ODOT contract 260505 bid tabulation

LOR-SR 252-03.65 (CULVERT REPLACEMENT). Let by Ohio DOT on November 12, 2026, LOR. 7 bids received; low bid $508,373 by Crawford Construction Company Inc, -1.3% against the engineer's estimate of $515,000.

Owner
Ohio DOT
Letting
12 NOV 2026
Pay items
56
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Crawford Construction Company Inc$508,373Low-1.0%
2TK Excavating & Grading LLC$515,135+1.0%0.0%
3Eius Company$552,997+9.0%+7.0%
4Grassbaugh LLC$617,506+21%+20%
5Fechko Excavating LLC$649,936+28%+26%
6Madex Construction Co$695,395+37%+35%
7Fabrizi Trucking & Paving Co Inc$846,072+66%+64%
ODOT contract 260505: bids by rank

Engineer's estimate: $515,000.

Bid tabulation

LinePay itemUnitQuantity1. Crawford Construction Company Inc2. TK Excavating & Grading LLC3. Eius Company4. Grassbaugh LLC5. Fechko Excavating LLC6. Madex Construction Co
1Clearing and grubbing (201E11000)LS1$3,000.00$16,976$6,192.00$5,000.00$17,000$16,739
2Special - tree removed, 4"-12" (201E20010)EACH9$490.00$0.15$175.44$150.00$145.00$115.79
3Tree removed, 18" diameter (201E21800)EACH13$350.00$0.10$529.62$600.00$550.00$231.58
4Stump removed, 18" diameter (201E26500)EACH1$460.00$1.15$387.00$2,000.00$215.00$115.79
5Stump removed, 30" diameter (201E26510)EACH1$600.00$1.15$645.00$2,500.00$315.00$289.47
6Structure removed, as per plan (202E11001)LS1$14,400$26,070$7,740.00$45,000$97,200$22,165
7Pavement removed (202E23000)SY276$12.00$11.75$5.16$17.00$27.75$27.93
8Excavation (203E10000)CY69$43.00$28.00$12.90$75.00$45.50$28.95
9Embankment (203E20000)CY1,234$34.00$29.00$53.60$38.00$17.00$34.74
10Subgrade compaction (204E10000)SY319$2.30$3.50$2.58$5.00$3.00$3.47
11Monument assembly, type C (623E38500)EACH1$2,660.00$1.15$3,064.50$5,000.00$785.00$2,894.74
12Preconstruction survey monument verification and report (623E50000)LS1$930.00$1.15$1,890.00$4,000.00$153.00$5,789.47
13Post construction survey monument verification and report (623E51000)LS1$930.00$1.15$1,890.00$4,000.00$153.00$5,789.47
14Rock channel protection, type A with filter (601E32000)CY115$150.00$166.00$180.01$175.00$153.00$292.27
15Soil analysis test (659E00100)EACH2$100.00$59.00$105.00$100.00$55.00$289.47
16Topsoil (659E00300)CY141$41.00$36.00$71.40$40.00$83.00$75.26
17Seeding and mulching (659E10000)SY1,266$4.00$4.50$3.99$3.00$3.60$4.63
18Repair seeding and mulching (659E14000)SY63$2.00$3.50$2.10$3.00$3.60$2.32
19Inter-seeding (659E15000)SY63$0.11$1.25$0.11$3.00$3.60$2.32
20Commercial fertilizer (659E20000)TON0.18$2,200.00$1,230.00$1,092.00$8,000.00$1,480.00$2,200.00
21Lime (659E31000)ACRE0.26$476.00$44.50$35.69$3,500.00$1,500.00$578.96
22Water (659E35000)MGAL7.01$3.00$1.50$1.05$1.00$50.00$17.35
23Slope erosion protection mat, type B (670E00520)SY331$3.60$28.00$3.52$8.00$5.50$4.63
24Erosion control (832E30000)EACH5,000$1.00$1.00$1.00$1.00$1.00$1.00
25Aggregate drains (605E31100)FT96$38.00$83.00$20.23$22.00$34.00$34.74
2610' X 5' conduit, type A, 706.05 (611E95000)FT80$1,120.00$1,377.00$1,756.22$1,800.00$1,220.00$1,785.76
