ODOT contract 260070 bid tabulation
D03-PM FY2026 (PAVEMENT MARKING). Let by Ohio DOT on January 29, 2026, District 3. 3 bids received; low bid $3,885,838 by Alpha Space Control LLC, -21% against the engineer's estimate of $4,939,000.
- Owner
- Ohio DOT
- Letting
- 29 JAN 2026
- Pay items
- 39
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Alpha Space Control LLC | $3,885,838 | Low | -21% |
| 2 | The Aero-Mark Company LLC | $4,200,000 | +8.0% | -15% |
| 3 | Oglesby Construction Inc | $4,494,422 | +16% | -9.0% |
Engineer's estimate: $4,939,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Alpha Space Control LLC | 2. The Aero-Mark Company LLC | 3. Oglesby Construction Inc |
|---|---|---|---|---|---|---|
| 1 | Erosion control (832E30000) | EACH | 1,500 | $1.00 | $1.00 | $1.00 |
| 2 | Rumble stripes, center line (asphalt concrete) (618E43000) | MI | 6.97 | $2,115.50 | $1,015.00 | $1,000.00 |
| 3 | Edge line, 6", type 1 (642E00104) | MI | 2,662.08 | $587.25 | $607.00 | $630.00 |
| 4 | Lane line, 6", type 1 (642E00204) | MI | 459.40 | $327.65 | $300.00 | $280.00 |
| 5 | Center line, type 1 (642E00300) | MI | 1,119.13 | $428.15 | $518.00 | $635.00 |
| 6 | Edge line, 6" (643E00104) | MI | 298.88 | $589.35 | $1,349.00 | $1,245.00 |
| 7 | Lane line, 6" (643E00204) | MI | 11.50 | $313.65 | $527.00 | $470.00 |
| 8 | Center line (643E00300) | MI | 140.96 | $426.45 | $1,150.00 | $1,250.00 |
| 9 | Channelizing line, 12" (643E00404) | FT | 149,751 | $0.50 | $0.53 | $0.60 |
| 10 | Stop line (643E00500) | FT | 68,457 | $2.65 | $4.00 | $4.00 |
| 11 | Crosswalk line, 12" (643E00620) | FT | 8,163 | $1.96 | $2.50 | $2.50 |
| 12 | Transverse/diagonal line (643E00700) | FT | 42,123 | $2.20 | $2.75 | $2.50 |
| 13 | Chevron marking (643E00720) | FT | 12,701 | $2.76 | $2.75 | $2.50 |
| 14 | Island marking (643E00900) | SF | 702 | $2.45 | $3.00 | $2.50 |
| 15 | Railroad symbol marking (643E01000) | EACH | 145 | $315.00 | $365.00 | $355.00 |
| 16 | School symbol marking, 96" (643E01110) | EACH | 81 | $225.00 | $365.00 | $355.00 |
| 17 | Lane arrow (643E01300) | EACH | 2,194 | $52.50 | $50.00 | $55.00 |
| 18 | Wrong way arrow (643E01310) | EACH | 171 | $195.00 | $225.00 | $180.00 |
| 19 | Two way left turn arrow (643E01350) | EACH | 588 | $95.00 | $75.00 | $100.00 |
| 20 | Word on pavement, 96" (643E01410) | EACH | 51 | $75.00 | $65.00 | $80.00 |
| 21 | Dotted line, 6" (643E01510) | FT | 45,960 | $0.47 | $0.53 | $0.85 |
| 22 | Bike lane symbol marking (643E01602) | EACH | 21 | $65.00 | $400.00 | $55.00 |
| 23 | Yield line (643E20802) | FT | 838 | $8.50 | $6.00 | $5.00 |
| 24 | Removal of pavement marking (643E30000) | FT | 200 | $2.35 | $5.00 | $2.00 |
| 25 | Removal of pavement marking (643E30010) | SF | 100 | $2.50 | $5.00 | $2.00 |
| 26 | Removal of pavement marking (643E30020) | EACH | 50 | $125.00 | $175.00 | $50.00 |
| 27 | Speed measurement marking (643E40000) | EACH | 15 | $335.00 | $900.00 | $900.00 |
| 28 | Pavement marking, misc.: bike crossing (643E50100) | EACH | 15 | $285.00 | $400.00 | $600.00 |
| 29 | Pavement marking, misc.: lane reduction arrow (643E50100) | EACH | 40 | $285.00 | $300.00 | $285.00 |
| 30 | Wet reflective traffic paint, edge line, 6" (807E10010) | MI | 136.76 | $2,615.00 | $1,685.00 | $2,550.00 |
| 31 | Wet reflective traffic paint, lane line, 6" (807E10110) | MI | 81.11 | $1,485.00 | $679.00 | $800.00 |
| 32 | Wet reflective traffic paint, channelizing line, 1 (807E10310) | FT | 21,420 | $1.47 | $1.43 | $1.25 |
| 33 | Wet reflective traffic paint, dotted line, 6" (807E10410) | FT | 825 | $1.00 | $1.00 | $0.70 |
| 34 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $58,500 | $17,697 | $23,000 |
| 35 | Maintaining traffic (614E11000) | LS | 1 | $2,500.00 | $29,000 | $25,000 |
| 36 | Field office, type B (619E16010) | MNTH | 6 | $750.00 | $650.00 | $500.00 |
| 37 | Construction layout stakes and surveying (623E10000) | LS | 1 | $1.00 | $1.00 | $1.00 |
| 38 | Mobilization (624E10000) | LS | 1 | $29,250 | $15,000 | $15,000 |
| 39 | Mobilization, as per plan (624E15001) | EACH | 20 | $5,000.00 | $1,000.00 | $500.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of January 29, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.