ODOT contract 260059 bid tabulation
MER-FT RECOVERY SIDEWALKS SA22 (SIDEWALK). Let by Ohio DOT on January 29, 2026, MER. 4 bids received; low bid $888,655 by Jutte Excavating Inc, -11% against the engineer's estimate of $998,000.
- Owner
- Ohio DOT
- Letting
- 29 JAN 2026
- Pay items
- 103
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Jutte Excavating Inc | $888,655 | Low | -11% |
| 2 | D L Smith Concrete LLC | $1,012,635 | +14% | +1.0% |
| 3 | Brumbaugh Construction Inc | $1,018,312 | +15% | +2.0% |
| 4 | L J Deweese Co Inc | $1,219,222 | +37% | +22% |
Engineer's estimate: $998,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Jutte Excavating Inc | 2. D L Smith Concrete LLC | 3. Brumbaugh Construction Inc | 4. L J Deweese Co Inc |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $30,000 | $4,000.00 | $24,000 | $10,000 |
| 2 | Pavement removed (202E23000) | SY | 917 | $12.00 | $16.00 | $15.00 | $27.00 |
| 3 | Walk removed (202E30000) | SF | 395 | $2.00 | $4.00 | $8.00 | $7.00 |
| 4 | Curb and gutter removed (202E32500) | FT | 163 | $5.00 | $10.00 | $20.00 | $25.00 |
| 5 | Pipe removed, 24" and under (202E35100) | FT | 45 | $5.00 | $25.00 | $18.00 | $45.00 |
| 6 | Pipe removed, over 24" diameter (202E35200) | FT | 10 | $5.00 | $25.00 | $20.00 | $65.00 |
| 7 | Catch basin removed (202E58100) | EACH | 2 | $150.00 | $650.00 | $800.00 | $900.00 |
| 8 | Excavation (203E10000) | CY | 425 | $40.00 | $85.00 | $75.00 | $40.00 |
| 9 | Embankment (203E20000) | CY | 242 | $30.00 | $68.00 | $75.00 | $40.00 |
| 10 | 4" concrete walk (608E10000) | SF | 31,891 | $7.00 | $9.00 | $8.00 | $9.00 |
| 11 | Curb ramp (608E52000) | SF | 2,146 | $2.00 | $25.00 | $22.00 | $28.00 |
| 12 | Preconstruction survey monument verification and report (623E50000) | LS | 1 | $500.00 | $3,500.00 | $3,650.00 | $3,000.00 |
| 13 | Post construction survey monument verification and report (623E51000) | LS | 1 | $500.00 | $3,500.00 | $3,650.00 | $3,000.00 |
| 14 | Topsoil furnished and placed (653E10000) | CY | 69 | $26.00 | $65.00 | $75.00 | $100.00 |
| 15 | Special - mailbox removed and reset (690E50350) | EACH | 14 | $200.00 | $150.00 | $305.00 | $250.00 |
| 16 | Topsoil (659E00300) | CY | 483 | $26.00 | $62.00 | $75.00 | $70.00 |
| 17 | Seeding and mulching, class 1 (659E00500) | SY | 5,449 | $1.75 | $5.75 | $2.00 | $2.00 |
| 18 | Repair seeding and mulching (659E14000) | SY | 217 | $1.75 | $5.75 | $1.75 | $2.00 |
| 19 | Inter-seeding (659E15000) | SY | 217 | $1.75 | $5.75 | $1.75 | $2.00 |
| 20 | Commercial fertilizer (659E20000) | TON | 0.60 | $760.00 | $260.00 | $850.00 | $1,000.00 |
| 21 | Lime (659E31000) | ACRE | 0.90 | $50.00 | $55.00 | $50.00 | $5.00 |
| 22 | Water (659E35000) | MGAL | 24 | $50.00 | $18.00 | $50.00 | $5.00 |
| 23 | Slope erosion protection (670E00500) | SY | 618 | $4.80 | $8.50 | $5.50 | $6.00 |
| 24 | Storm water pollution prevention plan (832E15000) | LS | 1 | $2,500.00 | $2,000.00 | $3,000.00 | $3,500.00 |
| 25 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $13,000 | $13,000 | $6,750.00 | $8,000.00 |
| 26 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $8,000.00 | $7,250.00 | $11,000 | $9,000.00 |
| 27 | Erosion control (832E30000) | EACH | 10,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 28 | 6" conduit, type B (611E00900) | FT | 23 | $20.00 | $35.00 | $54.00 | $80.00 |
| 29 | 6" conduit, type D (611E01200) | FT | 63 | $20.00 | $35.00 | $65.00 | $80.00 |
| 30 | 8" conduit, type B (611E01800) | FT | 16 | $30.00 | $38.00 | $67.00 | $125.00 |
| 31 | 8" conduit, type C (611E02000) | FT | 91 | $30.00 | $38.00 | $47.00 | $105.00 |
| 32 | 12" conduit, type D (611E04900) | FT | 119 | $40.00 | $46.00 | $49.00 | $125.00 |
| 33 | 18" conduit, type B (611E07400) | FT | 3 | $45.00 | $50.00 | $380.00 | $350.00 |
| 34 | 24" conduit, type B (611E10400) | FT | 4 | $70.00 | $58.00 | $400.00 | $400.00 |
| 35 | 30" conduit, type C (611E13600) | FT | 10 | $100.00 | $72.00 | $200.00 | $300.00 |
| 36 | Conduit, misc.:type B for drainage discharge conti (611E97400) | FT | 20 | $10.00 | $67.00 | $13.00 | $25.00 |
| 37 | Conduit, misc.:type C for drainage discharge conti (611E97400) | FT | 20 | $10.00 | $67.00 | $13.00 | $25.00 |
| 38 | Conduit, misc.:type E for drainage discharge conti (611E97400) | FT | 20 | $10.00 | $67.00 | $13.00 | $25.00 |
| 39 | Conduit, misc.:type F for drainage discharge conti (611E97400) | FT | 20 | $10.00 | $67.00 | $13.00 | $25.00 |
| 40 | Catch basin, no. 7 (611E98390) | EACH | 3 | $3,500.00 | $2,250.00 | $2,750.00 | $5,000.00 |
| 41 | Catch basin, no. 7, as per plan (611E98391) | EACH | 1 | $3,500.00 | $2,250.00 | $3,400.00 | $5,000.00 |
| 42 | Catch basin, no. 2-2B (611E98470) | EACH | 2 | $3,250.00 | $2,450.00 | $2,000.00 | $3,000.00 |
| 43 | Catch basin, no. 2-3, as per plan (611E98511) | EACH | 1 | $4,500.00 | $3,150.00 | $3,250.00 | $5,000.00 |
| 44 | Manhole, no. 3 (611E99574) | EACH | 1 | $8,000.00 | $4,150.00 | $3,250.00 | $6,500.00 |
| 45 | Manhole adjusted to grade (611E99654) | EACH | 1 | $250.00 | $1,285.00 | $300.00 | $1,000.00 |
| 46 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 9 | $925.00 | $305.00 | $1,070.00 | $1,000.00 |
| 47 | Aggregate base (304E20000) | CY | 89 | $74.00 | $72.00 | $86.00 | $125.00 |
| 48 | Non-tracking tack coat (407E20000) | GAL | 9 | $6.00 | $42.00 | $25.00 | $50.00 |
| 49 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 3 | $1,590.00 | $360.00 | $1,070.00 | $1,000.00 |
| 50 | Asphalt concrete intermediate course, type 2, (449) (441E70300) | CY | 5 | $1,035.00 | $320.00 | $1,090.00 | $1,000.00 |
