ODOT contract 260061 bid tabulation
MOT-IR 75-10.44 & 10.78 (BRIDGE REPAIR). Let by Ohio DOT on January 29, 2026, MOT. 4 bids received; low bid $817,615 by Ram Construction Services of Michigan, Inc, -32% against the engineer's estimate of $1,200,000.
- Owner
- Ohio DOT
- Letting
- 29 JAN 2026
- Pay items
- 16
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Ram Construction Services of Michigan, Inc | $817,615 | Low | -32% |
| 2 | Truesdell Corporation of Wisconsin Inc | $1,044,044 | +28% | -13% |
| 3 | Enneking Pressure Cleaning Inc | $1,183,256 | +45% | -1.0% |
| 4 | Perk Company Inc | $1,771,737 | +117% | +48% |
Engineer's estimate: $1,200,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Ram Construction Services of Michigan, Inc | 2. Truesdell Corporation of Wisconsin Inc | 3. Enneking Pressure Cleaning Inc | 4. Perk Company Inc |
|---|---|---|---|---|---|---|---|
| 1 | Erosion control (832E30000) | EACH | 2,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 2 | Edge line, 6" (646E10010) | MI | 0.88 | $14,590 | $15,500 | $15,000 | $14,590 |
| 3 | Lane line, 6" (646E10110) | MI | 0.88 | $5,990.00 | $6,500.00 | $6,000.00 | $5,990.00 |
| 4 | Channelizing line, 12" (646E10310) | FT | 247 | $300.00 | $3.25 | $5.00 | $3.00 |
| 5 | Dotted line, 6" (646E20504) | FT | 1,076 | $2.80 | $3.05 | $3.50 | $2.80 |
| 6 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 300 | $75.00 | $100.00 | $60.00 | $100.00 |
| 7 | Portable changeable message sign, as per plan (614E18601) | SNMT | 4 | $1,025.94 | $1,250.00 | $1,050.00 | $1,025.94 |
| 8 | Work zone lane line, class I, 6", 740.06, type I (614E20210) | MI | 0.88 | $4,310.05 | $4,585.00 | $4,500.00 | $4,310.05 |
| 9 | Work zone edge line, class I, 6", 740.06, type I (614E22210) | MI | 0.88 | $13,907 | $14,680 | $14,000 | $13,807 |
| 10 | Work zone channelizing line, class I, 12", 740.06, type I (614E23410) | FT | 247 | $4.97 | $5.50 | $5.00 | $4.97 |
| 11 | Work zone dotted line, class I, 6", 740.06, type I (614E24402) | FT | 1,076 | $0.84 | $0.95 | $1.00 | $0.84 |
| 12 | Thin polymer epoxy overlay, as per plan (858E10001) | SY | 12,474 | $34.17 | $45.50 | $54.47 | $79.84 |
| 13 | Thin polymer epoxy overlay, as per plan (858E10001) | SY | 2,510 | $34.17 | $45.50 | $62.56 | $79.84 |
| 14 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $8,200.00 | $1,000.00 | $15,500 | $20,000 |
| 15 | Maintaining traffic (614E11000) | LS | 1 | $121,122 | $185,000 | $110,000 | $257,000 |
| 16 | Mobilization (624E10000) | LS | 1 | $34,300 | $96,494 | $155,000 | $222,371 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of January 29, 2026. Compiled by Mirage Metrics.