ODOT contract 260059 bid tabulation

MER-FT RECOVERY SIDEWALKS SA22 (SIDEWALK). Let by Ohio DOT on January 29, 2026, MER. 4 bids received; low bid $888,655 by Jutte Excavating Inc, -11% against the engineer's estimate of $998,000.

Owner
Ohio DOT
Letting
29 JAN 2026
Pay items
103
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Jutte Excavating Inc$888,655Low-11%
2D L Smith Concrete LLC$1,012,635+14%+1.0%
3Brumbaugh Construction Inc$1,018,312+15%+2.0%
4L J Deweese Co Inc$1,219,222+37%+22%
ODOT contract 260059: bids by rank

Engineer's estimate: $998,000.

Bid tabulation

LinePay itemUnitQuantity1. Jutte Excavating Inc2. D L Smith Concrete LLC3. Brumbaugh Construction Inc4. L J Deweese Co Inc
1Clearing and grubbing (201E11000)LS1$30,000$4,000.00$24,000$10,000
2Pavement removed (202E23000)SY917$12.00$16.00$15.00$27.00
3Walk removed (202E30000)SF395$2.00$4.00$8.00$7.00
4Curb and gutter removed (202E32500)FT163$5.00$10.00$20.00$25.00
5Pipe removed, 24" and under (202E35100)FT45$5.00$25.00$18.00$45.00
6Pipe removed, over 24" diameter (202E35200)FT10$5.00$25.00$20.00$65.00
7Catch basin removed (202E58100)EACH2$150.00$650.00$800.00$900.00
8Excavation (203E10000)CY425$40.00$85.00$75.00$40.00
9Embankment (203E20000)CY242$30.00$68.00$75.00$40.00
104" concrete walk (608E10000)SF31,891$7.00$9.00$8.00$9.00
11Curb ramp (608E52000)SF2,146$2.00$25.00$22.00$28.00
12Preconstruction survey monument verification and report (623E50000)LS1$500.00$3,500.00$3,650.00$3,000.00
13Post construction survey monument verification and report (623E51000)LS1$500.00$3,500.00$3,650.00$3,000.00
14Topsoil furnished and placed (653E10000)CY69$26.00$65.00$75.00$100.00
15Special - mailbox removed and reset (690E50350)EACH14$200.00$150.00$305.00$250.00
16Topsoil (659E00300)CY483$26.00$62.00$75.00$70.00
17Seeding and mulching, class 1 (659E00500)SY5,449$1.75$5.75$2.00$2.00
18Repair seeding and mulching (659E14000)SY217$1.75$5.75$1.75$2.00
19Inter-seeding (659E15000)SY217$1.75$5.75$1.75$2.00
20Commercial fertilizer (659E20000)TON0.60$760.00$260.00$850.00$1,000.00
21Lime (659E31000)ACRE0.90$50.00$55.00$50.00$5.00
22Water (659E35000)MGAL24$50.00$18.00$50.00$5.00
23Slope erosion protection (670E00500)SY618$4.80$8.50$5.50$6.00
24Storm water pollution prevention plan (832E15000)LS1$2,500.00$2,000.00$3,000.00$3,500.00
25Storm water pollution prevention inspections (832E15002)LS1$13,000$13,000$6,750.00$8,000.00
26Storm water pollution prevention inspection software (832E15010)LS1$8,000.00$7,250.00$11,000$9,000.00
27Erosion control (832E30000)EACH10,000$1.00$1.00$1.00$1.00
286" conduit, type B (611E00900)FT23$20.00$35.00$54.00$80.00
296" conduit, type D (611E01200)FT63$20.00$35.00$65.00$80.00
308" conduit, type B (611E01800)FT16$30.00$38.00$67.00$125.00
318" conduit, type C (611E02000)FT91$30.00$38.00$47.00$105.00
3212" conduit, type D (611E04900)FT119$40.00$46.00$49.00$125.00
3318" conduit, type B (611E07400)FT3$45.00$50.00$380.00$350.00
3424" conduit, type B (611E10400)FT4$70.00$58.00$400.00$400.00
3530" conduit, type C (611E13600)FT10$100.00$72.00$200.00$300.00
36Conduit, misc.:type B for drainage discharge conti (611E97400)FT20$10.00$67.00$13.00$25.00
37Conduit, misc.:type C for drainage discharge conti (611E97400)FT20$10.00$67.00$13.00$25.00
38Conduit, misc.:type E for drainage discharge conti (611E97400)FT20$10.00$67.00$13.00$25.00
39Conduit, misc.:type F for drainage discharge conti (611E97400)FT20$10.00$67.00$13.00$25.00
40Catch basin, no. 7 (611E98390)EACH3$3,500.00$2,250.00$2,750.00$5,000.00
41Catch basin, no. 7, as per plan (611E98391)EACH1$3,500.00$2,250.00$3,400.00$5,000.00
42Catch basin, no. 2-2B (611E98470)EACH2$3,250.00$2,450.00$2,000.00$3,000.00
43Catch basin, no. 2-3, as per plan (611E98511)EACH1$4,500.00$3,150.00$3,250.00$5,000.00
44Manhole, no. 3 (611E99574)EACH1$8,000.00$4,150.00$3,250.00$6,500.00
45Manhole adjusted to grade (611E99654)EACH1$250.00$1,285.00$300.00$1,000.00
46Asphalt concrete base, PG64-22, (449) (301E56000)CY9$925.00$305.00$1,070.00$1,000.00
47Aggregate base (304E20000)CY89$74.00$72.00$86.00$125.00
48Non-tracking tack coat (407E20000)GAL9$6.00$42.00$25.00$50.00
49Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000)CY3$1,590.00$360.00$1,070.00$1,000.00
50Asphalt concrete intermediate course, type 2, (449) (441E70300)CY5$1,035.00$320.00$1,090.00$1,000.00
516" non-reinforced concrete pavement, class QC 1P, as per plan (452E10011)SY574$66.00$100.00$75.00$125.00
529" non-reinforced concrete pavement, class QC 1P, as per plan (452E13011)SY232$83.00$120.00$95.00$170.00
53Combination curb and gutter, type 2, as per plan (609E12001)FT163$30.00$55.00$47.00$60.00
54Fire hydrant extended and adjusted to grade (638E10300)EACH5$5,000.00$1,650.00$750.00$2,000.00
55Valve box adjusted to grade (638E10800)EACH6$150.00$685.00$300.00$350.00
56Drainage structure, misc.:cleanout adjusted to gra (611E99900)EACH1$150.00$1,150.00$300.00$350.00
574" conduit, type E (611E00400)FT140$5.00$6.00$15.00$12.00
58Connection, fused pull apart, as per plan (625E00451)EACH30$10.00$125.00$147.00$150.00
59Connection, unfused pull apart (625E00460)EACH10$8.00$125.00$158.00$150.00
60Connection, unfused permanent (625E00480)EACH6$80.00$120.00$147.00$170.00
61Light pole, decorative, as per plan (625E10481)EACH8$8,000.00$5,700.00$6,105.00$5,500.00
62Light pole foundation, 24" X 6' deep (625E14000)EACH8$3,000.00$2,600.00$2,525.00$7,500.00
63No. 6 AWG 600 volt distribution cable (625E22990)FT2,646$2.00$4.00$3.50$3.00
64No. 8 AWG 600 volt distribution cable (625E23304)FT3,204$3.00$3.50$3.00$2.50
65No. 12 AWG pole and bracket cable (625E23410)FT1,308$2.00$2.50$1.00$2.50
66Conduit, 2", 725.051 (625E25408)FT452$10.00$14.00$4.00$6.00
67Conduit, 3", 725.051 (625E25504)FT150$12.00$17.00$6.00$8.00
