ODOT contract 260066 bid tabulation
PRE-MR 112-00.99 N Maple Ph 2 (MINOR RECONSTRUCTION). Let by Ohio DOT on January 29, 2026, PRE. 6 bids received; low bid $2,438,718 by Brumbaugh Construction Inc, -19% against the engineer's estimate of $3,004,000.
- Owner
- Ohio DOT
- Letting
- 29 JAN 2026
- Pay items
- 111
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Brumbaugh Construction Inc | $2,438,718 | Low | -19% |
| 2 | Double Jay Construction Inc | $2,526,468 | +4.0% | -16% |
| 3 | Milcon Concrete Inc | $2,695,540 | +11% | -10% |
| 4 | Barrett Paving Materials Inc | $2,961,980 | +21% | -1.0% |
| 5 | Sunesis Construction Co | $3,406,382 | +40% | +13% |
| 6 | Complete General Construction Company | $3,963,156 | +63% | +32% |
Engineer's estimate: $3,004,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Brumbaugh Construction Inc | 2. Double Jay Construction Inc | 3. Milcon Concrete Inc | 4. Barrett Paving Materials Inc | 5. Sunesis Construction Co | 6. Complete General Construction Company |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $50,374 | $47,069 | $45,350 | $45,500 | $30,000 | $70,000 |
| 2 | Pavement removed (202E23000) | SY | 8,735 | $5.50 | $6.95 | $5.00 | $5.00 | $9.82 | $8.00 |
| 3 | Walk removed (202E30000) | SF | 16,342 | $1.25 | $1.20 | $0.70 | $3.00 | $1.05 | $2.50 |
| 4 | Steps removed (202E30200) | FT | 17 | $16.00 | $28.45 | $55.00 | $20.00 | $138.15 | $32.00 |
| 5 | Curb removed (202E32000) | FT | 3,075 | $4.00 | $5.05 | $2.40 | $4.00 | $3.25 | $6.00 |
| 6 | Pipe removed, 24" and under (202E35100) | FT | 1,989 | $29.00 | $14.45 | $29.00 | $27.00 | $19.27 | $20.00 |
| 7 | Manhole removed (202E58000) | EACH | 4 | $200.00 | $546.00 | $4,100.00 | $1,300.00 | $690.74 | $1,000.00 |
| 8 | Catch basin removed (202E58100) | EACH | 11 | $200.00 | $436.00 | $655.00 | $540.00 | $502.36 | $530.00 |
| 9 | Valve box removed (202E75610) | EACH | 4 | $200.00 | $199.00 | $225.00 | $135.00 | $144.98 | $510.00 |
| 10 | Removal misc.:abandoned gas line (202E98200) | FT | 1,500 | $5.00 | $14.00 | $8.50 | $14.00 | $21.17 | $20.00 |
| 11 | Removal misc.:conduit (202E98200) | FT | 25 | $10.00 | $14.80 | $19.00 | $17.00 | $25.96 | $40.00 |
| 12 | Excavation (203E10000) | CY | 2,976 | $22.00 | $19.30 | $27.00 | $31.00 | $43.27 | $50.00 |
| 13 | Embankment (203E20000) | CY | 164 | $21.00 | $19.35 | $20.00 | $48.00 | $27.70 | $24.00 |
| 14 | Excavation of subgrade (204E13000) | CY | 2,752 | $21.00 | $16.75 | $23.50 | $40.00 | $46.36 | $35.00 |
| 15 | Granular material, type C (204E30020) | CY | 2,752 | $60.00 | $51.15 | $49.00 | $60.00 | $77.50 | $45.00 |
| 16 | Proof rolling (204E45000) | HR | 5 | $225.00 | $229.00 | $210.00 | $250.00 | $208.76 | $350.00 |
| 17 | Geotextile fabric (204E50000) | SY | 7,801 | $1.25 | $1.55 | $0.75 | $2.00 | $3.44 | $1.50 |
| 18 | Fence, misc.:4' chain link, black, Z gate (607E98100) | EACH | 3 | $3,100.00 | $3,245.00 | $568.00 | $3,000.00 | $2,950.00 | $2,950.00 |
| 19 | 4" concrete walk, as per plan (608E10001) | SF | 14,343 | $7.75 | $7.10 | $8.30 | $6.25 | $8.15 | $10.00 |
| 20 | Concrete steps, type B, as per plan (608E41001) | FT | 17 | $235.00 | $132.75 | $253.00 | $200.00 | $265.24 | $90.00 |
| 21 | Curb ramp, as per plan (608E52001) | SF | 2,977 | $19.00 | $16.55 | $20.00 | $16.50 | $18.92 | $30.00 |
| 22 | Monument, misc.: reid stone (623E40900) | EACH | 3 | $900.00 | $2,855.00 | $1,214.00 | $2,000.00 | $1,122.04 | $1,000.00 |
| 23 | Special - consultant for concrete quality control (690E98400) | LS | 1 | $27,500 | $33,459 | $35,822 | $21,500 | $8,500.00 | $42,000 |
| 24 | Inspection and compaction testing of unbound materials (878E25000) | LS | 1 | $44,000 | $48,931 | $26,270 | $31,500 | $18,300 | $11,000 |
| 25 | Topsoil (659E00300) | CY | 271 | $75.00 | $71.50 | $72.00 | $72.00 | $65.00 | $55.00 |
| 26 | Seeding and mulching, class 1 (659E00500) | SY | 2,435 | $2.00 | $2.70 | $2.00 | $1.70 | $10.39 | $1.90 |
| 27 | Repair seeding and mulching (659E14000) | SY | 123 | $2.00 | $2.70 | $2.30 | $1.70 | $2.45 | $1.90 |
| 28 | Commercial fertilizer (659E20000) | TON | 0.34 | $1,000.00 | $840.00 | $1,592.00 | $900.00 | $760.00 | $900.00 |
| 29 | Lime (659E31000) | ACRE | 0.51 | $100.00 | $60.00 | $472.00 | $100.00 | $50.00 | $100.00 |
| 30 | Water (659E35000) | MGAL | 8 | $1.00 | $55.00 | $1.25 | $10.00 | $50.00 | $10.00 |
| 31 | Storm water pollution prevention plan (832E15000) | LS | 1 | $3,150.00 | $2,970.00 | $3,300.00 | $4,500.00 | $2,900.00 | $2,900.00 |
| 32 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $8,250.00 | $19,800 | $14,600 | $16,000 | $7,560.00 | $7,490.00 |
| 33 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $6,500.00 | $12,100 | $12,770 | $12,000 | $10,494 | $10,500 |
| 34 | Erosion control (832E30000) | EACH | 30,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 35 | 4" base pipe underdrains (605E06000) | FT | 2,804 | $10.00 | $12.15 | $11.75 | $20.00 | $17.22 | $15.00 |
| 36 | 4" conduit, type F for underdrain outlet (611E00410) | FT | 270 | $15.00 | $21.45 | $14.00 | $25.00 | $42.88 | $14.00 |
| 37 | 6" conduit, type B (611E00900) | FT | 17 | $55.00 | $45.45 | $150.00 | $100.00 | $55.19 | $95.00 |
| 38 | 6" conduit, type E (611E01400) | FT | 1,564 | $24.00 | $23.10 | $30.40 | $25.00 | $43.79 | $110.00 |
| 39 | 12" conduit, type B (611E04400) | FT | 595 | $47.00 | $50.75 | $97.00 | $100.00 | $92.42 | $152.00 |
| 40 | 15" conduit, type B (611E05900) | FT | 240 | $65.00 | $71.50 | $111.00 | $100.00 | $112.29 | $165.00 |
| 41 | 18" conduit, type B (611E07400) | FT | 348 | $72.00 | $80.25 | $125.00 | $105.00 | $104.99 | $176.00 |
| 42 | 24" conduit, type B (611E10400) | FT | 379 | $91.00 | $97.80 | $190.00 | $125.00 | $138.56 | $230.00 |
| 43 | 36" conduit, type B (611E16400) | FT | 343 | $128.00 | $152.70 | $193.00 | $125.00 | $211.15 | $324.00 |
| 44 | Conduit, misc.:type B for drainage discharge conti (611E97400) | FT | 20 | $13.00 | $70.45 | $55.00 | $30.00 | $87.50 | $122.00 |
| 45 | Conduit, misc.:type C for drainage discharge conti (611E97400) | FT | 20 | $13.00 | $66.80 | $55.00 | $30.00 | $68.42 | $102.00 |
| 46 | Conduit, misc.:type E for drainage discharge conti (611E97400) | FT | 20 | $13.00 | $75.50 | $55.00 | $30.00 | $68.42 | $124.00 |
| 47 | Conduit, misc.:type F for drainage discharge conti (611E97400) | FT | 20 | $13.00 | $71.80 | $55.00 | $30.00 | $68.42 | $124.00 |
| 48 | Catch basin, misc.: CB-1 (611E98690) | EACH | 18 | $2,350.00 | $2,716.00 | $2,831.00 | $3,575.00 | $3,871.45 | $4,800.00 |
| 49 | Catch basin, misc.: CB-1A (611E98690) | EACH | 7 | $3,000.00 | $4,963.00 | $4,871.00 | $6,000.00 | $5,112.64 | $6,000.00 |
| 50 | Manhole, no. 3 (611E99574) | EACH | 11 | $3,175.00 | $5,152.00 | $5,143.00 | $5,550.00 | $5,535.92 | $5,200.00 |
| 51 | Manhole, no. 3, as per plan (611E99575) | EACH | 1 | $9,400.00 | $16,039 | $14,885 | $12,500 | $17,192 | $15,000 |
| 52 | Manhole, no. 3 with 90" base I.D. and 8" weir (611E99582) | EACH | 1 | $11,700 | $13,093 | $17,151 | $12,750 | $13,456 | $13,000 |
| 53 | Inspection well (611E99720) | EACH | 1 | $750.00 | $2,849.00 | $6,600.00 | $1,600.00 | $2,393.28 | $1,750.00 |
| 54 | Drainage structure, misc.:clean out (611E99900) | EACH | 12 | $950.00 | $538.00 | $780.00 | $520.00 | $1,136.93 | $1,350.00 |
| 55 | Manufactured water quality structure, type 2 (895E10020) | EACH | 1 | $37,000 | $20,085 | $19,630 | $28,500 | $31,994 | $19,500 |
| 56 | Pavement planing, asphalt concrete, as per plan, 1 (254E01001) | SY | 716 | $13.00 | $13.75 | $17.00 | $25.00 | $22.00 | $22.00 |
| 57 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 602 | $230.00 | $242.00 | $256.00 | $200.00 | $320.00 | $320.00 |
| 58 | Aggregate base (304E20000) | CY | 1,860 | $62.00 | $55.40 | $57.50 | $70.00 | $86.46 | $80.00 |
| 59 | Non-tracking tack coat (407E20000) | GAL | 897 | $6.00 | $6.60 | $7.40 | $4.00 | $10.00 | $10.00 |
| 60 | Stabilized crushed aggregate (411E10000) | CY | 178 | $66.00 | $134.85 | $78.00 | $110.00 | $131.26 | $80.00 |
| 61 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 276 | $250.00 | $264.00 | $279.00 | $235.00 | $495.00 | $495.00 |
| 62 | Asphalt concrete intermediate course, type 2, (449) (441E70300) | CY | 352 | $240.00 | $253.00 | $267.00 | $200.00 | $460.00 | $460.00 |
| 63 | Asphalt concrete surface course, type 1, (449), (driveways) (441E70500) | CY | 2 | $315.00 | $465.00 | $341.00 | $1,500.00 | $3,500.00 | $3,500.00 |
| 64 | Asphalt concrete intermediate course, type 2, (449), (driveways) (441E70700) | CY | 3 | $315.00 | $420.00 | $341.00 | $1,000.00 | $2,500.00 | $2,500.00 |
| 65 | 6" non-reinforced concrete pavement, class QC 1P, as per plan (452E10011) | SY | 180 | $96.00 | $89.85 | $99.00 | $77.00 | $93.69 | $125.00 |
| 66 | 8" non-reinforced concrete pavement, class QC 1P, as per plan (452E12011) | SY | 13 | $121.00 | $113.90 | $114.00 | $91.00 | $137.22 | $238.00 |
| 67 | Combination curb and gutter, type 2, as per plan (609E12001) | FT | 3,232 | $27.00 | $27.25 | $28.75 | $22.00 | $27.66 | $38.00 |
| 68 | Curb, type 6, as per plan (609E26001) | FT | 167 | $59.00 | $61.70 | $65.00 | $50.00 | $62.70 | $62.00 |
| 69 | 6" water main polyvinyl chloride pipe and fittings, AWWA C900, DR18 (638E01130) | FT | 42 | $53.00 | $132.80 | $87.25 | $177.00 | $391.17 | $300.00 |
| 70 | 3/4" polyethylene service branch (638E05300) | FT | 875 | $70.00 | $100.40 | $98.75 | $160.00 | $119.10 | $185.00 |
| 71 | 6" gate valve and valve box (638E07800) | EACH | 1 | $1,925.00 | $1,921.00 | $1,900.00 | $1,580.00 | $7,485.71 | $1,750.00 |
| 72 | 6" X 6" tapping sleeve, valve and valve box (638E09300) | EACH | 3 | $4,700.00 | $5,444.00 | $6,760.00 | $5,945.00 | $8,368.47 | $22,500 |
| 73 | 6" fire hydrant (638E10200) | EACH | 3 | $5,900.00 | $5,420.00 | $5,975.00 | $5,360.00 | $14,394 | $7,000.00 |
| 74 | Fire hydrant removed (638E10480) | EACH | 3 | $525.00 | $794.00 | $1,100.00 | $150.00 | $526.00 | $4,000.00 |
| 75 | Valve box adjusted to grade (638E10800) | EACH | 11 | $140.00 | $294.00 | $445.00 | $700.00 | $46.48 | $410.00 |
| 76 | Service box adjusted to grade (638E10900) | EACH | 2 | $140.00 | $294.00 | $245.00 | $25.00 | $234.04 | $175.00 |
| 77 | Meter and chamber removed and reset (638E11100) | EACH | 38 | $425.00 | $499.00 | $366.00 | $365.00 | $561.02 | $1,600.00 |
| 78 | Water work, misc.: 6" water main reconnected (638E98000) | EACH | 12 | $675.00 | $1,118.00 | $741.00 | $837.00 | $1,237.90 | $5,000.00 |
| 79 | Water work, misc.: 6" water main relocated (638E98600) | FT | 195 | $365.00 | $209.00 | $215.00 | $295.00 | $378.58 | $270.00 |
| 80 | 6" conduit, type B (611E00900) | FT | 32 | $360.00 | $147.95 | $137.00 | $400.00 | $201.49 | $185.00 |
| 81 | 6" conduit, type B (611E00900) | FT | 255 | $135.00 | $95.95 | $140.00 | $435.00 | $291.69 | $225.00 |
| 82 | 8" conduit, type B (611E01800) | FT | 537 | $108.00 | $110.00 | $110.00 | $335.00 | $217.17 | $220.00 |
| 83 | Conduit, misc.:4" sanitary sewer lateral repair (611E97400) | FT | 50 | $23.00 | $53.40 | $108.00 | $156.50 | $302.68 | $165.00 |
| 84 | Conduit, misc.:6" sanitary sewer lateral repair (611E97400) | FT | 50 | $27.00 | $66.40 | $133.00 | $162.50 | $312.79 | $175.00 |
| 85 | Manhole, no. 3 (611E99574) | EACH | 6 | $4,900.00 | $6,760.00 | $5,507.00 | $6,440.00 | $5,876.05 | $7,000.00 |
| 86 | Manhole reconstructed to grade (611E99660) | EACH | 4 | $1,675.00 | $1,778.00 | $3,464.00 | $1,036.00 | $1,174.91 | $1,800.00 |
| 87 | Drainage structure, misc.: sanitary cleanout (611E99900) | EACH | 9 | $885.00 | $638.00 | $1,317.00 | $874.00 | $1,097.33 | $1,400.00 |
| 88 | Ground mounted support, no. 3 post (630E03100) | FT | 261 | $16.00 | $16.50 | $22.00 | $15.00 | $15.00 | $16.50 |
| 89 | Street name sign support, no. 3 post (630E08520) | FT | 102 | $16.00 | $16.50 | $22.00 | $15.00 | $15.00 | $19.50 |
| 90 | Sign post reflector (630E08600) | EACH | 21 | $55.00 | $58.00 | $80.00 | $52.00 | $52.00 | $60.00 |
| 91 | Sign, flat sheet (630E80100) | SF | 186 | $16.00 | $17.05 | $26.45 | $15.50 | $15.50 | $23.50 |
| 92 | Sign, double faced, street name (630E80500) | EACH | 12 | $135.00 | $143.00 | $335.00 | $130.00 | $130.00 | $103.00 |
| 93 | Removal of ground mounted sign and disposal (630E84900) | EACH | 28 | $21.00 | $22.00 | $19.00 | $20.00 | $20.00 | $15.00 |
| 94 | Removal of ground mounted post support and disposal (630E86002) | EACH | 19 | $26.00 | $28.00 | $25.00 | $25.00 | $25.00 | $25.00 |
| 95 | Removal of pole mounted sign and disposal (630E87500) | EACH | 1 | $21.00 | $22.00 | $18.00 | $20.00 | $20.00 | $15.00 |
| 96 | Center line (644E00300) | MI | 0.32 | $13,750 | $5,500.00 | $5,686.00 | $8,175.00 | $8,175.00 | $13,000 |
| 97 | Stop line (644E00500) | FT | 144 | $11.00 | $8.80 | $9.50 | $10.20 | $10.50 | $10.25 |
| 98 | Crosswalk line, 12" (644E00620) | FT | 573 | $5.00 | $6.60 | $7.00 | $5.10 | $5.10 | $4.90 |
| 99 | Crosswalk line, 24" (644E00630) | FT | 560 | $10.00 | $7.70 | $8.00 | $8.15 | $8.15 | $9.75 |
| 100 | Railroad symbol marking (644E01000) | EACH | 2 | $825.00 | $550.00 | $570.00 | $520.00 | $520.00 | $785.00 |
| 101 | Detour signing, as per plan (614E12421) | LS | 1 | $5,250.00 | $5,489.00 | $10,880 | $5,000.00 | $4,990.00 | $9,500.00 |
| 102 | Water (616E10000) | MGAL | 10 | $1.00 | $110.00 | $135.00 | $100.00 | $14.93 | $200.00 |
| 103 | Railroad flagging services (900E00100) | EACH | 84,280 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 104 | Premium on railroads' protective public liability and property damage liability insurance (100E00300) | LS | 1 | $4,500.00 | $16,500 | $5,686.00 | $16,525 | $5,500.00 | $3,500.00 |
| 105 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $14,750 | $18,146 | $32,232 | $15,000 | $17,596 | $25,500 |
| 106 | Maintaining traffic (614E11000) | LS | 1 | $35,000 | $88,403 | $23,360 | $55,715 | $17,500 | $10,000 |
| 107 | Field office, type B (619E16010) | MNTH | 9 | $3,000.00 | $2,280.00 | $3,255.00 | $1,500.00 | $1,273.89 | $4,760.00 |
| 108 | Construction layout stakes and surveying, as per plan (623E10001) | LS | 1 | $50,000 | $24,211 | $63,555 | $40,000 | $39,200 | $75,000 |
| 109 | Preconstruction survey monument verification and report (623E50000) | LS | 1 | $3,500.00 | $2,200.00 | $9,400.00 | $5,600.00 | $5,600.00 | $5,000.00 |
| 110 | Post construction survey monument verification and report (623E51000) | LS | 1 | $3,500.00 | $2,200.00 | $9,400.00 | $8,400.00 | $5,600.00 | $5,000.00 |
| 111 | Mobilization (624E10000) | LS | 1 | $65,000 | $60,388 | $33,350 | $50,000 | $107,550 | $195,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of January 29, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.