ODOT contract 260427 bid tabulation
LAW-SR 93-11.21 Flooding (MINOR RECONSTRUCTION). Let by Ohio DOT on October 1, 2026, LAW. 4 bids received; low bid $2,734,290 by Allard Excavation LLC, +2.2% against the engineer's estimate of $2,675,000.
- Owner
- Ohio DOT
- Letting
- 01 OCT 2026
- Pay items
- 107
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Allard Excavation LLC | $2,734,290 | Low | +2.0% |
| 2 | D G M Inc | $2,879,195 | +5.0% | +8.0% |
| 3 | Axis Civil Construction LLC | $3,028,712 | +11% | +13% |
| 4 | Alan Stone Co Inc | $3,261,373 | +19% | +22% |
Engineer's estimate: $2,675,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Allard Excavation LLC | 2. D G M Inc | 3. Axis Civil Construction LLC | 4. Alan Stone Co Inc |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing, as per plan (201E11001) | LS | 1 | $30,000 | $70,000 | $30,000 | $55,000 |
| 2 | Pavement removed (202E23000) | SY | 7,105 | $14.00 | $15.00 | $20.00 | $10.00 |
| 3 | Pipe removed, 24" and under (202E35100) | FT | 159 | $41.00 | $25.00 | $40.00 | $10.00 |
| 4 | Pipe removed, over 24" diameter (202E35200) | FT | 31 | $104.00 | $40.00 | $55.00 | $35.00 |
| 5 | Guardrail removed (202E38000) | FT | 2,286 | $4.00 | $3.00 | $2.50 | $2.00 |
| 6 | Anchor assembly removed, type E (202E42010) | EACH | 5 | $78.00 | $200.00 | $250.00 | $500.00 |
| 7 | Mailbox removed (202E53100) | EACH | 2 | $48.00 | $100.00 | $125.00 | $65.00 |
| 8 | Fence removed (202E75000) | FT | 508 | $2.00 | $6.00 | $12.00 | $4.00 |
| 9 | Removal misc.: decorative rock removed (202E98100) | EACH | 1 | $147.00 | $100.00 | $500.00 | $500.00 |
| 10 | Removal misc.: conduit (202E98200) | FT | 30 | $10.00 | $10.00 | $50.00 | $25.00 |
| 11 | Excavation (203E10000) | CY | 1,678 | $32.00 | $17.00 | $38.00 | $10.00 |
| 12 | Embankment (203E20000) | CY | 1,479 | $35.00 | $30.00 | $38.00 | $40.00 |
| 13 | Embankment, as per plan (203E20001) | CY | 50 | $32.00 | $20.00 | $45.00 | $40.00 |
| 14 | Subgrade compaction (204E10000) | SY | 9,347 | $3.00 | $3.50 | $3.00 | $4.50 |
| 15 | Excavation of subgrade (204E13000) | CY | 1,881 | $31.00 | $30.00 | $35.00 | $35.00 |
| 16 | Granular material, type B (204E30010) | CY | 3,860 | $90.00 | $95.00 | $108.00 | $100.00 |
| 17 | Granular material, type C (204E30020) | CY | 137 | $89.00 | $130.00 | $140.00 | $110.00 |
| 18 | Proof rolling (204E45000) | HR | 9 | $255.00 | $100.00 | $250.00 | $280.00 |
| 19 | Geotextile fabric (204E50000) | SY | 11,749 | $2.00 | $2.25 | $1.80 | $1.50 |
| 20 | Geogrid, as per plan (204E51001) | SY | 431 | $2.00 | $6.00 | $37.00 | $2.50 |
| 21 | Rock excavation (503E31100) | CY | 20 | $52.00 | $150.00 | $75.00 | $65.00 |
| 22 | Guardrail, type MGS (606E15050) | FT | 2,175 | $21.50 | $25.00 | $23.00 | $25.00 |
| 23 | Guardrail, type MGS with long posts (606E15100) | FT | 212.50 | $24.64 | $28.00 | $32.00 | $30.00 |
| 24 | Guardrail, type MGS, long-span (606E17360) | FT | 87.50 | $22.10 | $38.00 | $25.00 | $30.00 |
| 25 | Anchor assembly, MGS type E (606E26150) | EACH | 3 | $2,320.00 | $2,700.00 | $2,700.00 | $3,300.00 |
| 26 | Anchor assembly, MGS type T (606E26550) | EACH | 2 | $1,200.00 | $1,500.00 | $1,400.00 | $1,600.00 |
| 27 | Reference monument, type A (623E40500) | EACH | 7 | $375.00 | $500.00 | $500.00 | $800.00 |
| 28 | Special - mailbox support (690E50000) | EACH | 2 | $150.00 | $200.00 | $200.00 | $110.00 |
| 29 | Inspection and compaction testing of unbound materials (878E25000) | LS | 1 | $57,190 | $20,000 | $44,000 | $35,000 |
| 30 | Rock channel protection, type B with aggregate filter (601E32110) | CY | 104 | $103.00 | $150.00 | $144.00 | $200.00 |
| 31 | Topsoil (659E00300) | CY | 1,038 | $29.00 | $25.00 | $60.00 | $20.00 |
| 32 | Seeding and mulching (659E10000) | SY | 9,349 | $0.90 | $2.00 | $0.90 | $1.00 |
| 33 | Repair seeding and mulching (659E14000) | SY | 467 | $0.90 | $0.05 | $0.90 | $3.00 |
| 34 | Inter-seeding (659E15000) | SY | 467 | $0.90 | $0.05 | $0.90 | $1.00 |
| 35 | Commercial fertilizer (659E20000) | TON | 1.30 | $1,250.00 | $1,500.00 | $1,250.00 | $640.00 |
| 36 | Lime (659E31000) | ACRE | 1.93 | $150.00 | $300.00 | $150.00 | $920.00 |
| 37 | Water (659E35000) | MGAL | 52 | $1.00 | $1.00 | $1.00 | $110.00 |
| 38 | Slope erosion protection (670E00500) | SY | 2,049 | $2.00 | $2.50 | $2.00 | $1.50 |
| 39 | Ditch erosion protection mat, type B (670E00720) | SY | 23 | $2.00 | $4.00 | $2.00 | $30.00 |
| 40 | Storm water pollution prevention plan (832E15000) | LS | 1 | $3,500.00 | $4,000.00 | $3,500.00 | $5,400.00 |
| 41 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $14,800 | $12,000 | $16,000 | $15,000 |
| 42 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $13,200 | $15,000 | $15,000 | $15,000 |
| 43 | Erosion control (832E30000) | EACH | 87,771 | $1.00 | $1.00 | $1.00 | $1.00 |
| 44 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $6,852.00 | $200.00 | $36,000 | $13,000 |
| 45 | Concrete masonry (602E20000) | CY | 3.60 | $5,433.00 | $2,750.00 | $4,500.00 | $3,500.00 |
| 46 | Aggregate drains (605E31100) | FT | 1,107 | $17.00 | $25.00 | $25.00 | $15.00 |
| 47 | 18" conduit, type A (611E07200) | FT | 125 | $240.00 | $190.00 | $230.00 | $190.00 |
| 48 | 24" conduit, type A (611E10200) | FT | 15 | $382.00 | $300.00 | $310.00 | $250.00 |
| 49 | 30" conduit, type A, 706.02, 707.33 (611E13200) | FT | 68 | $435.00 | $300.00 | $275.00 | $220.00 |
| 50 | 14" X 23" conduit, type A, 706.04 (611E52200) | FT | 50 | $379.00 | $325.00 | $640.00 | $310.00 |
| 51 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 1,433 | $217.00 | $225.00 | $217.00 | $280.00 |
| 52 | Asphalt concrete base, PG64-22, (449), (driveways) (301E56100) | CY | 7 | $280.00 | $300.00 | $280.00 | $650.00 |
| 53 | Aggregate base (304E20000) | CY | 1,527 | $101.00 | $117.50 | $106.00 | $100.00 |
| 54 | Non-tracking tack coat (407E20000) | GAL | 933 | $4.30 | $4.30 | $4.30 | $6.50 |
| 55 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 294 | $245.00 | $260.00 | $245.00 | $300.00 |
| 56 | Asphalt concrete intermediate course, type 2, (449) (441E70300) | CY | 411 | $240.00 | $252.00 | $240.00 | $310.00 |
| 57 | Asphalt concrete surface course, type 1, (449), (driveways) (441E70500) | CY | 3 | $500.00 | $500.00 | $500.00 | $850.00 |
| 58 | RPM (621E00100) | EACH | 30 | $125.00 | $125.00 | $125.00 | $150.00 |
| 59 | Barrier reflector, type 3, bidirectional (626E00112) | EACH | 27 | $10.00 | $15.00 | $10.00 | $15.00 |
| 60 | Ground mounted support, no. 2 post (630E02100) | FT | 11 | $12.00 | $60.00 | $12.00 | $15.00 |
| 61 | Sign post reflector (630E08600) | EACH | 1 | $30.00 | $75.00 | $30.00 | $35.00 |
| 62 | Sign, flat sheet (630E80100) | SF | 6.30 | $40.00 | $60.00 | $40.00 | $45.00 |
| 63 | Removal of ground mounted sign and disposal (630E84900) | EACH | 6 | $12.00 | $25.00 | $10.00 | $10.00 |
| 64 | Removal of ground mounted post support and disposal (630E86002) | EACH | 4 | $12.00 | $25.00 | $10.00 | $10.00 |
| 65 | Edge line, 6" (644E00104) | MI | 0.91 | $7,300.00 | $8,500.00 | $7,300.00 | $8,400.00 |
| 66 | Center line (644E00300) | MI | 0.45 | $10,950 | $10,500 | $10,950 | $13,000 |
| 67 | Stop line (644E00500) | FT | 16 | $15.50 | $60.00 | $15.50 | $20.00 |
| 68 | Traffic compacted surface, type A or B (410E12000) | CY | 50 | $83.80 | $100.00 | $118.00 | $190.00 |
| 69 | Increased barrier delineation (614E11630) | FT | 1,600 | $1.00 | $1.50 | $2.00 | $1.50 |
| 70 | Work zone impact attenuator, 24" wide hazards, (bidirectional) (614E12384) | EACH | 12 | $1,950.00 | $2,250.00 | $1,950.00 | $3,100.00 |
| 71 | Work zone marking sign (614E12460) | EACH | 2 | $150.00 | $150.00 | $150.00 | $180.00 |
| 72 | Asphalt concrete for maintaining traffic (614E13000) | CY | 50 | $290.00 | $175.00 | $450.00 | $750.00 |
| 73 | Barrier reflector, type 1, (bidirectional) (614E13310) | EACH | 64 | $15.00 | $25.00 | $11.00 | $35.00 |
| 74 | Barrier reflector, type 3, (bidirectional) (614E13314) | EACH | 63 | $15.00 | $25.00 | $11.00 | $40.00 |
| 75 | Object marker, two way (614E13360) | EACH | 127 | $15.00 | $25.00 | $19.00 | $35.00 |
| 76 | Maintaining traffic, misc.: residential driveway T (614E18002) | LS | 1 | $16,518 | $24,000 | $36,000 | $8,000.00 |
| 77 | Portable changeable message sign, as per plan (614E18601) | SNMT | 14 | $1,250.00 | $1,000.00 | $1,050.00 | $1,500.00 |
| 78 | Work zone center line, class I (614E21000) | MI | 0.45 | $2,500.00 | $3,000.00 | $2,500.00 | $3,000.00 |
| 79 | Work zone center line, class II (614E21400) | MI | 0.45 | $385.00 | $1,000.00 | $385.00 | $3,000.00 |
| 80 | Work zone edge line, class I, 6" (614E22010) | MI | 1.52 | $1,400.00 | $2,000.00 | $1,400.00 | $1,700.00 |
| 81 | Work zone edge line, class I, 6", 740.06, type I (614E22210) | MI | 0.14 | $10,500 | $11,500 | $10,500 | $12,000 |
| 82 | Work zone stop line, class I, 740.06, type I (614E26400) | FT | 23 | $14.00 | $20.00 | $14.00 | $15.00 |
| 83 | Roads for maintaining traffic (615E10000) | LS | 1 | $13,924 | $15,000 | $39,000 | $89,000 |
| 84 | Pavement for maintaining traffic, class A (615E20000) | SY | 842 | $104.00 | $125.00 | $80.00 | $100.00 |
| 85 | Water (616E10000) | MGAL | 9 | $1.00 | $1.00 | $1.00 | $110.00 |
| 86 | Portable barrier, unanchored (622E41100) | FT | 2,110 | $24.00 | $19.00 | $25.00 | $55.00 |
| 87 | Portable barrier, anchored (622E41110) | FT | 2,530 | $30.00 | $26.00 | $30.50 | $85.00 |
| 88 | Structure removed, as per plan (202E11001) | LS | 1 | $16,543 | $16,000 | $24,500 | $19,000 |
| 89 | Cofferdams and excavation bracing, as per plan (503E11101) | LS | 1 | $78,543 | $33,000 | $85,000 | $80,000 |
| 90 | Unclassified excavation (503E21300) | LS | 1 | $16,709 | $8,000.00 | $16,500 | $35,000 |
| 91 | Epoxy coated steel reinforcement (509E10000) | LB | 3,727 | $2.00 | $2.50 | $2.80 | $2.50 |
| 92 | Class QC1 concrete, retaining/wingwall not including footing (511E46010) | CY | 10 | $3,512.00 | $1,050.00 | $2,600.00 | $2,300.00 |
| 93 | Class QC1 concrete, footing (511E46510) | CY | 27 | $1,597.00 | $825.00 | $1,000.00 | $880.00 |
| 94 | Class QC1 concrete, headwall (511E46610) | CY | 1 | $3,384.00 | $1,600.00 | $1,800.00 | $5,400.00 |
| 95 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 44 | $75.00 | $45.00 | $65.00 | $75.00 |
| 96 | Type 2 waterproofing (512E33000) | SY | 79 | $165.00 | $20.00 | $26.50 | $60.00 |
| 97 | Type 3 waterproofing (512E33010) | SY | 92 | $259.00 | $35.00 | $65.00 | $70.00 |
| 98 | 1" preformed expansion joint filler (516E13600) | SF | 26 | $3.00 | $20.00 | $10.00 | $1.50 |
| 99 | Porous backfill with geotextile fabric (518E21200) | CY | 12 | $305.00 | $200.00 | $300.00 | $330.00 |
| 100 | 10' X 4' conduit, type A, 706.05 (611E94980) | FT | 62 | $2,402.00 | $3,425.00 | $2,350.00 | $2,000.00 |
| 101 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $18,896 | $115,000 | $18,500 | $35,000 |
| 102 | Maintaining traffic (614E11000) | LS | 1 | $100,604 | $120,000 | $95,000 | $100,000 |
| 103 | Field office, type A (619E16000) | MNTH | 7 | $1,800.00 | $750.00 | $2,500.00 | $1,500.00 |
| 104 | Construction layout stakes and surveying (623E10000) | LS | 1 | $25,793 | $23,000 | $39,000 | $49,000 |
| 105 | Preconstruction survey monument verification and report (623E50000) | LS | 1 | $4,283.00 | $1,000.00 | $1,600.00 | $5,000.00 |
| 106 | Post construction survey monument verification and report (623E51000) | LS | 1 | $4,283.00 | $1,000.00 | $1,600.00 | $5,000.00 |
| 107 | Mobilization (624E10000) | LS | 1 | $40,000 | $100,000 | $100,000 | $125,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of October 1, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.