ODOT contract 260055 bid tabulation
LAK-IR 90-08.77 VSL Signs (SIGNALIZATION). Let by Ohio DOT on January 29, 2026, LAK. 2 bids received; low bid $4,123,000 by Perram Electric Inc, +26% against the engineer's estimate of $3,272,000.
- Owner
- Ohio DOT
- Letting
- 29 JAN 2026
- Pay items
- 76
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Perram Electric Inc | $4,123,000 | Low | +26% |
| 2 | Miller Cable Company | $4,799,760 | +16% | +47% |
Engineer's estimate: $3,272,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Perram Electric Inc | 2. Miller Cable Company |
|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $6,400.00 | $85,000 |
| 2 | Guardrail removed (202E38000) | FT | 655 | $3.00 | $3.00 |
| 3 | Anchor assembly removed (202E42206) | EACH | 23 | $195.00 | $165.00 |
| 4 | Excavation (203E10000) | CY | 170 | $118.00 | $160.00 |
| 5 | Subgrade compaction (204E10000) | SY | 748 | $3.00 | $7.50 |
| 6 | Geogrid (204E51000) | SY | 748 | $2.00 | $5.25 |
| 7 | Linear grading, as per plan (209E60201) | STA | 49 | $514.00 | $800.00 |
| 8 | Guardrail, type MGS (606E15050) | FT | 1,887.50 | $23.20 | $25.00 |
| 9 | Guardrail, barrier design, type MGS (606E15550) | FT | 1,587.50 | $37.60 | $39.00 |
| 10 | Anchor assembly, type B (606E26000) | EACH | 9 | $2,880.00 | $3,100.00 |
| 11 | Anchor assembly, MGS type E (606E26150) | EACH | 18 | $2,940.00 | $3,000.00 |
| 12 | Anchor assembly, MGS type T (606E26550) | EACH | 19 | $1,440.00 | $1,500.00 |
| 13 | MGS bridge terminal assembly, type 1 (606E35002) | EACH | 3 | $2,950.00 | $3,200.00 |
| 14 | Soil analysis test (659E00100) | EACH | 2 | $250.00 | $75.00 |
| 15 | Topsoil (659E00300) | CY | 477 | $60.00 | $100.00 |
| 16 | Seeding and mulching (659E10000) | SY | 4,500 | $4.00 | $3.45 |
| 17 | Repair seeding and mulching (659E14000) | SY | 230 | $2.00 | $1.40 |
| 18 | Inter-seeding (659E15000) | SY | 230 | $2.00 | $0.10 |
| 19 | Commercial fertilizer (659E20000) | TON | 0.63 | $1,500.00 | $450.00 |
| 20 | Lime (659E31000) | ACRE | 0.93 | $2,000.00 | $50.00 |
| 21 | Water (659E35000) | MGAL | 25 | $10.00 | $1.00 |
| 22 | Mowing (659E40000) | MSF | 10 | $420.00 | $550.00 |
| 23 | Erosion control (832E30000) | EACH | 35,000 | $1.00 | $1.00 |
| 24 | Aggregate base (304E20000) | CY | 170 | $165.00 | $190.00 |
| 25 | Asphalt concrete intermediate course, type 1, (448), as per plan (441E50201) | CY | 109 | $1,985.50 | $775.00 |
| 26 | Barrier reflector, type 2, bidirectional (626E00110) | EACH | 55 | $14.00 | $25.00 |
| 27 | Barrier reflector, type 2, one way (626E00110) | EACH | 11 | $15.00 | $25.00 |
| 28 | Ground mounted structural beam support, S4X7.7 (630E06400) | FT | 990 | $111.05 | $40.00 |
| 29 | Ground mounted structural beam support, W8X18 (630E07000) | FT | 135 | $139.15 | $65.00 |
| 30 | Breakaway structural beam connection (630E09000) | EACH | 79 | $519.50 | $475.00 |
| 31 | Ground mounted structural beam support foundation (630E84500) | EACH | 79 | $706.50 | $1,220.00 |
| 32 | Removal of ground mounted sign and disposal (630E84900) | EACH | 1 | $200.00 | $20.00 |
| 33 | Removal of ground mounted sign and reerection (630E85100) | EACH | 2 | $1,650.00 | $75.00 |
| 34 | Removal of ground mounted structural beam support (630E86102) | EACH | 2 | $600.00 | $385.00 |
| 35 | Removal of ground mounted structural beam support and reerection (630E86250) | EACH | 4 | $3,420.00 | $725.00 |
| 36 | No. 6 AWG 600 volt distribution cable (625E22990) | FT | 34,274 | $2.55 | $3.20 |
| 37 | Conduit, 2", 725.04 (625E25400) | FT | 2,104 | $20.10 | $20.00 |
| 38 | Conduit, 2", 725.051 (625E25408) | FT | 3,112 | $5.86 | $12.00 |
| 39 | Conduit, 3", 725.04 (625E25500) | FT | 210 | $40.35 | $31.00 |
| 40 | Conduit, 3", 725.051 (625E25504) | FT | 106 | $9.80 | $15.00 |
| 41 | Conduit, jacked or drilled, 725.051, 2" (625E25906) | FT | 3,360 | $34.46 | $60.00 |
| 42 | Trench, 30" deep (625E29010) | FT | 26,366 | $7.35 | $15.00 |
| 43 | Pull box, 725.08, 24" (625E30706) | EACH | 53 | $2,020.00 | $1,300.00 |
| 44 | Ground rod (625E32000) | EACH | 180 | $325.00 | $275.00 |
| 45 | Underground warning marking tape (625E36010) | FT | 26,366 | $1.45 | $2.00 |
| 46 | Controller work pad, as per plan (633E67201) | EACH | 33 | $550.00 | $1,500.00 |
| 47 | Fiber optic cable, 48 fiber (804E15020) | FT | 35,773 | $3.57 | $5.00 |
| 48 | Drop cable, 48 fiber (804E32070) | FT | 1,806 | $3.77 | $5.00 |
| 49 | Fiber termination panel, 48 fiber (804E34030) | EACH | 2 | $5,110.00 | $1,600.00 |
| 50 | Fusion splice (804E35000) | EACH | 96 | $51.00 | $40.00 |
| 51 | Splice enclosure, butt style (804E37000) | EACH | 8 | $900.00 | $1,500.00 |
| 52 | ITS pull box with pad and standard lid assembly, 3 (809E01900) | EACH | 63 | $4,476.00 | $5,500.00 |
| 53 | ITS pull box with pad and hinged lid assembly, 32" wide, type 1 (809E01920) | EACH | 3 | $5,750.00 | $5,800.00 |
| 54 | Micro-duct pathway, 4 cell 14/10 (809E20020) | FT | 20,810 | $6.48 | $4.50 |
| 55 | Micro-duct pathway, jacked or drilled, 4 cell 14/1 (809E22000) | FT | 5,830 | $42.30 | $65.00 |
| 56 | Conduit, multicell, jacked or drilled, 4" (809E24000) | FT | 2,426 | $69.75 | $64.00 |
| 57 | Conduit, 4", multicell, HDPE with 4 - 1" innerducts (809E24500) | FT | 1,999 | $54.75 | $52.00 |
| 58 | ITS power service, pole mounted, 120/240V, 100 amp (809E55100) | EACH | 7 | $7,775.00 | $10,500 |
| 59 | CCTV IP-camera system, dome-type (809E60000) | EACH | 3 | $6,920.00 | $13,000 |
| 60 | CCTV pole, 70' tall (809E61040) | EACH | 3 | $35,130 | $47,500 |
| 61 | CCTV lowering unit (809E61090) | EACH | 3 | $13,045 | $12,300 |
| 62 | Dynamic message sign (DMS), front-access (809E63010) | EACH | 3 | $61,835 | $74,850 |
| 63 | Variable speed limit sign with beacons, as per pla (809E64000) | EACH | 33 | $12,735 | $17,250 |
| 64 | Ethernet cable, outdoor-rated (809E64550) | FT | 7,751 | $2.62 | $3.50 |
| 65 | ITS cabinet - ground mounted (809E65000) | EACH | 8 | $7,275.00 | $14,000 |
| 66 | ITS cabinet - power distribution cabinet (PDC) (809E65020) | EACH | 3 | $6,878.00 | $8,500.00 |
| 67 | ITS device, misc.: beacons, as per plan (809E65990) | EACH | 19 | $3,730.00 | $4,300.00 |
| 68 | ITS device, misc.: road weather information system (809E65990) | EACH | 2 | $8,700.00 | $7,250.00 |
| 69 | As-built construction plans (809E70050) | LS | 1 | $14,480 | $4,000.00 |
| 70 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $69,161 | $16,000 |
| 71 | Maintaining traffic (614E11000) | LS | 1 | $111,600 | $85,000 |
| 72 | Field office, type B, as per plan (619E16011) | MNTH | 9 | $2,590.00 | $850.00 |
| 73 | Construction layout stakes and surveying (623E10000) | LS | 1 | $19,200 | $85,000 |
| 74 | Mobilization (624E10000) | LS | 1 | $100,000 | $100,000 |
| 100 | Cabinet foundation (633E67100) | EACH | 11 | $9,200.00 | $2,600.00 |
| 101 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 60 | $100.00 | $75.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of January 29, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.