68Conduit, 4", 725.051 (625E25604)FT85$14.00$19.00$10.50$9.00
69Conduit, jacked or drilled, 725.052, as per plan (625E25909)FT69$15.00$48.00$25.00$45.00
70Conduit, jacked or drilled, 725.052, as per plan (625E25909)FT171$17.00$55.50$27.00$65.00
71Conduit, jacked or drilled, 725.052, as per plan (625E25909)FT81$20.00$60.00$32.00$50.00
72Luminaire, decorative, as per plan ies-III-M, LED, (625E27551)EACH10$5,000.00$3,300.00$3,580.00$3,300.00
73Trench (625E29000)FT687$10.00$15.00$17.00$11.00
74Pull box, 725.06, size 7 (625E30520)EACH7$1,000.00$1,750.00$2,750.00$900.00
75Ground rod (625E32000)EACH10$100.00$300.00$210.00$300.00
76Power service, as per plan (625E34001)EACH2$3,000.00$11,500$6,500.00$13,500
77Underground warning marking tape (625E36010)FT687$1.00$3.50$0.50$2.00
78Power cable, 3 conductor, no. 2 AWG (632E69320)FT133$12.00$16.00$17.00$4.00
79Ground mounted support, no. 3 post (630E03100)FT181$15.00$18.00$10.00$12.00
80Sign, flat sheet (630E80100)SF106$25.00$19.00$28.00$25.00
81Removal of ground mounted sign and disposal (630E84900)EACH3$50.00$24.00$21.00$20.00
82Removal of ground mounted sign and reerection (630E85100)EACH32$100.00$50.00$47.00$60.00
83Removal of ground mounted post support and disposal (630E86002)EACH1$50.00$30.00$26.00$40.00
84Removal of ground mounted post support and reerection (630E86010)EACH20$100.00$72.00$68.00$115.00
85Edge line, 4" (644E00100)MI0.03$11,204$11,500$11,800$12,000
86Channelizing line, 8" (644E00400)FT78$3.00$3.50$3.00$3.00
87Stop line (644E00500)FT70$12.75$13.50$13.00$13.00
88Crosswalk line, 12" (644E00620)FT409$6.35$7.00$7.00$7.00
89Crosswalk line, 24" (644E00630)FT380$11.45$12.00$12.00$12.00
90Lane arrow (644E01300)EACH2$200.00$215.00$210.00$225.00
91Yield line (644E20800)FT38$25.00$27.00$26.00$30.00
92Removal of pavement marking (644E30000)FT142$20.62$25.00$21.00$21.00
93Light pole, decorative, as per plan (625E10481)EACH2$7,000.00$5,700.00$6,100.00$5,500.00
94Light pole foundation, 24" X 6' deep (625E14000)EACH2$3,000.00$2,500.00$2,500.00$7,400.00
95Ground rod (625E32000)EACH2$100.00$300.00$210.00$270.00
96Signing, misc.:rectangular rapid flashing beacon ( (630E97700)EACH2$7,500.00$6,250.00$7,900.00$6,500.00
97Accessible pedestrian pushbutton (632E20750)EACH2$750.00$858.00$750.00$900.00
98Signal cable, 3 conductor, no. 14 AWG (632E40300)FT490$3.00$3.00$3.00$3.00
99Signal cable, 5 conductor, no. 14 AWG (632E40500)FT498$3.00$3.50$4.00$3.25
100Premium for contract performance bond and for payment bond (103E05000)LS1$27,000$15,000$8,000.00$12,500
101Maintaining traffic (614E11000)LS1$23,500$11,000$50,000$65,000
102Construction layout stakes and surveying (623E10000)LS1$34,000$7,800.00$11,500$25,000
103Mobilization (624E10000)LS1$28,000$15,000$45,029$58,000
ODOT contract 260059: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of January 29, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy