ODOT letting results, January 11, 2024
42 contracts let by Ohio DOT on January 11, 2024, $70,691,168 in low bids, a median of 3 bidders per contract. On the 42 with an engineer's estimate, the low bid came in under it 25 times; median low bid -5.0% against the estimate.
- Owner
- Ohio DOT
- Contracts
- 42
- Low bids, total
- $70,691,168
- Data through
- 12 NOV 2026
Contracts let that day
| Contract | Project | County | Bids | Low bidder | Low bid | Second bid | Gap | Against estimate | Source |
|---|---|---|---|---|---|---|---|---|---|
| 240008 | CRA-US 30-09.53 (FOUR LANE RESURFACING) | CRA | 2 | Kokosing Construction Company Inc | $9,248,944 | $9,366,181 | +1.0% | -5.0% | ODOT |
| 240022 | MOT-IR 70-00.00 (FOUR LANE RESURFACING) | MOT | 2 | John R Jurgensen Company | $5,398,241 | $6,434,915 | +19% | -6.0% | ODOT |
| 244002 | GEA-/LAK CU FY2023 (CULVERT REPLACEMENT) | GEA | 1 | Shook Company LLC | $3,596,245 | +37% | ODOT | ||
| 240038 | MUS-SR 284-00.00 (TWO LANE RESURFACING) | MUS | 2 | Shelly & Sands Inc | $3,555,325 | $4,288,813 | +21% | -6.0% | ODOT |
| 240015 | KNO-SR 229/SR 308-13.06/00.00 (INTERSECTION) | KNO | 3 | Shelly & Sands Inc | $3,269,457 | $3,269,517 | 0.0% | -7.0% | ODOT |
| 240029 | WYA-US 23-13.60 (MINOR RECONSTRUCTION) | WYA | 3 | Shelly & Sands Inc | $3,161,884 | $3,248,581 | +3.0% | -12% | ODOT |
| 240017 | LOG-PAVE-FY24 (TWO LANE RESURFACING) | LOG | 1 | Shelly Company | $2,928,109 | +9.0% | ODOT | ||
| 230596 | FRA-SR 3-19.92 (FOUR LANE RESURFACING) | FRA | 2 | Shelly & Sands Inc | $2,926,963 | $3,346,898 | +14% | +6.0% | ODOT |
| 240007 | CLE-SR 132-12.49 (INTERSECTION) | CLE | 4 | John R Jurgensen Company | $2,651,196 | $2,719,490 | +3.0% | +1.0% | ODOT |
| 240033 | D04-PM FY2024 (East) (PAVEMENT MARKING) | District 4 | 2 | The Aero-Mark Company LLC | $2,612,000 | $2,866,463 | +10% | -5.0% | ODOT |
| 240002 | AUG-SR 196/SR 197/SR 198-VAR (TWO LANE RESURFACING) | AUG | 1 | Shelly Company | $2,439,243 | +10% | ODOT | ||
| 240027 | UNI-/DEL-US 33/VAR-17.95/VAR (BRIDGE REPAIR) | UNI | 5 | Ruhlin Company | $2,360,194 | $2,542,756 | +8.0% | -14% | ODOT |
| 240003 | BEL-SR 147-02.84 (SLIDE REPAIR) | BEL | 5 | Alan Stone Co Inc | $2,094,252 | $2,122,115 | +1.0% | -18% | ODOT |
| 240018 | MAH-SR 11-13.30 Noise Wall (NOISE WALLS) | MAH | 5 | Rudzik Excavating Inc | $1,983,589 | $2,060,512 | +4.0% | -24% | ODOT |
| 240026 | SUM-SR 18-01.01 (FOUR LANE RESURFACING) | SUM | 7 | Shelly & Sands Inc | $1,899,094 | $2,109,000 | +11% | +2.0% | ODOT |
| 240013 | HOL-SR 39-06.72 (TWO LANE RESURFACING) | HOL | 3 | Melway Paving Co Inc | $1,439,186 | $1,466,993 | +2.0% | +1.0% | ODOT |
| 240028 | VAN-SR 81-02.55 (MINOR RECONSTRUCTION) | VAN | 3 | Miller Contracting Group Inc | $1,410,690 | $1,416,475 | 0.0% | -14% | ODOT |
| 240025 | SHE-SR 29-00.00 (TWO LANE RESURFACING) | SHE | 2 | Shelly Company | $1,380,796 | $1,442,000 | +4.0% | +3.0% | ODOT |
| 240021 | MER-SR 29-07.80 (BRIDGE REPLACEMENT (1 BRIDGE)) | MER | 5 | Brumbaugh Construction Inc | $1,315,000 | $1,322,749 | +1.0% | -19% | ODOT |
| 240020 | MED-/WAY-SR 83/SR 585-00.91/11.98 (TWO LANE RESURFACING) | MED | 5 | Kokosing Construction Company Inc | $1,293,122 | $1,509,537 | +17% | -7.0% | ODOT |
| 240024 | PIK-SR 220-08.28 (TWO LANE RESURFACING) | PIK | 2 | Shelly & Sands Inc | $1,176,467 | $1,335,404 | +14% | +3.0% | ODOT |
| 240004 | BRO-US 52-22.27 Slide Repair (SLIDE REPAIR) | BRO | 5 | Allard Excavation LLC | $1,170,854 | $1,170,947 | 0.0% | -6.0% | ODOT |
| 244000 | CLI-SR 73-01.80/20.74, CLI-SR 350-15.78 (CULVERT REPLACEMENT) | CLI | 4 | Axis Civil Construction LLC | $1,146,375 | $1,204,504 | +5.0% | +40% | ODOT |
| 244001 | CUY-US 422-09.59 Culvert (CULVERT REPLACEMENT) | CUY | 4 | Shook Company LLC | $1,055,630 | $794,922 | -25% | +15% | ODOT |
| 240019 | MAR-US 23-03.32/03.93, MAR-SR 423-01.60 (INTERSECTION) | MAR | 4 | Shelly & Sands Inc | $999,403 | $1,057,595 | +6.0% | -6.0% | ODOT |
| 240010 | D07-BH-FY24 (C) (BRIDGE REPAIR) | District 7 | 2 | Complete General Construction Company | $956,894 | $958,764 | 0.0% | +24% | ODOT |
| 240039 | NOB-SR 513/SR 564-07.03/00.26 (CULVERT REPLACEMENT) | NOB | 8 | Axis Civil Construction LLC | $868,442 | $967,947 | +11% | -9.0% | ODOT |
| 240035 | D08-Mowing FY2024 (A) (MOWING) | District 8 | 2 | Linkel Company | $820,912 | $849,150 | +3.0% | -5.0% | ODOT |
| 240014 | JEF-SR 152-06.45 (CHIP SEAL) | JEF | 3 | Shelly Company | $764,373 | $796,318 | +4.0% | +16% | ODOT |
| 240006 | CHP-SR 29-31.24 (BRIDGE REPAIR) | CHP | 2 | R & I Construction Inc | $763,960 | $888,892 | +16% | +5.0% | ODOT |
| 240016 | LIC-SR 13-00.42 (INTERSECTION) | LIC | 5 | Shelly Company | $738,428 | $769,602 | +4.0% | -8.0% | ODOT |
| 240034 | D04-PM R-WR FY2024 (PAVEMENT MARKING) | District 4 | 4 | American Roadway Logistics | $593,193 | $609,000 | +3.0% | -20% | ODOT |
| 240037 | D11-RPM-FY2024 (RAISED PAVEMENT MARKERS) | District 11 | 2 | A & A Safety Inc | $414,423 | $461,012 | +11% | +14% | ODOT |
| 240040 | RIC-SR 61/SR 598-12.74/00.71 (CULVERT REPLACEMENT) | RIC | 5 | Adena Corporation | $321,805 | $343,327 | +7.0% | +3.0% | ODOT |
| 240005 | CHP-/CLA-SR 29/US 40-24.31/03.73 (BRIDGE REPAIR) | CHP | 1 | BCC Ohio Inc | $305,675 | -4.0% | ODOT | ||
| 240023 | PER-CR 99-00.00 SRTS (SIDEWALK) | PER | 3 of 4 | $303,593 | $319,217 | +5.0% | -3.0% | ODOT | |
| 240012 | HOC-SR 664-15.15 (SIGNALIZATION) | HOC | 5 | Complete General Construction Company | $288,645 | $301,701 | +5.0% | -15% | ODOT |
| 240011 | HOC-SR 328-06.22 (CULVERT REPLACEMENT) | HOC | 7 | Axis Civil Construction LLC | $258,008 | $266,913 | +3.0% | -14% | ODOT |
| 240036 | D09-RPM-FY2024 (RAISED PAVEMENT MARKERS) | District 9 | 3 | Eaton Construction Co Inc | $224,839 | $296,824 | +32% | -18% | ODOT |
| 240041 | VIN-SR 328-06.42 (CULVERT REPLACEMENT) | VIN | 7 | Parker Corporation | $216,718 | $225,891 | +4.0% | -16% | ODOT |
| 240030 | CUY-IR 90-11.33 Ramp Safety (SIGNALIZATION) | CUY | 4 | Cornerstone Electric Inc | $190,000 | $211,875 | +12% | -24% | ODOT |
| 240032 | D03-MOW FY2024 (B) (MOWING) | District 3 | 2 | Linkel Company | $149,000 | $180,400 | +21% | +1.0% | ODOT |
Gap is the second bid over the low bid. Where a contract shows fewer bids than ODOT received, the others did not match their published totals and are left out.