ODOT contract 260505 bid tabulation
LOR-SR 252-03.65 (CULVERT REPLACEMENT). Let by Ohio DOT on November 12, 2026, LOR. 7 bids received; low bid $508,373 by Crawford Construction Company Inc, -1.3% against the engineer's estimate of $515,000.
- Owner
- Ohio DOT
- Letting
- 12 NOV 2026
- Pay items
- 56
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Crawford Construction Company Inc | $508,373 | Low | -1.0% |
| 2 | TK Excavating & Grading LLC | $515,135 | +1.0% | 0.0% |
| 3 | Eius Company | $552,997 | +9.0% | +7.0% |
| 4 | Grassbaugh LLC | $617,506 | +21% | +20% |
| 5 | Fechko Excavating LLC | $649,936 | +28% | +26% |
| 6 | Madex Construction Co | $695,395 | +37% | +35% |
| 7 | Fabrizi Trucking & Paving Co Inc | $846,072 | +66% | +64% |
Engineer's estimate: $515,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Crawford Construction Company Inc | 2. TK Excavating & Grading LLC | 3. Eius Company | 4. Grassbaugh LLC | 5. Fechko Excavating LLC | 6. Madex Construction Co |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $3,000.00 | $16,976 | $6,192.00 | $5,000.00 | $17,000 | $16,739 |
| 2 | Special - tree removed, 4"-12" (201E20010) | EACH | 9 | $490.00 | $0.15 | $175.44 | $150.00 | $145.00 | $115.79 |
| 3 | Tree removed, 18" diameter (201E21800) | EACH | 13 | $350.00 | $0.10 | $529.62 | $600.00 | $550.00 | $231.58 |
| 4 | Stump removed, 18" diameter (201E26500) | EACH | 1 | $460.00 | $1.15 | $387.00 | $2,000.00 | $215.00 | $115.79 |
| 5 | Stump removed, 30" diameter (201E26510) | EACH | 1 | $600.00 | $1.15 | $645.00 | $2,500.00 | $315.00 | $289.47 |
| 6 | Structure removed, as per plan (202E11001) | LS | 1 | $14,400 | $26,070 | $7,740.00 | $45,000 | $97,200 | $22,165 |
| 7 | Pavement removed (202E23000) | SY | 276 | $12.00 | $11.75 | $5.16 | $17.00 | $27.75 | $27.93 |
| 8 | Excavation (203E10000) | CY | 69 | $43.00 | $28.00 | $12.90 | $75.00 | $45.50 | $28.95 |
| 9 | Embankment (203E20000) | CY | 1,234 | $34.00 | $29.00 | $53.60 | $38.00 | $17.00 | $34.74 |
| 10 | Subgrade compaction (204E10000) | SY | 319 | $2.30 | $3.50 | $2.58 | $5.00 | $3.00 | $3.47 |
| 11 | Monument assembly, type C (623E38500) | EACH | 1 | $2,660.00 | $1.15 | $3,064.50 | $5,000.00 | $785.00 | $2,894.74 |
| 12 | Preconstruction survey monument verification and report (623E50000) | LS | 1 | $930.00 | $1.15 | $1,890.00 | $4,000.00 | $153.00 | $5,789.47 |
| 13 | Post construction survey monument verification and report (623E51000) | LS | 1 | $930.00 | $1.15 | $1,890.00 | $4,000.00 | $153.00 | $5,789.47 |
| 14 | Rock channel protection, type A with filter (601E32000) | CY | 115 | $150.00 | $166.00 | $180.01 | $175.00 | $153.00 | $292.27 |
| 15 | Soil analysis test (659E00100) | EACH | 2 | $100.00 | $59.00 | $105.00 | $100.00 | $55.00 | $289.47 |
| 16 | Topsoil (659E00300) | CY | 141 | $41.00 | $36.00 | $71.40 | $40.00 | $83.00 | $75.26 |
| 17 | Seeding and mulching (659E10000) | SY | 1,266 | $4.00 | $4.50 | $3.99 | $3.00 | $3.60 | $4.63 |
| 18 | Repair seeding and mulching (659E14000) | SY | 63 | $2.00 | $3.50 | $2.10 | $3.00 | $3.60 | $2.32 |
| 19 | Inter-seeding (659E15000) | SY | 63 | $0.11 | $1.25 | $0.11 | $3.00 | $3.60 | $2.32 |
| 20 | Commercial fertilizer (659E20000) | TON | 0.18 | $2,200.00 | $1,230.00 | $1,092.00 | $8,000.00 | $1,480.00 | $2,200.00 |
| 21 | Lime (659E31000) | ACRE | 0.26 | $476.00 | $44.50 | $35.69 | $3,500.00 | $1,500.00 | $578.96 |
| 22 | Water (659E35000) | MGAL | 7.01 | $3.00 | $1.50 | $1.05 | $1.00 | $50.00 | $17.35 |
| 23 | Slope erosion protection mat, type B (670E00520) | SY | 331 | $3.60 | $28.00 | $3.52 | $8.00 | $5.50 | $4.63 |
| 24 | Erosion control (832E30000) | EACH | 5,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 25 | Aggregate drains (605E31100) | FT | 96 | $38.00 | $83.00 | $20.23 | $22.00 | $34.00 | $34.74 |
| 26 | 10' X 5' conduit, type A, 706.05 (611E95000) | FT | 80 | $1,120.00 | $1,377.00 | $1,756.22 | $1,800.00 | $1,220.00 | $1,785.76 |
| 27 | Pavement planing, asphalt concrete (varies 0" to 3 (254E01000) | SY | 138 | $75.00 | $35.00 | $31.50 | $37.00 | $30.00 | $34.74 |
| 28 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 76 | $348.00 | $415.00 | $358.05 | $450.00 | $350.00 | $455.26 |
| 29 | Aggregate base (304E20000) | CY | 96 | $151.00 | $95.00 | $137.66 | $100.00 | $76.00 | $115.79 |
| 30 | Tack coat (407E10000) | GAL | 62 | $5.35 | $29.50 | $26.25 | $2.75 | $2.00 | $2.32 |
| 31 | Prime coat, as per plan (408E10001) | GAL | 74 | $10.00 | $14.00 | $12.60 | $9.00 | $5.00 | $5.79 |
| 32 | Asphalt concrete surface course, 9.5 MM, type A (4 (442E22001) | CY | 37 | $749.00 | $1,530.00 | $1,366.05 | $700.00 | $1,250.00 | $1,547.37 |
| 33 | Raised pavement marker removed (621E54000) | EACH | 2 | $115.00 | $119.00 | $20.64 | $400.00 | $50.00 | $28.95 |
| 34 | Ground mounted support, no. 3 post, as per plan (630E03101) | FT | 24 | $101.00 | $29.50 | $61.87 | $35.00 | $25.00 | $70.53 |
| 35 | Sign, flat sheet (630E80100) | SF | 2 | $91.00 | $119.00 | $89.25 | $55.00 | $100.00 | $82.11 |
| 36 | Removal of ground mounted sign and disposal (630E84900) | EACH | 3 | $77.00 | $30.50 | $36.75 | $40.00 | $25.00 | $28.95 |
| 37 | Removal of ground mounted post support and disposal (630E86002) | EACH | 2 | $115.00 | $31.75 | $42.00 | $50.00 | $25.00 | $28.95 |
| 38 | Edge line, 6", type 1 (642E00104) | MI | 0.08 | $10,700 | $11,765 | $12,185 | $25,000 | $10,000 | $13,895 |
| 39 | Center line, type 1 (642E00300) | MI | 0.04 | $16,050 | $17,645 | $16,259 | $45,000 | $15,000 | $18,526 |
| 40 | Detour signing (614E12420) | LS | 1 | $9,100.00 | $10,000 | $12,364 | $20,000 | $8,500.00 | $13,895 |
| 41 | Portable changeable message sign, as per plan (614E18601) | SNMT | 4 | $522.00 | $1,147.00 | $997.50 | $1,200.00 | $975.00 | $1,273.68 |
| 42 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $2,500.00 | $1,425.00 | $9,607.65 | $25,000 | $25,000 | $22,189 |
| 43 | Unclassified excavation (503E21300) | LS | 1 | $51,000 | $6,953.00 | $4,386.00 | $15,000 | $56,400 | $8,469.00 |
| 44 | Epoxy coated steel reinforcement (509E10000) | LB | 4,931 | $2.60 | $1.20 | $2.20 | $3.50 | $3.00 | $4.05 |
| 45 | Class QC1 concrete, retaining/wingwall not including footing (511E46010) | CY | 16 | $1,316.00 | $2,806.00 | $1,704.94 | $1,300.00 | $1,840.00 | $3,376.69 |
| 46 | Class QC1 concrete, footing (511E46510) | CY | 32 | $857.00 | $530.00 | $1,411.50 | $800.00 | $1,285.00 | $1,301.13 |
| 47 | Class QC1 concrete, headwall (511E46610) | CY | 2.40 | $2,100.00 | $1,505.00 | $1,994.94 | $2,600.00 | $1,718.00 | $2,315.79 |
| 48 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 48 | $45.00 | $37.00 | $42.66 | $65.00 | $62.00 | $102.76 |
| 49 | Type 2 waterproofing (512E33000) | SY | 248 | $33.00 | $12.50 | $31.73 | $15.00 | $19.00 | $40.53 |
| 50 | 1" preformed expansion joint filler (516E13600) | SF | 51 | $10.00 | $0.01 | $6.11 | $17.50 | $5.00 | $11.58 |
| 51 | Porous backfill (518E21220) | LS | 1 | $2,300.00 | $3,854.00 | $2,506.80 | $5,000.00 | $1,706.00 | $5,789.60 |
| 52 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $7,800.00 | $23,750 | $6,826.92 | $7,500.00 | $6,160.00 | $14,821 |
| 53 | Maintaining traffic (614E11000) | LS | 1 | $6,000.00 | $13,235 | $2,838.00 | $10,000 | $2,060.00 | $8,684.21 |
| 54 | Field office, type B (619E16010) | MNTH | 3 | $800.00 | $588.00 | $4,150.50 | $3,300.00 | $1,400.00 | $1,736.84 |
| 55 | Construction layout stakes and surveying (623E10000) | LS | 1 | $4,400.00 | $4,117.00 | $3,810.00 | $15,000 | $5,841.00 | $17,368 |
| 56 | Mobilization (624E10000) | LS | 1 | $49,400 | $13,185 | $9,963.87 | $25,000 | $51,425 | $28,991 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of November 12, 2026. Compiled by Mirage Metrics.