ODOT contract 250200 bid tabulation
STA-Sippo Valley Trail Bridge 11 (CULVERT REPLACEMENT). Let by Ohio DOT on April 10, 2025, STA. 5 bids received; low bid $330,889 by Stanley Miller Construction Company, -12% against the engineer's estimate of $375,000.
- Owner
- Ohio DOT
- Letting
- 10 APR 2025
- Pay items
- 42
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Stanley Miller Construction Company | $330,889 | Low | -12% |
| 2 | Crawford Construction Company Inc | $368,958 | +12% | -2.0% |
| 3 | Black Horse Bridge Construction Inc | $383,785 | +16% | +2.0% |
| 4 | Eclipse Co LLC | $658,561 | +99% | +76% |
| 5 | Craig Edward Susany Inc | $749,519 | +127% | +100% |
Engineer's estimate: $375,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Stanley Miller Construction Company | 2. Crawford Construction Company Inc | 3. Black Horse Bridge Construction Inc | 4. Eclipse Co LLC | 5. Craig Edward Susany Inc |
|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $2,670.00 | $5,600.00 | $5,200.00 | $5,500.00 | $5,000.00 |
| 2 | Pavement removed (202E23000) | SY | 50 | $6.00 | $27.00 | $10.00 | $16.50 | $100.00 |
| 3 | Excavation (203E10000) | CY | 12 | $232.00 | $207.00 | $40.00 | $184.00 | $200.00 |
| 4 | Embankment (203E20000) | CY | 25 | $147.00 | $175.00 | $22.00 | $222.50 | $200.00 |
| 5 | Granular material, type B (203E35110) | CY | 10 | $267.00 | $306.00 | $120.00 | $332.50 | $200.00 |
| 6 | Subgrade compaction (204E10000) | SY | 62 | $5.00 | $5.70 | $10.00 | $10.00 | $25.00 |
| 7 | Special - as-built construction plans (690E91000) | LS | 1 | $1,755.00 | $970.00 | $2,000.00 | $3,500.00 | $500.00 |
| 8 | Special - survey control verification (690E98400) | LS | 1 | $1,200.00 | $1,700.00 | $2,500.00 | $3,500.00 | $10,000 |
| 9 | Topsoil (659E00300) | CY | 6 | $63.00 | $355.00 | $140.00 | $258.00 | $200.00 |
| 10 | Seeding and mulching (659E10000) | SY | 51 | $62.00 | $48.00 | $12.00 | $29.50 | $10.00 |
| 11 | Commercial fertilizer (659E20000) | TON | 0.01 | $800.00 | $4,480.00 | $500.00 | $1,750.00 | $1,000.00 |
| 12 | Lime (659E31000) | ACRE | 0.02 | $900.00 | $1,700.00 | $200.00 | $100.00 | $500.00 |
| 13 | Water (659E35000) | MGAL | 1 | $1.00 | $11.20 | $1.00 | $1.00 | $1.00 |
| 14 | Erosion control (832E30000) | EACH | 2,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 15 | Aggregate base (304E20000) | CY | 10 | $261.00 | $306.00 | $150.00 | $277.50 | $200.00 |
| 16 | Tack coat (407E10000) | GAL | 3 | $2.25 | $5.50 | $10.00 | $10.00 | $10.00 |
| 17 | Prime coat (408E10000) | GAL | 20 | $3.35 | $50.00 | $20.00 | $20.00 | $60.00 |
| 18 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 5 | $1,250.00 | $5,230.00 | $710.00 | $710.00 | $2,500.00 |
| 19 | Structure removed (202E11000) | LS | 1 | $4,889.00 | $34,600 | $20,520 | $18,980 | $178,000 |
| 20 | Embankment, as per plan (203E20001) | CY | 72 | $101.00 | $80.00 | $125.00 | $118.00 | $200.00 |
| 21 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $7,556.00 | $7,900.00 | $51,500 | $55,622 | $50,000 |
| 22 | Unclassified excavation (503E21300) | LS | 1 | $11,889 | $14,700 | $20,650 | $9,992.00 | $50,000 |
| 23 | Pile driving equipment mobilization (505E11100) | LS | 1 | $23,944 | $17,900 | $32,000 | $40,800 | $100,000 |
| 24 | 12" cast-in-place reinforced concrete piles, driven (507E00500) | FT | 450 | $26.00 | $7.00 | $40.00 | $135.50 | $55.00 |
| 25 | 12" cast-in-place reinforced concrete piles, furnished (507E00550) | FT | 500 | $46.30 | $61.00 | $44.00 | $139.50 | $96.00 |
| 26 | Prebored holes (507E92200) | FT | 50 | $40.00 | $185.00 | $110.00 | $125.00 | $500.00 |
| 27 | Epoxy coated steel reinforcement (509E10000) | LB | 3,670 | $1.90 | $3.50 | $4.00 | $7.50 | $4.00 |
| 28 | Class QC1 concrete, retaining/wingwall including footing (511E46210) | CY | 33 | $780.00 | $1,200.00 | $950.00 | $2,398.50 | $1,000.00 |
| 29 | Class QC1 concrete, headwall (511E46610) | CY | 4 | $1,040.00 | $1,400.00 | $1,450.00 | $3,876.50 | $1,000.00 |
| 30 | Sealing of concrete surfaces (512E10000) | SY | 40 | $85.00 | $77.00 | $40.00 | $58.50 | $20.00 |
| 31 | Type 2 waterproofing (512E33000) | SY | 64 | $31.00 | $50.00 | $24.00 | $35.00 | $35.00 |
| 32 | 1" preformed expansion joint filler (516E13600) | SF | 45 | $2.60 | $12.00 | $6.00 | $8.00 | $15.00 |
| 33 | Railing, misc.:timber railing on steel posts (517E76300) | FT | 64.25 | $203.00 | $265.00 | $284.00 | $428.00 | $250.00 |
| 34 | Porous backfill with geotextile fabric (518E21200) | CY | 12 | $316.00 | $260.00 | $180.00 | $269.50 | $250.00 |
| 35 | Dynamic load testing (523E20000) | EACH | 1 | $4,756.00 | $4,400.00 | $4,500.00 | $6,000.00 | $6,000.00 |
| 36 | Rock channel protection, type C with geotextile fabric (601E32204) | CY | 16 | $285.00 | $450.00 | $180.00 | $322.50 | $250.00 |
| 37 | Conduit, type A, precast reinforced concrete three sided flat topped culvert (611E70000) | FT | 16 | $2,093.00 | $2,800.00 | $3,600.00 | $6,335.50 | $3,750.00 |
| 38 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $4,670.00 | $4,400.00 | $4,000.00 | $8,580.50 | $20,000 |
| 39 | Maintaining traffic (614E11000) | LS | 1 | $2,445.00 | $3,900.00 | $4,000.00 | $5,387.00 | $2,000.00 |
| 40 | Field office, type B (619E16010) | MNTH | 6 | $500.00 | $2,750.00 | $1,000.00 | $1,281.50 | $2,000.00 |
| 41 | Construction layout stakes and surveying (623E10000) | LS | 1 | $17,156 | $2,700.00 | $8,000.00 | $8,288.50 | $10,000 |
| 42 | Mobilization (624E10000) | LS | 1 | $79,340 | $19,500 | $20,000 | $50,501 | $20,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of April 10, 2025. Compiled by Mirage Metrics.