ODOT contract 260427 bid tabulation

LAW-SR 93-11.21 Flooding (MINOR RECONSTRUCTION). Let by Ohio DOT on October 1, 2026, LAW. 4 bids received; low bid $2,734,290 by Allard Excavation LLC, +2.2% against the engineer's estimate of $2,675,000.

Owner
Ohio DOT
Letting
01 OCT 2026
Pay items
107
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Allard Excavation LLC$2,734,290Low+2.0%
2D G M Inc$2,879,195+5.0%+8.0%
3Axis Civil Construction LLC$3,028,712+11%+13%
4Alan Stone Co Inc$3,261,373+19%+22%
ODOT contract 260427: bids by rank

Engineer's estimate: $2,675,000.

Bid tabulation

LinePay itemUnitQuantity1. Allard Excavation LLC2. D G M Inc3. Axis Civil Construction LLC4. Alan Stone Co Inc
1Clearing and grubbing, as per plan (201E11001)LS1$30,000$70,000$30,000$55,000
2Pavement removed (202E23000)SY7,105$14.00$15.00$20.00$10.00
3Pipe removed, 24" and under (202E35100)FT159$41.00$25.00$40.00$10.00
4Pipe removed, over 24" diameter (202E35200)FT31$104.00$40.00$55.00$35.00
5Guardrail removed (202E38000)FT2,286$4.00$3.00$2.50$2.00
6Anchor assembly removed, type E (202E42010)EACH5$78.00$200.00$250.00$500.00
7Mailbox removed (202E53100)EACH2$48.00$100.00$125.00$65.00
8Fence removed (202E75000)FT508$2.00$6.00$12.00$4.00
9Removal misc.: decorative rock removed (202E98100)EACH1$147.00$100.00$500.00$500.00
10Removal misc.: conduit (202E98200)FT30$10.00$10.00$50.00$25.00
11Excavation (203E10000)CY1,678$32.00$17.00$38.00$10.00
12Embankment (203E20000)CY1,479$35.00$30.00$38.00$40.00
13Embankment, as per plan (203E20001)CY50$32.00$20.00$45.00$40.00
14Subgrade compaction (204E10000)SY9,347$3.00$3.50$3.00$4.50
15Excavation of subgrade (204E13000)CY1,881$31.00$30.00$35.00$35.00
16Granular material, type B (204E30010)CY3,860$90.00$95.00$108.00$100.00
17Granular material, type C (204E30020)CY137$89.00$130.00$140.00$110.00
18Proof rolling (204E45000)HR9$255.00$100.00$250.00$280.00
19Geotextile fabric (204E50000)SY11,749$2.00$2.25$1.80$1.50
20Geogrid, as per plan (204E51001)SY431$2.00$6.00$37.00$2.50
21Rock excavation (503E31100)CY20$52.00$150.00$75.00$65.00
22Guardrail, type MGS (606E15050)FT2,175$21.50$25.00$23.00$25.00
23Guardrail, type MGS with long posts (606E15100)FT212.50$24.64$28.00$32.00$30.00
24Guardrail, type MGS, long-span (606E17360)FT87.50$22.10$38.00$25.00$30.00
25Anchor assembly, MGS type E (606E26150)EACH3$2,320.00$2,700.00$2,700.00$3,300.00
26Anchor assembly, MGS type T (606E26550)EACH2$1,200.00$1,500.00$1,400.00$1,600.00
27Reference monument, type A (623E40500)EACH7$375.00$500.00$500.00$800.00
28Special - mailbox support (690E50000)EACH2$150.00$200.00$200.00$110.00
29Inspection and compaction testing of unbound materials (878E25000)LS1$57,190$20,000$44,000$35,000
30Rock channel protection, type B with aggregate filter (601E32110)CY104$103.00$150.00$144.00$200.00
31Topsoil (659E00300)CY1,038$29.00$25.00$60.00$20.00
32Seeding and mulching (659E10000)SY9,349$0.90$2.00$0.90$1.00
33Repair seeding and mulching (659E14000)SY467$0.90$0.05$0.90$3.00