| 51 | 6" non-reinforced concrete pavement, class QC 1P, as per plan (452E10011) | SY | 574 | $66.00 | $100.00 | $75.00 | $125.00 |
| 52 | 9" non-reinforced concrete pavement, class QC 1P, as per plan (452E13011) | SY | 232 | $83.00 | $120.00 | $95.00 | $170.00 |
| 53 | Combination curb and gutter, type 2, as per plan (609E12001) | FT | 163 | $30.00 | $55.00 | $47.00 | $60.00 |
| 54 | Fire hydrant extended and adjusted to grade (638E10300) | EACH | 5 | $5,000.00 | $1,650.00 | $750.00 | $2,000.00 |
| 55 | Valve box adjusted to grade (638E10800) | EACH | 6 | $150.00 | $685.00 | $300.00 | $350.00 |
| 56 | Drainage structure, misc.:cleanout adjusted to gra (611E99900) | EACH | 1 | $150.00 | $1,150.00 | $300.00 | $350.00 |
| 57 | 4" conduit, type E (611E00400) | FT | 140 | $5.00 | $6.00 | $15.00 | $12.00 |
| 58 | Connection, fused pull apart, as per plan (625E00451) | EACH | 30 | $10.00 | $125.00 | $147.00 | $150.00 |
| 59 | Connection, unfused pull apart (625E00460) | EACH | 10 | $8.00 | $125.00 | $158.00 | $150.00 |
| 60 | Connection, unfused permanent (625E00480) | EACH | 6 | $80.00 | $120.00 | $147.00 | $170.00 |
| 61 | Light pole, decorative, as per plan (625E10481) | EACH | 8 | $8,000.00 | $5,700.00 | $6,105.00 | $5,500.00 |
| 62 | Light pole foundation, 24" X 6' deep (625E14000) | EACH | 8 | $3,000.00 | $2,600.00 | $2,525.00 | $7,500.00 |
| 63 | No. 6 AWG 600 volt distribution cable (625E22990) | FT | 2,646 | $2.00 | $4.00 | $3.50 | $3.00 |
| 64 | No. 8 AWG 600 volt distribution cable (625E23304) | FT | 3,204 | $3.00 | $3.50 | $3.00 | $2.50 |
| 65 | No. 12 AWG pole and bracket cable (625E23410) | FT | 1,308 | $2.00 | $2.50 | $1.00 | $2.50 |
| 66 | Conduit, 2", 725.051 (625E25408) | FT | 452 | $10.00 | $14.00 | $4.00 | $6.00 |
| 67 | Conduit, 3", 725.051 (625E25504) | FT | 150 | $12.00 | $17.00 | $6.00 | $8.00 |
| 68 | Conduit, 4", 725.051 (625E25604) | FT | 85 | $14.00 | $19.00 | $10.50 | $9.00 |
| 69 | Conduit, jacked or drilled, 725.052, as per plan (625E25909) | FT | 69 | $15.00 | $48.00 | $25.00 | $45.00 |
| 70 | Conduit, jacked or drilled, 725.052, as per plan (625E25909) | FT | 171 | $17.00 | $55.50 | $27.00 | $65.00 |
| 71 | Conduit, jacked or drilled, 725.052, as per plan (625E25909) | FT | 81 | $20.00 | $60.00 | $32.00 | $50.00 |
| 72 | Luminaire, decorative, as per plan ies-III-M, LED, (625E27551) | EACH | 10 | $5,000.00 | $3,300.00 | $3,580.00 | $3,300.00 |
| 73 | Trench (625E29000) | FT | 687 | $10.00 | $15.00 | $17.00 | $11.00 |
| 74 | Pull box, 725.06, size 7 (625E30520) | EACH | 7 | $1,000.00 | $1,750.00 | $2,750.00 | $900.00 |
| 75 | Ground rod (625E32000) | EACH | 10 | $100.00 | $300.00 | $210.00 | $300.00 |
| 76 | Power service, as per plan (625E34001) | EACH | 2 | $3,000.00 | $11,500 | $6,500.00 | $13,500 |
| 77 | Underground warning marking tape (625E36010) | FT | 687 | $1.00 | $3.50 | $0.50 | $2.00 |
| 78 | Power cable, 3 conductor, no. 2 AWG (632E69320) | FT | 133 | $12.00 | $16.00 | $17.00 | $4.00 |
| 79 | Ground mounted support, no. 3 post (630E03100) | FT | 181 | $15.00 | $18.00 | $10.00 | $12.00 |
| 80 | Sign, flat sheet (630E80100) | SF | 106 | $25.00 | $19.00 | $28.00 | $25.00 |
| 81 | Removal of ground mounted sign and disposal (630E84900) | EACH | 3 | $50.00 | $24.00 | $21.00 | $20.00 |
| 82 | Removal of ground mounted sign and reerection (630E85100) | EACH | 32 | $100.00 | $50.00 | $47.00 | $60.00 |
| 83 | Removal of ground mounted post support and disposal (630E86002) | EACH | 1 | $50.00 | $30.00 | $26.00 | $40.00 |
| 84 | Removal of ground mounted post support and reerection (630E86010) | EACH | 20 | $100.00 | $72.00 | $68.00 | $115.00 |
| 85 | Edge line, 4" (644E00100) | MI | 0.03 | $11,204 | $11,500 | $11,800 | $12,000 |
| 86 | Channelizing line, 8" (644E00400) | FT | 78 | $3.00 | $3.50 | $3.00 | $3.00 |
| 87 | Stop line (644E00500) | FT | 70 | $12.75 | $13.50 | $13.00 | $13.00 |
| 88 | Crosswalk line, 12" (644E00620) | FT | 409 | $6.35 | $7.00 | $7.00 | $7.00 |
| 89 | Crosswalk line, 24" (644E00630) | FT | 380 | $11.45 | $12.00 | $12.00 | $12.00 |
| 90 | Lane arrow (644E01300) | EACH | 2 | $200.00 | $215.00 | $210.00 | $225.00 |
| 91 | Yield line (644E20800) | FT | 38 | $25.00 | $27.00 | $26.00 | $30.00 |
| 92 | Removal of pavement marking (644E30000) | FT | 142 | $20.62 | $25.00 | $21.00 | $21.00 |
| 93 | Light pole, decorative, as per plan (625E10481) | EACH | 2 | $7,000.00 | $5,700.00 | $6,100.00 | $5,500.00 |
| 94 | Light pole foundation, 24" X 6' deep (625E14000) | EACH | 2 | $3,000.00 | $2,500.00 | $2,500.00 | $7,400.00 |
| 95 | Ground rod (625E32000) | EACH | 2 | $100.00 | $300.00 | $210.00 | $270.00 |
| 96 | Signing, misc.:rectangular rapid flashing beacon ( (630E97700) | EACH | 2 | $7,500.00 | $6,250.00 | $7,900.00 | $6,500.00 |
| 97 | Accessible pedestrian pushbutton (632E20750) | EACH | 2 | $750.00 | $858.00 | $750.00 | $900.00 |
| 98 | Signal cable, 3 conductor, no. 14 AWG (632E40300) | FT | 490 | $3.00 | $3.00 | $3.00 | $3.00 |
| 99 | Signal cable, 5 conductor, no. 14 AWG (632E40500) | FT | 498 | $3.00 | $3.50 | $4.00 | $3.25 |
| 100 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $27,000 | $15,000 | $8,000.00 | $12,500 |
| 101 | Maintaining traffic (614E11000) | LS | 1 | $23,500 | $11,000 | $50,000 | $65,000 |
| 102 | Construction layout stakes and surveying (623E10000) | LS | 1 | $34,000 | $7,800.00 | $11,500 | $25,000 |
| 103 | Mobilization (624E10000) | LS | 1 | $28,000 | $15,000 | $45,029 | $58,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of January 29, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.