02100) | FT | 24 | $60.00 | $55.62 |
| 57 | Removal of ground mounted sign and disposal (630E84900) | EACH | 6 | $100.00 | $96.94 |
| 58 | Removal of ground mounted sign and reerection (630E85100) | EACH | 1 | $300.00 | $284.55 |
| 59 | Removal of ground mounted post support and disposal (630E86002) | EACH | 8 | $25.00 | $22.70 |
| 60 | Edge line, 6" (646E10010) | MI | 0.11 | $45,000 | $40,429 |
| 61 | Center line (646E10200) | MI | 0.07 | $56,000 | $54,007 |
| 62 | Detour signing (614E12420) | LS | 1 | $12,000 | $14,341 |
| 63 | Asphalt concrete for maintaining traffic (614E13000) | CY | 140 | $120.00 | $146.79 |
| 64 | Work zone center line, class I, 642 paint (614E21100) | MI | 0.07 | $15,000 | $34,392 |
| 65 | Work zone edge line, class I, 6", 642 paint (614E22110) | MI | 0.11 | $15,000 | $28,152 |
| 66 | Water (616E10000) | MGAL | 15 | $1.00 | $10.00 |
| 67 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $30,000 | $13,500 |
| 68 | Maintaining traffic (614E11000) | LS | 1 | $6,500.00 | $14,840 |
| 69 | Field office, type B (619E16010) | MNTH | 6 | $500.00 | $3,250.00 |
| 70 | Construction layout stakes and surveying (623E10000) | LS | 1 | $20,000 | $22,750 |
| 71 | Mobilization (624E10000) | LS | 1 | $30,000 | $74,819 |