34Inter-seeding (659E15000)SY467$0.90$0.05$0.90$1.00
35Commercial fertilizer (659E20000)TON1.30$1,250.00$1,500.00$1,250.00$640.00
36Lime (659E31000)ACRE1.93$150.00$300.00$150.00$920.00
37Water (659E35000)MGAL52$1.00$1.00$1.00$110.00
38Slope erosion protection (670E00500)SY2,049$2.00$2.50$2.00$1.50
39Ditch erosion protection mat, type B (670E00720)SY23$2.00$4.00$2.00$30.00
40Storm water pollution prevention plan (832E15000)LS1$3,500.00$4,000.00$3,500.00$5,400.00
41Storm water pollution prevention inspections (832E15002)LS1$14,800$12,000$16,000$15,000
42Storm water pollution prevention inspection software (832E15010)LS1$13,200$15,000$15,000$15,000
43Erosion control (832E30000)EACH87,771$1.00$1.00$1.00$1.00
44Cofferdams and excavation bracing (503E11100)LS1$6,852.00$200.00$36,000$13,000
45Concrete masonry (602E20000)CY3.60$5,433.00$2,750.00$4,500.00$3,500.00
46Aggregate drains (605E31100)FT1,107$17.00$25.00$25.00$15.00
4718" conduit, type A (611E07200)FT125$240.00$190.00$230.00$190.00
4824" conduit, type A (611E10200)FT15$382.00$300.00$310.00$250.00
4930" conduit, type A, 706.02, 707.33 (611E13200)FT68$435.00$300.00$275.00$220.00
5014" X 23" conduit, type A, 706.04 (611E52200)FT50$379.00$325.00$640.00$310.00
51Asphalt concrete base, PG64-22, (449) (301E56000)CY1,433$217.00$225.00$217.00$280.00
52Asphalt concrete base, PG64-22, (449), (driveways) (301E56100)CY7$280.00$300.00$280.00$650.00
53Aggregate base (304E20000)CY1,527$101.00$117.50$106.00$100.00
54Non-tracking tack coat (407E20000)GAL933$4.30$4.30$4.30$6.50
55Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000)CY294$245.00$260.00$245.00$300.00
56Asphalt concrete intermediate course, type 2, (449) (441E70300)CY411$240.00$252.00$240.00$310.00
57Asphalt concrete surface course, type 1, (449), (driveways) (441E70500)CY3$500.00$500.00$500.00$850.00
58RPM (621E00100)EACH30$125.00$125.00$125.00$150.00
59Barrier reflector, type 3, bidirectional (626E00112)EACH27$10.00$15.00$10.00$15.00
60Ground mounted support, no. 2 post (630E02100)FT11$12.00$60.00$12.00$15.00
61Sign post reflector (630E08600)EACH1$30.00$75.00$30.00$35.00
62Sign, flat sheet (630E80100)SF6.30$40.00$60.00$40.00$45.00
63Removal of ground mounted sign and disposal (630E84900)EACH6$12.00$25.00$10.00$10.00
64Removal of ground mounted post support and disposal (630E86002)EACH4$12.00$25.00$10.00$10.00
65Edge line, 6" (644E00104)MI0.91$7,300.00$8,500.00$7,300.00$8,400.00
66Center line (644E00300)MI0.45$10,950$10,500$10,950$13,000
67Stop line (644E00500)FT16$15.50$60.00$15.50$20.00
68Traffic compacted surface, type A or B (410E12000)CY50$83.80$100.00$118.00$190.00
69Increased barrier delineation (614E11630)FT1,600$1.00$1.50$2.00$1.50
70Work zone impact attenuator, 24" wide hazards, (bidirectional) (614E12384)EACH12$1,950.00$2,250.00$1,950.00$3,100.00
71Work zone marking sign (614E12460)EACH2$150.00$150.00$150.00$180.00
72Asphalt concrete for maintaining traffic (614E13000)CY50$290.00$175.00$450.00$750.00
73Barrier reflector, type 1, (bidirectional) (614E13310)EACH64$15.00$25.00$11.00$35.00
