ODOT contract 260057 bid tabulation
LAK-SR 84/VAR-18.21/VAR (TWO LANE RESURFACING). Let by Ohio DOT on January 29, 2026, LAK. 7 bids received; low bid $1,126,236 by Geauga Highway Co, -32% against the engineer's estimate of $1,665,000.
- Owner
- Ohio DOT
- Letting
- 29 JAN 2026
- Pay items
- 48
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Geauga Highway Co | $1,126,236 | Low | -32% |
| 2 | Kokosing Construction Company Inc | $1,269,234 | +13% | -24% |
| 3 | Karvo Companies Inc | $1,525,181 | +35% | -8.0% |
| 4 | Ronyak Paving Inc | $1,571,832 | +40% | -6.0% |
| 5 | Phillips Paving LLC | $1,736,660 | +54% | +4.0% |
| 6 | Shelly Company | $1,765,563 | +57% | +6.0% |
| 7 | Barbicas Construction Company Inc | $1,771,547 | +57% | +6.0% |
Engineer's estimate: $1,665,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Geauga Highway Co | 2. Kokosing Construction Company Inc | 3. Karvo Companies Inc | 4. Ronyak Paving Inc | 5. Phillips Paving LLC | 6. Shelly Company |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Walk removed (202E30000) | SF | 4,125 | $3.00 | $1.65 | $6.00 | $2.00 | $7.00 | $10.00 |
| 2 | Curb removed (202E32000) | FT | 702 | $10.00 | $13.75 | $25.00 | $14.00 | $12.00 | $12.00 |
| 3 | Guardrail removed (202E38000) | FT | 1,530 | $2.30 | $3.00 | $3.00 | $2.30 | $2.30 | $3.00 |
| 4 | Anchor assembly removed (202E42206) | EACH | 2 | $125.00 | $250.00 | $250.00 | $125.00 | $125.00 | $250.00 |
| 5 | Anchor assembly removed, as per plan (202E42207) | EACH | 4 | $325.00 | $450.00 | $450.00 | $325.00 | $325.00 | $450.00 |
| 6 | Guardrail, type MGS (606E15050) | FT | 1,318 | $22.00 | $21.00 | $21.00 | $22.00 | $22.00 | $21.00 |
| 7 | Anchor assembly, type E (606E26100) | EACH | 3 | $2,120.00 | $2,550.00 | $2,550.00 | $2,120.00 | $2,120.00 | $2,550.00 |
| 8 | Anchor assembly, type T (606E26500) | EACH | 3 | $950.00 | $1,450.00 | $1,450.00 | $950.00 | $950.00 | $1,450.00 |
| 9 | Curb ramp (608E52000) | SF | 4,064 | $17.00 | $11.35 | $14.00 | $12.00 | $20.00 | $28.00 |
| 10 | Monument assembly adjusted to grade, as per plan (623E39501) | EACH | 21 | $750.00 | $499.95 | $1,300.00 | $925.00 | $950.00 | $1,100.00 |
| 11 | Monument assembly reconstructed to grade, as per plan (623E39601) | EACH | 1 | $1,000.00 | $1,464.95 | $2,000.00 | $2,100.00 | $2,000.00 | $1,200.00 |
| 12 | Topsoil (659E00300) | CY | 60 | $80.00 | $145.00 | $25.00 | $85.00 | $125.00 | $75.00 |
| 13 | Seeding and mulching, class 1 (659E00500) | SY | 1,050 | $4.00 | $1.75 | $1.00 | $2.00 | $4.00 | $4.00 |
| 14 | Erosion control (832E30000) | EACH | 14,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 15 | Catch basin adjusted to grade, as per plan (611E98631) | EACH | 40 | $1,150.00 | $900.00 | $1,400.00 | $1,000.00 | $1,450.00 | $1,200.00 |
| 16 | Catch basin reconstructed to grade, as per plan (611E98635) | EACH | 4 | $1,800.00 | $2,624.95 | $2,500.00 | $2,625.00 | $2,600.00 | $1,500.00 |
| 17 | Manhole adjusted to grade, as per plan (611E99655) | EACH | 49 | $1,150.00 | $690.00 | $1,200.00 | $825.00 | $1,100.00 | $1,200.00 |
| 18 | Manhole reconstructed to grade, as per plan (611E99661) | EACH | 5 | $1,800.00 | $1,394.95 | $2,500.00 | $1,400.00 | $2,600.00 | $1,500.00 |
| 19 | Special - miscellaneous metal (611E99820) | LB | 9,500 | $2.25 | $2.25 | $3.00 | $5.00 | $3.00 | $4.00 |
| 20 | Pavement planing, asphalt concrete, 3" (254E01000) | SY | 26,213 | $5.00 | $3.25 | $5.00 | $5.00 | $5.00 | $4.25 |
| 21 | Patching planed surface (254E01600) | SY | 500 | $0.25 | $3.00 | $0.50 | $15.00 | $10.00 | $1.00 |
| 22 | Full depth pavement removal and rigid replacement, type 1, class QC RS, as per plan (255E19001) | SY | 900 | $120.00 | $190.75 | $185.00 | $350.00 | $330.00 | $400.00 |
| 23 | Non-tracking tack coat (407E20000) | GAL | 4,202 | $3.50 | $2.25 | $2.53 | $2.00 | $2.00 | $3.00 |
| 24 | Asphalt concrete surface course, type 1, (449), as per plan (441E70101) | CY | 1,058 | $222.00 | $241.00 | $230.00 | $225.00 | $240.00 | $240.00 |
| 25 | Asphalt concrete intermediate course, type 2, (449) (441E70300) | CY | 1,058 | $175.00 | $203.00 | $220.00 | $195.00 | $200.00 | $205.00 |
| 26 | Curb, type 6 (609E26000) | FT | 702 | $26.00 | $27.45 | $45.00 | $30.00 | $50.00 | $60.00 |
| 27 | Longitudinal joint adhesive (875E10000) | LB | 1,260 | $2.27 | $0.85 | $1.00 | $4.00 | $3.00 | $5.50 |
| 28 | Valve box adjusted to grade, as per plan (638E10801) | EACH | 24 | $650.00 | $499.95 | $1,000.00 | $550.00 | $950.00 | $645.00 |
| 29 | Edge line, 4" (646E10000) | MI | 0.86 | $1,860.00 | $1,860.00 | $1,860.00 | $1,860.00 | $1,860.00 | $4,250.00 |
| 30 | Center line (646E10200) | MI | 1.48 | $4,245.00 | $4,245.00 | $4,245.00 | $4,245.00 | $4,245.00 | $5,000.00 |
| 31 | Stop line (646E10400) | FT | 241 | $11.40 | $11.40 | $12.00 | $11.40 | $11.40 | $12.50 |
| 32 | Crosswalk line, 12" (646E10510) | FT | 1,394 | $6.20 | $6.40 | $6.50 | $6.40 | $6.40 | $9.50 |
| 33 | Railroad symbol marking (646E20000) | EACH | 1 | $500.00 | $500.00 | $500.00 | $500.00 | $500.00 | $650.00 |
| 34 | Detector loop, as per plan (632E26501) | EACH | 10 | $1,600.00 | $1,450.00 | $1,450.00 | $1,450.00 | $1,450.00 | $1,450.00 |
| 35 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 40 | $100.00 | $130.00 | $125.00 | $125.00 | $125.00 | $120.00 |
| 36 | Work zone center line, class I, 642 paint (614E21100) | MI | 4.44 | $1,180.00 | $1,180.00 | $1,180.00 | $1,180.00 | $1,180.00 | $1,450.00 |
| 37 | Work zone edge line, class I, 4", 642 paint (614E22100) | MI | 2.58 | $725.00 | $725.00 | $725.00 | $725.00 | $725.00 | $675.00 |
| 38 | Work zone stop line, class I, 642 paint (614E26200) | FT | 723 | $2.50 | $2.50 | $2.50 | $2.50 | $2.50 | $4.00 |
| 39 | Work zone crosswalk line, class I, 12", 642 paint (614E27050) | FT | 4,182 | $1.75 | $1.75 | $1.75 | $1.75 | $1.75 | $3.00 |
| 40 | Work zone railroad symbol marking, class I, 642 paint (614E32200) | EACH | 3 | $350.00 | $350.00 | $350.00 | $350.00 | $350.00 | $250.00 |
| 41 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $8,759.92 | $5,100.00 | $16,000 | $11,925 | $35,000 | $10,000 |
| 42 | CPM progress schedule short duration projects (108E30000) | LS | 1 | $2,500.00 | $1,500.00 | $5,000.00 | $2,500.00 | $5,000.00 | $10,000 |
| 43 | Maintaining traffic (614E11000) | LS | 1 | $20,100 | $106,200 | $110,000 | $170,000 | $175,000 | $182,500 |
| 44 | Construction layout stakes and surveying (623E10000) | LS | 1 | $1,000.00 | $870.00 | $4,000.00 | $2,290.00 | $5,000.00 | $5,000.00 |
| 45 | Preconstruction survey monument verification and report (623E50000) | LS | 1 | $1,500.00 | $3,000.00 | $2,500.00 | $2,790.00 | $2,800.00 | $3,000.00 |
| 46 | Post construction survey monument verification and report (623E51000) | LS | 1 | $1,500.00 | $3,000.00 | $2,500.00 | $2,790.00 | $2,800.00 | $3,000.00 |
| 47 | Mobilization (624E10000) | LS | 1 | $6,500.00 | $63,050 | $124,000 | $71,000 | $104,450 | $40,000 |
| 100 | Portable changeable message sign, as per plan (614E18601) | SNMT | 6 | $875.00 | $875.00 | $875.00 | $1,300.00 | $1,300.00 | $875.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of January 29, 2026. Compiled by Mirage Metrics.