ODOT contract 260049 bid tabulation
CLE-SR 132-12.64 (BRIDGE REPAIR). Let by Ohio DOT on January 29, 2026, CLE. 5 bids received; low bid $568,754 by Complete General Construction Company, -17% against the engineer's estimate of $685,000.
- Owner
- Ohio DOT
- Letting
- 29 JAN 2026
- Pay items
- 42
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Complete General Construction Company | $568,754 | Low | -17% |
| 2 | Eagle Bridge Co | $583,081 | +3.0% | -15% |
| 3 | Prus Construction Company | $608,287 | +7.0% | -11% |
| 4 | BCC Ohio Inc | $614,325 | +8.0% | -10% |
| 5 | KT Holden Construction LLC | $631,523 | +11% | -8.0% |
Engineer's estimate: $685,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Complete General Construction Company | 2. Eagle Bridge Co | 3. Prus Construction Company | 4. BCC Ohio Inc | 5. KT Holden Construction LLC |
|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $3,000.00 | $500.00 | $2,175.00 | $774.00 | $25,000 |
| 2 | Guardrail removed (202E38000) | FT | 200 | $2.40 | $3.00 | $2.65 | $2.52 | $11.50 |
| 3 | Anchor assembly removed, type A, as per plan (202E42001) | EACH | 2 | $500.00 | $650.00 | $357.50 | $341.25 | $1,000.00 |
| 4 | Bridge terminal assembly removed, as per plan (202E47001) | EACH | 4 | $500.00 | $150.00 | $82.50 | $78.75 | $380.00 |
| 5 | Embankment (203E20000) | CY | 15 | $45.00 | $150.00 | $77.25 | $86.70 | $100.00 |
| 6 | Guardrail, type MGS (606E15050) | FT | 187.50 | $22.80 | $26.00 | $25.00 | $23.94 | $26.00 |
| 7 | Anchor assembly, MGS type E (MASH 2016) (606E26150) | EACH | 2 | $2,680.00 | $2,600.00 | $2,948.00 | $2,814.00 | $2,600.00 |
| 8 | Bridge terminal assembly, type 4, as per plan (606E35141) | EACH | 4 | $1,385.00 | $1,500.00 | $1,523.50 | $1,454.25 | $1,500.00 |
| 9 | Seeding and mulching (659E10000) | SY | 315 | $10.00 | $10.00 | $4.65 | $5.00 | $10.00 |
| 10 | Commercial fertilizer (659E20000) | TON | 0.04 | $1,250.00 | $1,250.00 | $1,000.00 | $6,225.00 | $1,500.00 |
| 11 | Lime (659E31000) | ACRE | 0.06 | $150.00 | $1.00 | $2,315.00 | $4,150.00 | $200.00 |
| 12 | Water (659E35000) | MGAL | 1.50 | $1.00 | $20.00 | $95.00 | $8.40 | $1.00 |
| 13 | Erosion control (832E30000) | EACH | 7,200 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 14 | Barrier reflector, type 2 (bidirectional) (626E00110) | EACH | 7 | $15.00 | $12.50 | $16.50 | $15.75 | $12.50 |
| 15 | Edge line, 6" (646E10010) | MI | 0.04 | $60,000 | $60,000 | $74,865 | $63,000 | $60,000 |
| 16 | Center line (646E10200) | MI | 0.02 | $60,000 | $60,000 | $149,735 | $63,000 | $60,000 |
| 17 | Detour signing (614E12420) | LS | 1 | $6,500.00 | $9,000.00 | $7,625.00 | $6,814.74 | $12,000 |
| 18 | Portions of structure removed, over 20 foot span, as per plan (202E11203) | LS | 1 | $78,000 | $77,500 | $44,150 | $33,683 | $82,965 |
| 19 | Epoxy coated reinforcing steel, as per plan (509E10001) | LB | 472 | $6.00 | $3.00 | $5.00 | $3.91 | $15.00 |
| 20 | Concrete reinforcement, replacement of existing concrete reinforcement, as per plan (509E20001) | LB | 100 | $6.00 | $1.50 | $4.00 | $3.91 | $6.00 |
| 21 | Dowel holes with nonshrink, nonmetallic grout (510E10000) | EACH | 10 | $35.00 | $20.00 | $210.00 | $31.88 | $31.00 |
| 22 | Class QC2 concrete with QC/QA, superstructure (511E34412) | CY | 10 | $5,500.00 | $4,600.00 | $4,285.00 | $3,276.60 | $3,800.00 |
| 23 | Surface preparation of existing structural steel (514E00050) | SF | 3,562 | $10.00 | $10.00 | $11.00 | $10.50 | $10.00 |
| 24 | Field painting of existing structural steel, prime coat (514E00056) | SF | 3,562 | $9.00 | $9.00 | $10.00 | $9.45 | $9.00 |
| 25 | Field painting structural steel, intermediate coat (514E00060) | SF | 3,562 | $9.00 | $9.00 | $10.00 | $9.45 | $9.00 |
| 26 | Field painting structural steel, finish coat (514E00066) | SF | 3,562 | $8.00 | $8.00 | $9.00 | $8.40 | $8.00 |
| 27 | Grinding fins, tears, slivers on existing structural steel (514E00504) | MNHR | 6 | $150.00 | $150.00 | $165.00 | $157.50 | $150.00 |
| 28 | Final inspection repair (514E10000) | EACH | 3 | $100.00 | $100.00 | $110.00 | $105.00 | $100.00 |
| 29 | Preformed elastomeric compression joint seal (516E10000) | FT | 80 | $26.00 | $30.00 | $77.50 | $38.05 | $26.00 |
| 30 | Structural expansion joint including elastomeric strip seal, as per plan (516E11211) | FT | 80 | $1,000.00 | $1,125.00 | $1,265.00 | $1,239.45 | $1,055.00 |
| 31 | Deep beam bridge retrofit railing, as per plan (517E75601) | FT | 150 | $152.80 | $130.00 | $168.00 | $160.44 | $130.00 |
| 32 | Special - steel drip strip (518E22300) | FT | 154 | $16.00 | $20.00 | $21.75 | $19.12 | $15.75 |
| 33 | Patching concrete structures with trowelable mortar (843E50000) | SF | 10 | $250.00 | $300.00 | $425.00 | $153.63 | $250.00 |
| 34 | Superplasticized dense concrete overlay using hydrodemolition (848E10200) | SY | 389 | $100.00 | $145.00 | $110.00 | $96.92 | $100.00 |
| 35 | Surface preparation using hydrodemolition, as per plan (848E20001) | SY | 389 | $140.00 | $145.00 | $135.00 | $102.61 | $121.00 |
| 36 | Superplasticized dense concrete overlay (variable thickness), material only (848E30200) | CY | 16 | $370.00 | $300.00 | $420.00 | $517.50 | $325.00 |
| 37 | Hand chipping (848E50000) | SY | 10 | $85.00 | $110.00 | $247.50 | $273.00 | $250.00 |
| 38 | Test slab (848E50100) | LS | 1 | $1,500.00 | $1,250.00 | $1,000.00 | $3,829.05 | $3,000.00 |
| 39 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $5,000.00 | $12,500 | $6,100.00 | $7,584.25 | $11,480 |
| 40 | Maintaining traffic (614E11000) | LS | 1 | $15,000 | $3,500.00 | $52,525 | $29,578 | $38,000 |
| 41 | Construction layout stakes and surveying (623E10000) | LS | 1 | $3,000.00 | $2,500.00 | $4,000.00 | $3,600.00 | $10,000 |
| 42 | Mobilization (624E10000) | LS | 1 | $25,000 | $27,500 | $20,000 | $105,951 | $31,575 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of January 29, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.