ODOT contract 260058 bid tabulation
LAW-SR 775-08.77 (SLIDE REPAIR). Let by Ohio DOT on January 29, 2026, LAW. 2 bids received; low bid $1,185,492 by Axis Civil Construction LLC, +25% against the engineer's estimate of $950,000.
- Owner
- Ohio DOT
- Letting
- 29 JAN 2026
- Pay items
- 41
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Axis Civil Construction LLC | $1,185,492 | Low | +25% |
| 2 | Allard Excavation LLC | $1,353,953 | +14% | +43% |
Engineer's estimate: $950,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Axis Civil Construction LLC | 2. Allard Excavation LLC |
|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $35,000 | $13,293 |
| 2 | Pavement removed (202E23000) | SY | 17 | $20.00 | $7.00 |
| 3 | Excavation, as per plan (203E10001) | CY | 25,588 | $33.90 | $35.00 |
| 4 | Embankment (203E20000) | CY | 66 | $38.00 | $21.00 |
| 5 | Subgrade compaction (204E10000) | SY | 19 | $15.00 | $14.00 |
| 6 | Scaling (862E00500) | HR | 60 | $990.00 | $1,200.00 |
| 7 | Seeding and mulching (659E10000) | SY | 1,118 | $2.70 | $2.70 |
| 8 | Commercial fertilizer (659E20000) | TON | 0.10 | $1,250.00 | $1,250.00 |
| 9 | Lime (659E31000) | ACRE | 0.23 | $150.00 | $150.00 |
| 10 | Water (659E35000) | MGAL | 4 | $1.00 | $1.00 |
| 11 | Erosion control (832E30000) | EACH | 5,000 | $1.00 | $1.00 |
| 12 | Curb and gutter removed (202E32500) | FT | 505 | $18.00 | $12.00 |
| 13 | Pipe removed, 24" and under (202E35100) | FT | 77 | $20.00 | $6.00 |
| 14 | Catch basin removed (202E58100) | EACH | 1 | $1,200.00 | $123.00 |
| 15 | Special - fill and plug existing conduit (202E70000) | FT | 40 | $120.00 | $170.00 |
| 16 | Removal misc.:catch basin clean out (202E98100) | EACH | 2 | $1,000.00 | $365.00 |
| 17 | Ditch cleanout, as per plan (209E10001) | FT | 250 | $5.00 | $10.00 |
| 18 | Paved gutter, type 5 (601E39500) | FT | 10 | $150.00 | $236.00 |
| 19 | 15" conduit, type B (611E05900) | FT | 77 | $120.00 | $183.00 |
| 20 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 2 | $750.00 | $300.00 |
| 21 | Aggregate base (304E20000) | CY | 3 | $450.00 | $194.00 |
| 22 | Tack coat (407E10000) | GAL | 2 | $7.00 | $6.00 |
| 23 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 2 | $850.00 | $400.00 |
| 24 | Special - work zone traffic signal (614E11300) | EACH | 3 | $4,800.00 | $10,462 |
| 25 | Work zone impact attenuator, 24" wide hazards, (bidirectional) (614E12384) | EACH | 4 | $2,800.00 | $2,400.00 |
| 26 | Barrier reflector, type 1, BI-directional (614E13310) | EACH | 42 | $15.00 | $25.00 |
| 27 | Barrier reflector, type 3 (for guardrail) (614E13314) | EACH | 23 | $15.00 | $32.00 |
| 28 | Object marker, two way (614E13360) | EACH | 36 | $20.00 | $25.00 |
| 29 | Work zone center line, class I (614E21000) | MI | 0.10 | $6,250.00 | $6,250.00 |
| 30 | Work zone edge line, class I, 4" (614E22000) | MI | 0.03 | $18,000 | $18,000 |
| 31 | Work zone stop line, class I (614E26000) | FT | 25 | $14.00 | $14.00 |
| 32 | Water (616E10000) | MGAL | 70 | $1.00 | $1.00 |
| 33 | Portable barrier, 50", as per plan (622E41011) | FT | 732 | $40.00 | $66.00 |
| 34 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $10,000 | $9,960.00 |
| 35 | Maintaining traffic (614E11000) | LS | 1 | $35,000 | $105,399 |
| 36 | Field office, type A (619E16000) | MNTH | 6 | $2,500.00 | $1,800.00 |
| 37 | Construction layout stakes and surveying, as per plan (623E10001) | LS | 1 | $12,000 | $15,479 |
| 38 | Preconstruction survey monument verification and report (623E50000) | LS | 1 | $1,600.00 | $3,000.00 |
| 39 | Post construction survey monument verification and report (623E51000) | LS | 1 | $1,600.00 | $3,000.00 |
| 40 | Mobilization (624E10000) | LS | 1 | $40,000 | $83,000 |
| 100 | Detour signing (614E12420) | LS | 1 | $3,800.00 | $3,800.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of January 29, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.