74Barrier reflector, type 3, (bidirectional) (614E13314)EACH63$15.00$25.00$11.00$40.00
75Object marker, two way (614E13360)EACH127$15.00$25.00$19.00$35.00
76Maintaining traffic, misc.: residential driveway T (614E18002)LS1$16,518$24,000$36,000$8,000.00
77Portable changeable message sign, as per plan (614E18601)SNMT14$1,250.00$1,000.00$1,050.00$1,500.00
78Work zone center line, class I (614E21000)MI0.45$2,500.00$3,000.00$2,500.00$3,000.00
79Work zone center line, class II (614E21400)MI0.45$385.00$1,000.00$385.00$3,000.00
80Work zone edge line, class I, 6" (614E22010)MI1.52$1,400.00$2,000.00$1,400.00$1,700.00
81Work zone edge line, class I, 6", 740.06, type I (614E22210)MI0.14$10,500$11,500$10,500$12,000
82Work zone stop line, class I, 740.06, type I (614E26400)FT23$14.00$20.00$14.00$15.00
83Roads for maintaining traffic (615E10000)LS1$13,924$15,000$39,000$89,000
84Pavement for maintaining traffic, class A (615E20000)SY842$104.00$125.00$80.00$100.00
85Water (616E10000)MGAL9$1.00$1.00$1.00$110.00
86Portable barrier, unanchored (622E41100)FT2,110$24.00$19.00$25.00$55.00
87Portable barrier, anchored (622E41110)FT2,530$30.00$26.00$30.50$85.00
88Structure removed, as per plan (202E11001)LS1$16,543$16,000$24,500$19,000
89Cofferdams and excavation bracing, as per plan (503E11101)LS1$78,543$33,000$85,000$80,000
90Unclassified excavation (503E21300)LS1$16,709$8,000.00$16,500$35,000
91Epoxy coated steel reinforcement (509E10000)LB3,727$2.00$2.50$2.80$2.50
92Class QC1 concrete, retaining/wingwall not including footing (511E46010)CY10$3,512.00$1,050.00$2,600.00$2,300.00
93Class QC1 concrete, footing (511E46510)CY27$1,597.00$825.00$1,000.00$880.00
94Class QC1 concrete, headwall (511E46610)CY1$3,384.00$1,600.00$1,800.00$5,400.00
95Sealing of concrete surfaces (epoxy-urethane) (512E10100)SY44$75.00$45.00$65.00$75.00
96Type 2 waterproofing (512E33000)SY79$165.00$20.00$26.50$60.00
97Type 3 waterproofing (512E33010)SY92$259.00$35.00$65.00$70.00
981" preformed expansion joint filler (516E13600)SF26$3.00$20.00$10.00$1.50
99Porous backfill with geotextile fabric (518E21200)CY12$305.00$200.00$300.00$330.00
10010' X 4' conduit, type A, 706.05 (611E94980)FT62$2,402.00$3,425.00$2,350.00$2,000.00
101Premium for contract performance bond and for payment bond (103E05000)LS1$18,896$115,000$18,500$35,000
102Maintaining traffic (614E11000)LS1$100,604$120,000$95,000$100,000
103Field office, type A (619E16000)MNTH7$1,800.00$750.00$2,500.00$1,500.00
104Construction layout stakes and surveying (623E10000)LS1$25,793$23,000$39,000$49,000
105Preconstruction survey monument verification and report (623E50000)LS1$4,283.00$1,000.00$1,600.00$5,000.00
106Post construction survey monument verification and report (623E51000)LS1$4,283.00$1,000.00$1,600.00$5,000.00
107Mobilization (624E10000)LS1$40,000$100,000$100,000$125,000
ODOT contract 260427: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of October 1, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy