ODOT contract 260416 bid tabulation
WIL-US 127-15.09 Culvert (CULVERT REPLACEMENT). Let by Ohio DOT on September 17, 2026, WIL. 3 bids received; low bid $404,515 by Geddis Paving & Excavating Inc, -4.8% against the engineer's estimate of $425,000.
- Owner
- Ohio DOT
- Letting
- 17 SEP 2026
- Pay items
- 61
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Geddis Paving & Excavating Inc | $404,515 | Low | -5.0% |
| 2 | Advanced Excavating & Demolition LLC | $426,132 | +5.0% | 0.0% |
| 3 | Ebony Construction Co | $471,087 | +16% | +11% |
Engineer's estimate: $425,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Geddis Paving & Excavating Inc | 2. Advanced Excavating & Demolition LLC | 3. Ebony Construction Co |
|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing, as per plan (201E11001) | LS | 1 | $1,800.00 | $6,000.00 | $1,900.00 |
| 2 | Pavement removed (202E23000) | SY | 168 | $25.00 | $20.00 | $28.00 |
| 3 | Pipe removed, 24" and under (202E35100) | FT | 18 | $53.00 | $32.00 | $18.00 |
| 4 | Guardrail removed (202E38000) | FT | 150 | $12.00 | $2.40 | $2.75 |
| 5 | Anchor assembly removed, type E (202E42010) | EACH | 3 | $240.00 | $175.00 | $200.00 |
| 6 | Anchor assembly removed, type T (202E42040) | EACH | 1 | $240.00 | $95.00 | $109.00 |
| 7 | Fence removed, as per plan (202E75001) | FT | 137 | $9.00 | $7.50 | $8.75 |
| 8 | Removal misc.:, riprap (202E98000) | LS | 1 | $765.00 | $5,000.00 | $520.00 |
| 9 | Removal misc.: concrete base for post (202E98100) | EACH | 11 | $46.00 | $65.00 | $95.00 |
| 10 | Excavation (203E10000) | CY | 225 | $46.00 | $27.00 | $29.00 |
| 11 | Embankment (203E20000) | CY | 675 | $10.00 | $25.00 | $28.00 |
| 12 | Subgrade compaction (204E10000) | SY | 205 | $0.50 | $1.50 | $1.80 |
| 13 | Guardrail, type MGS (606E15050) | FT | 225 | $43.00 | $25.00 | $28.00 |
| 14 | Anchor assembly, MGS type E (606E26150) | EACH | 2 | $3,750.00 | $3,000.00 | $3,260.00 |
| 15 | Anchor assembly, MGS type T (606E26550) | EACH | 2 | $2,350.00 | $1,400.00 | $1,575.00 |
| 16 | Monument assembly, type C (623E38500) | EACH | 2 | $880.00 | $1,500.00 | $1,675.00 |
| 17 | Special - mailbox removed and reset (690E50350) | EACH | 1 | $295.00 | $200.00 | $650.00 |
| 18 | Rock channel protection, type B with filter (601E32100) | CY | 25 | $165.00 | $160.00 | $132.00 |
| 19 | Topsoil (659E00300) | CY | 107 | $115.00 | $40.00 | $88.00 |
| 20 | Seeding and mulching (659E10000) | SY | 955 | $2.50 | $3.05 | $2.80 |
| 21 | Repair seeding and mulching (659E14000) | SY | 48 | $2.50 | $3.05 | $2.80 |
| 22 | Inter-seeding (659E15000) | SY | 48 | $2.00 | $1.55 | $2.30 |
| 23 | Commercial fertilizer (659E20000) | TON | 0.13 | $850.00 | $750.00 | $970.00 |
| 24 | Lime (659E31000) | ACRE | 0.20 | $35.00 | $0.30 | $40.00 |
| 25 | Water (659E35000) | MGAL | 1 | $1.00 | $0.10 | $1.15 |
| 26 | Erosion control (832E30000) | EACH | 2,000 | $1.00 | $1.00 | $1.00 |
| 27 | Concrete masonry (602E20000) | CY | 0.20 | $4,400.00 | $7,000.00 | $1,670.00 |
| 28 | 4" conduit, type F (611E00406) | FT | 20 | $35.00 | $55.00 | $25.00 |
| 29 | 6" conduit, type F (611E01500) | FT | 20 | $43.00 | $55.00 | $26.00 |
| 30 | 8" conduit, type F (611E02600) | FT | 40 | $45.00 | $60.00 | $20.00 |
| 31 | 12" conduit, type D (611E04900) | FT | 32 | $59.00 | $80.00 | $45.00 |
| 32 | 12" conduit, type F (611E05200) | FT | 20 | $59.00 | $70.00 | $50.00 |
| 33 | 7' X 7' conduit, type A, 706.05, as per plan (611E94733) | FT | 54 | $2,150.00 | $1,750.00 | $1,850.00 |
| 34 | Low strength mortar backfill (613E41200) | CY | 128 | $285.00 | $195.00 | $250.00 |
| 35 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 39 | $350.00 | $378.00 | $330.00 |
| 36 | Aggregate base (304E20000) | CY | 31 | $100.00 | $115.00 | $120.00 |
| 37 | Tack coat (407E10000) | GAL | 29 | $4.00 | $2.50 | $4.00 |
| 38 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 14 | $380.00 | $675.00 | $520.00 |
| 39 | Compacted aggregate (617E10100) | CY | 2 | $130.00 | $250.00 | $160.00 |
| 40 | Barrier reflector, type 5, bidirectional (626E00116) | EACH | 6 | $15.00 | $15.00 | $17.00 |
| 41 | Removal of ground mounted sign and disposal (630E84900) | EACH | 3 | $180.00 | $150.00 | $40.00 |
| 42 | Removal of ground mounted sign and reerection (630E85100) | EACH | 2 | $360.00 | $300.00 | $400.00 |
| 43 | Pavement planing, asphalt concrete, 1.5" (254E01000) | SY | 129 | $17.00 | $30.00 | $10.00 |
| 44 | Tack coat (407E10000) | GAL | 8 | $4.00 | $2.50 | $4.00 |
| 45 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 6 | $380.00 | $775.00 | $420.00 |
| 46 | Portable changeable message sign, as per plan (614E18601) | SNMT | 4 | $1,450.00 | $1,000.00 | $1,275.00 |
| 47 | Structure removed, as per plan (202E11001) | LS | 1 | $8,200.00 | $14,000 | $15,000 |
| 48 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $7,900.00 | $15,000 | $33,000 |
| 49 | Unclassified excavation (503E21300) | LS | 1 | $7,150.00 | $7,500.00 | $5,500.00 |
| 50 | Epoxy coated steel reinforcement (509E10000) | LB | 4,828 | $4.75 | $5.25 | $3.50 |
| 51 | Class QC1 concrete, retaining/wingwall not including footing (511E46010) | CY | 19 | $1,150.00 | $1,300.00 | $2,250.00 |
| 52 | Class QC1 concrete, footing (511E46510) | CY | 31 | $590.00 | $690.00 | $1,400.00 |
| 53 | Class QC1 concrete, headwall (511E46610) | CY | 2 | $2,700.00 | $1,250.00 | $2,850.00 |
| 54 | Sealing of concrete surfaces (non-epoxy) (512E10050) | SY | 51 | $31.50 | $45.00 | $27.50 |
| 55 | Type 2 waterproofing (512E33000) | SY | 164 | $13.00 | $45.00 | $11.00 |
| 56 | 1" preformed expansion joint filler (516E13600) | SF | 51 | $12.00 | $13.50 | $21.00 |
| 57 | Porous backfill with geotextile fabric (518E21230) | LS | 1 | $6,600.00 | $3,850.00 | $3,000.00 |
| 58 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $3,250.00 | $8,500.00 | $6,450.00 |
| 59 | Maintaining traffic (614E11000) | LS | 1 | $3,800.00 | $13,500 | $7,000.00 |
| 60 | Construction layout stakes and surveying (623E10000) | LS | 1 | $10,300 | $11,000 | $15,000 |
| 61 | Mobilization (624E10000) | LS | 1 | $16,000 | $25,000 | $28,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of September 17, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.