27Pavement planing, asphalt concrete (varies 0" to 3 (254E01000)SY138$75.00$35.00$31.50$37.00$30.00$34.74
28Asphalt concrete base, PG64-22, (449) (301E56000)CY76$348.00$415.00$358.05$450.00$350.00$455.26
29Aggregate base (304E20000)CY96$151.00$95.00$137.66$100.00$76.00$115.79
30Tack coat (407E10000)GAL62$5.35$29.50$26.25$2.75$2.00$2.32
31Prime coat, as per plan (408E10001)GAL74$10.00$14.00$12.60$9.00$5.00$5.79
32Asphalt concrete surface course, 9.5 MM, type A (4 (442E22001)CY37$749.00$1,530.00$1,366.05$700.00$1,250.00$1,547.37
33Raised pavement marker removed (621E54000)EACH2$115.00$119.00$20.64$400.00$50.00$28.95
34Ground mounted support, no. 3 post, as per plan (630E03101)FT24$101.00$29.50$61.87$35.00$25.00$70.53
35Sign, flat sheet (630E80100)SF2$91.00$119.00$89.25$55.00$100.00$82.11
36Removal of ground mounted sign and disposal (630E84900)EACH3$77.00$30.50$36.75$40.00$25.00$28.95
37Removal of ground mounted post support and disposal (630E86002)EACH2$115.00$31.75$42.00$50.00$25.00$28.95
38Edge line, 6", type 1 (642E00104)MI0.08$10,700$11,765$12,185$25,000$10,000$13,895
39Center line, type 1 (642E00300)MI0.04$16,050$17,645$16,259$45,000$15,000$18,526
40Detour signing (614E12420)LS1$9,100.00$10,000$12,364$20,000$8,500.00$13,895
41Portable changeable message sign, as per plan (614E18601)SNMT4$522.00$1,147.00$997.50$1,200.00$975.00$1,273.68
42Cofferdams and excavation bracing (503E11100)LS1$2,500.00$1,425.00$9,607.65$25,000$25,000$22,189
43Unclassified excavation (503E21300)LS1$51,000$6,953.00$4,386.00$15,000$56,400$8,469.00
44Epoxy coated steel reinforcement (509E10000)LB4,931$2.60$1.20$2.20$3.50$3.00$4.05
45Class QC1 concrete, retaining/wingwall not including footing (511E46010)CY16$1,316.00$2,806.00$1,704.94$1,300.00$1,840.00$3,376.69
46Class QC1 concrete, footing (511E46510)CY32$857.00$530.00$1,411.50$800.00$1,285.00$1,301.13
47Class QC1 concrete, headwall (511E46610)CY2.40$2,100.00$1,505.00$1,994.94$2,600.00$1,718.00$2,315.79
48Sealing of concrete surfaces (epoxy-urethane) (512E10100)SY48$45.00$37.00$42.66$65.00$62.00$102.76
49Type 2 waterproofing (512E33000)SY248$33.00$12.50$31.73$15.00$19.00$40.53
501" preformed expansion joint filler (516E13600)SF51$10.00$0.01$6.11$17.50$5.00$11.58
51Porous backfill (518E21220)LS1$2,300.00$3,854.00$2,506.80$5,000.00$1,706.00$5,789.60
52Premium for contract performance bond and for payment bond (103E05000)LS1$7,800.00$23,750$6,826.92$7,500.00$6,160.00$14,821
53Maintaining traffic (614E11000)LS1$6,000.00$13,235$2,838.00$10,000$2,060.00$8,684.21
54Field office, type B (619E16010)MNTH3$800.00$588.00$4,150.50$3,300.00$1,400.00$1,736.84
55Construction layout stakes and surveying (623E10000)LS1$4,400.00$4,117.00$3,810.00$15,000$5,841.00$17,368
56Mobilization (624E10000)LS1$49,400$13,185$9,963.87$25,000$51,425$28,991
ODOT contract 260505: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of November 12, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy