ODOT contract 260051 bid tabulation

CUY-Greenhurst Drive Bridge Demo (MISCELLANEOUS). Let by Ohio DOT on January 29, 2026, CUY. 5 bids received; low bid $333,889 by Daniel R Schmoldt Enterprises Inc, -14% against the engineer's estimate of $390,000.

Owner
Ohio DOT
Letting
29 JAN 2026
Pay items
44
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Daniel R Schmoldt Enterprises Inc$333,889Low-14%
2Baumann Enterprises Inc$343,565+3.0%-12%
3Madex Construction Co$451,381+35%+16%
4Matt Winters Excavation LLC$466,187+40%+20%
5Schirmer Construction LLC$486,503+46%+25%
ODOT contract 260051: bids by rank

Engineer's estimate: $390,000.

Bid tabulation

LinePay itemUnitQuantity1. Daniel R Schmoldt Enterprises Inc2. Baumann Enterprises Inc3. Madex Construction Co4. Matt Winters Excavation LLC5. Schirmer Construction LLC
1Clearing and grubbing (201E11000)LS1$8,800.00$8,000.00$15,455$30,000$5,000.00
2Pavement removed (202E23000)SY825$18.00$9.25$20.66$20.00$14.00
3Wearing course removed (202E23500)SY152$20.75$7.50$52.11$50.00$21.00
4Curb removed (202E32000)FT701$5.00$8.00$12.39$15.00$7.00
5Fence removed (202E75000)FT24$10.00$15.00$11.58$20.00$27.00
6Excavation (203E10000)CY32$50.00$35.00$68.34$25.00$90.00
7Embankment (203E20000)CY26$60.00$40.00$82.77$90.00$100.00
8Subgrade compaction (204E10000)SY1,349$3.00$5.00$4.63$8.00$2.00
9Proof rolling (204E45000)HR3$125.00$200.00$173.68$500.00$50.00
10Monument assembly, type C (623E38500)EACH3$1,400.00$2,000.00$2,547.37$2,250.00$500.00
11Right-of-way monument, type B (623E40520)EACH3$1,660.00$500.00$926.32$2,250.00$500.00
12Special - mailbox removed and reset (690E50350)EACH1$150.00$600.00$289.47$450.00$200.00
13Special - bollard, hinged (690E50610)EACH8$1,250.00$1,400.00$1,536.84$1,600.00$1,600.00
14Soil analysis test (659E00100)EACH1$450.00$2,000.00$73.68$200.00$10.00
15Topsoil (659E00300)CY23$52.00$55.00$88.42$100.00$160.00
16Seeding and mulching, class 1 (659E00500)SY207$3.25$1.25$11.58$17.00$10.00
17Repair seeding and mulching (659E14000)SY11$5.00$1.50$11.58$8.00$5.00
18Inter-seeding (659E15000)SY11$10.00$1.50$11.58$0.25$5.00
19Commercial fertilizer (659E20000)TON0.03$1,000.00$3,000.00$2,026.33$860.00$500.00
20Lime (659E31000)ACRE0.04$1,000.00$2,000.00$447.25$100.00$500.00
21Water (659E35000)MGAL2$2.00$38.00$17.37$1.00$10.00
22Erosion control (832E30000)EACH11,500$1.00$1.00$1.00$1.00$1.00
23Tied concrete block mat with type 2 underlayment (601E21060)SY4$200.00$200.00$169.55$1,150.00$150.00
24Catch basin adjusted to grade (611E98630)EACH2$750.00$2,000.00$2,315.79$1,500.00$400.00
25Manhole adjusted to grade (611E99654)EACH2$1,200.00$2,000.00$2,894.74$1,500.00$600.00
26Pavement planing, asphalt concrete , T=3" (254E01000)SY213$3.19$8.50$40.53$22.00$30.00
27Asphalt concrete base, PG64-22, (449) (301E56000)CY235$231.00$190.00$254.74$210.00$215.00
28Aggregate base (304E20000)CY229$98.00$85.00$128.00$130.00$110.00
29Tack coat (407E10000)GAL101$2.20$8.00$2.32$3.25$2.00
30Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000)CY57$374.00$220.00$405.26$520.00$345.00
31Asphalt concrete intermediate course, type 2, (449) (441E70300)CY78$302.50$320.00$330.00$300.00$280.00
326" non-reinforced concrete pavement, class QC 1P (452E10010)SY189$79.00$155.00$103.16$150.00$71.00
33Curb, type 6 (609E26000)FT1,004$24.50$48.00$43.68$75.00$23.00
34Special - valve box adjusted to grade, city of cle (638E20500)EACH1$500.00$4,000.00$1,042.11$1,600.00$150.00
35Object marker, one way (614E13350)EACH8$35.75$50.00$46.32$65.00$35.00
36Removal of ground mounted sign and disposal (630E84900)EACH2$27.50$250.00$173.68$21.00$50.00
37Removal of ground mounted post support and disposal (630E86002)EACH2$27.50$200.00$173.68$26.00$50.00
38Portions of structure removed, over 20 foot span, as per plan (202E11203)LS1$50,000$35,000$52,064$58,980$222,500
39Premium for contract performance bond and for payment bond (103E05000)LS1$6,750.00$11,797$9,957.89$8,800.00$11,000
40CPM progress schedule short duration projects (108E30000)LS1$1,000.00$1,500.00$5,789.47$2,500.00$1,000.00
41Maintaining traffic (614E11000)LS1$2,750.00$2,000.00$8,137.14$3,000.00$1,000.00
42Field office, type A (619E16000)MNTH3$1,200.00$1,200.00$736.84$250.00$800.00
43Construction layout stakes and surveying (623E10000)LS1$10,604$7,000.00$17,474$3,600.00$8,000.00
44Mobilization (624E10000)LS1$20,000$20,000$32,439$10,000$10,000
ODOT contract 260051: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of January 29, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy