ODOT contract 260371 bid tabulation

SUM-SR 21-01.07 (BRIDGE REPAIR). Let by Ohio DOT on August 13, 2026, SUM. 9 bids received; low bid $1,872,704 by J D Williamson Construction Co Inc, -17% against the engineer's estimate of $2,250,000.

Owner
Ohio DOT
Letting
13 AUG 2026
Pay items
88
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1J D Williamson Construction Co Inc$1,872,704Low-17%
2Ruhlin Company$1,999,872+7.0%-11%
3Beaver Excavating Company$2,278,750+22%+1.0%
4Shelly & Sands Inc$2,319,457+24%+3.0%
5Kenmore Construction Co Inc$2,335,877+25%+4.0%
6Black Horse Bridge Construction Inc$2,347,540+25%+4.0%
7Great Lakes Construction Co$2,514,163+34%+12%
8Fechko Excavating LLC$2,593,927+39%+15%
9Perk Company Inc$2,625,158+40%+17%
ODOT contract 260371: bids by rank

Engineer's estimate: $2,250,000.

Bid tabulation

LinePay itemUnitQuantity1. J D Williamson Construction Co Inc2. Ruhlin Company3. Beaver Excavating Company4. Shelly & Sands Inc5. Kenmore Construction Co Inc6. Black Horse Bridge Construction Inc
1Clearing and grubbing (201E11000)LS1$8,000.00$5,500.00$6,000.00$5,000.00$5,000.00$8,200.00
2Pavement removed (202E23000)SY199$8.00$29.00$22.00$25.00$30.00$18.00
3Guardrail removed (202E38000)FT638$2.50$2.50$2.50$2.50$3.00$3.50
4Excavation (203E10000)CY122$24.00$54.00$30.00$32.00$40.00$50.00
5Embankment (203E20000)CY50$20.00$75.00$50.00$45.00$50.00$29.00
6Subgrade compaction (204E10000)SY325$6.25$7.00$4.00$10.00$3.00$4.00
7Excavation of subgrade (204E13000)CY3$40.00$168.00$30.00$200.00$100.00$85.00
8Granular material, type B (204E30010)CY3$100.00$347.00$120.00$250.00$100.00$175.00
9Geotextile fabric (204E50000)SY9$5.00$58.00$10.00$45.00$10.00$46.00
10Guardrail, type MGS (606E15050)FT425$23.00$22.80$22.80$23.00$24.50$22.80
11Rounded end section (606E20050)EACH1$120.00$120.00$120.00$120.00$200.00$120.00
12Anchor assembly, MGS type E (606E26150)EACH2$2,600.00$2,580.00$2,580.00$2,580.00$2,950.00$2,580.00
13Anchor assembly, MGS type T (606E26550)EACH1$1,400.00$1,375.00$1,375.00$1,375.00$1,650.00$1,375.00
14MGS bridge terminal assembly, type 1 (606E35002)EACH4$2,600.00$2,540.00$2,540.00$2,540.00$2,950.00$2,540.00
15Fence, type CLT (607E23000)FT117$42.00$41.50$41.50$43.00$66.50$42.00
16Special - mailbox support (690E50000)EACH3$150.00$265.00$265.00$265.00$300.00$265.00
17Special - as-built construction plans (690E91000)LS1$1,600.00$500.00$1,250.00$2,750.00$3,000.00$2,500.00
18Special - survey control verification (690E98400)LS1$5,000.00$5,300.00$1,250.00$3,000.00$2,500.00$5,000.00
19Tied concrete block mat with type 2 underlayment (601E21060)SY107$90.00$126.00$130.00$100.00$85.00$90.00
20Soil analysis test (659E00100)EACH2$75.00$400.00$400.00$150.00$50.00$200.00
21Topsoil (659E00300)CY15$70.00$140.00$80.00$125.00$70.00$90.00
22Seeding and mulching (659E10000)SY134$4.00$6.50$10.00$25.00$20.00$11.00
23Commercial fertilizer (659E20000)TON0.03$450.00$1,500.00$1,500.00$1,250.00$10.00$1,000.00
24Lime (659E31000)ACRE0.03$30.00$135.00$1.00$150.00$10.00$500.00
25Water (659E35000)MGAL2$1.00$60.00$60.00$1.00$10.00$1.00
26Erosion control (832E30000)EACH24,000$1.00$1.00$1.00$1.00$1.00$1.00
27Aggregate drains (605E31100)FT168$17.00$26.00$18.00$30.00$30.00$24.00
28Pavement planing, asphalt concrete, variable thick (254E01000)SY698$20.00$10.40$10.40$23.25$6.00$20.00
29Asphalt concrete base, PG64-22, (449) (301E56000)CY35$220.00$420.00$420.00$459.00$350.00$220.00
30Aggregate base (304E20000)CY55$100.00$228.00$130.00$175.00$85.00$120.00
31Non-tracking tack coat (407E20000)GAL116$4.00$3.10$3.10$3.05$6.00$4.00
32Prime coat, as per plan (408E10001)GAL20$20.00$30.00$30.00$3.75$6.00$20.00
33Asphalt concrete surface course, type 1, (449), PG70-22M (441E70100)CY73$340.00$391.00$391.00$479.25$255.00$340.00
34Curb, type 4-C (609E24510)FT72$30.00$49.29$90.00$85.00$50.00$60.00
35Compacted aggregate (617E10100)CY5$155.00$630.00$150.00$175.00$100.00$165.00
36Ground mounted support, no. 2 post (630E02100)FT66$24.00$15.00$15.00$15.00$15.00$15.00
37Ground mounted support, no. 3 post (630E03100)FT14$26.00$16.50$16.50$16.50$16.50$16.50
38Sign, flat sheet (630E80100)SF18$30.00$30.00$30.00$30.00$30.00$31.00
39Sign, flat sheet (630E80100)SF6$30.00$30.00$30.00$30.00$30.00$30.00
40Removal of ground mounted sign and disposal (630E84900)EACH6$17.00$25.00$25.00$25.00$25.00$25.00
41Removal of ground mounted sign and reerection (630E85100)EACH1$120.00$100.00$100.00$100.00$100.00$100.00
42Removal of ground mounted post support and disposal (630E86002)EACH7$23.00$25.00$25.00$25.00$25.00$25.00
43Edge line, 4" (646E10000)MI0.15$12,500$23,000$23,000$23,000$23,000$23,000
44Center line (646E10200)MI0.07$25,000$34,000$34,000$34,000$34,000$34,000
45Law enforcement officer with patrol car for assistance (614E11110)HR80$100.00$100.00$85.00$130.00$110.00$100.00
46Detour signing (614E12420)LS1$8,200.00$4,500.00$4,500.00$4,500.00$7,500.00$4,500.00
47Water (616E10000)MGAL10$5.00$38.54$70.00$110.00$10.00$10.00
48Portions of structure removed, over 20 foot span, as per plan (202E11203)LS1$160,000$156,500$300,000$164,705$280,000$252,600
49Approach slab removed (202E22900)SY80$45.00$85.00$60.00$85.00$60.00$55.00
50Wearing course removed (202E23500)SY709$6.00$1.00$4.00$4.50$5.00$5.00
51Unclassified excavation (503E21300)LS1$20,000$15,000$9,000.00$11,000$9,000.00$11,100
52Epoxy coated steel reinforcement (509E10000)LB77,270$1.40$1.70$1.60$1.50$1.75$1.50
53No. 4 deformed GFRP reinforcement (509E30020)FT4,996$1.60$2.00$1.90$3.00$1.75$2.00
54Dowel holes with nonshrink, nonmetallic grout (510E10000)EACH192$22.00$30.00$34.00$30.00$35.00$24.00
55Class QC2 concrete with QC/QA, bridge deck (511E34446)CY227$950.00$1,115.00$1,150.00$1,400.00$1,500.00$1,325.00
56Class QC2 concrete with QC/QA, bridge deck (parapet) (511E34450)CY56$880.00$750.00$1,100.00$700.00$1,200.00$1,400.00
57Class QC1 concrete, pier cap (511E42510)CY10$2,100.00$4,250.00$1,800.00$5,500.00$2,000.00$1,300.00
58Sealing of concrete surfaces (epoxy-urethane) (512E10100)SY661$30.00$36.00$35.00$35.00$25.00$50.00
59Removal of existing coatings from concrete surfaces (512E74000)SY234$32.00$32.00$35.00$35.00$50.00$42.00
60Structural steel members, level 2, as per plan (513E10241)LB152,400$4.25$3.90$4.84$5.00$4.72$5.00
61Welded stud shear connectors (513E20000)EACH3,190$4.50$4.45$5.00$4.45$4.45$5.00
62Armorless preformed joint seal (516E10010)FT69$54.00$61.00$65.00$65.00$120.00$24.00
631" preformed expansion joint filler (516E13600)SF15$7.00$22.00$16.00$10.00$20.00$10.00
642" preformed expansion joint filler (516E13900)SF63$9.00$13.55$16.00$10.00$20.00$14.00
65Semi-integral abutment expansion joint seal (516E14020)FT95$50.00$58.00$40.00$55.00$55.00$40.00
66Elastomeric bearing with internal laminates and load plate, as per plan (516E44101)EACH10$2,300.00$1,770.00$1,275.00$1,600.00$1,100.00$1,700.00
67Elastomeric bearing with internal laminates and load plate, as per plan (516E44101)EACH5$1,600.00$1,800.00$1,450.00$1,600.00$1,250.00$1,900.00
68Elastomeric bearing with internal laminates and load plate, as per plan (516E44201)EACH10$1,400.00$1,920.00$1,600.00$1,600.00$1,400.00$2,500.00
69Porous backfill with geotextile fabric (518E21200)CY27$125.00$204.00$140.00$250.00$100.00$185.00
706" perforated corrugated plastic pipe (518E40000)FT70$21.00$17.00$16.00$10.00$25.00$16.00
716" non-perforated corrugated plastic pipe, including specials (518E40010)FT60$23.00$23.00$20.00$9.00$30.00$18.00
72Special - composite fiber wrap system (519E00100)SF102$50.00$95.00$125.00$125.00$65.00$105.00
73Patching concrete structure, as per plan (519E11101)SF100$110.00$165.00$185.00$200.00$110.00$210.00
74Reinforced concrete approach slabs with QC/QA (T=1 (526E10011)SY115$370.00$575.00$375.00$750.00$520.00$475.00
75Type C installation (526E90030)FT69$115.00$235.00$315.00$350.00$150.00$250.00
76Crushed aggregate slope protection (601E20010)CY99$120.00$117.00$160.00$200.00$100.00$130.00
77Tied concrete block mat with type 1 underlayment (601E21050)SY8$90.00$152.00$185.00$175.00$160.00$350.00
78Vandal protection fence, 6' straight, coated fabric, as per plan (607E39901)FT297$140.00$128.50$128.50$121.00$175.00$120.00
79Precast reinforced concrete outlet (611E99710)EACH4$350.00$340.00$425.00$360.00$400.00$700.00
80Structure grounding system (625E33000)EACH1$13,000$5,000.00$12,500$26,500$28,500$26,500
81Special - vertical clerance (690E98000)EACH1$1,000.00$5,300.00$1,250.00$1,100.00$1,000.00$2,500.00
82Premium for contract performance bond and for payment bond (103E05000)LS1$20,000$12,000$20,000$12,950$25,000$19,000
83Maintaining traffic (614E11000)LS1$50,000$50,000$92,500$47,900$90,000$110,000
84Field office, type B (619E16010)MNTH12$1,800.00$3,500.00$3,000.00$4,000.00$3,250.00$1,000.00
85Construction layout stakes and surveying (623E10000)LS1$15,000$40,000$14,000$22,250$15,000$14,000
86Mobilization (624E10000)LS1$95,000$100,000$113,937$119,853$100,000$120,000
100Semi-integral diaphragm guide (511E33500)EACH1$4,400.00$3,000.00$6,500.00$13,900$5,500.00$10,700
101Portable changeable message sign, as per plan (614E18601)SNMT12$1,100.00$850.00$850.00$850.00$1,000.00$850.00
ODOT contract 260371: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of August 13, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy