Rudzik Excavating Inc: ODOT bid record
Rudzik Excavating Inc submitted 51 bids on Ohio DOT contracts in the data, from 23 JAN 2020 to 13 AUG 2026, and was the low bidder on 6 of them (12%). When it was not low, its total sat a median +19% above the low bid.
- Owner
- Ohio DOT
- Low bid volume
- $4,172,632
- Latest bid
- 13 AUG 2026
- Data through
- 12 NOV 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2020 | 14 | 1 | 7% |
| 2021 | 8 | 1 | 13% |
| 2022 | 5 | 1 | 20% |
| 2023 | 9 | 0 | 0% |
| 2024 | 5 | 2 | 40% |
| 2025 | 3 | 0 | 0% |
| 2026 | 7 | 1 | 14% |
By county
| County | Bids | Low bids | Win rate |
|---|---|---|---|
| COL | 11 | 1 | 9% |
| BEL | 7 | 1 | 14% |
| JEF | 6 | 0 | 0% |
| MAH | 6 | 2 | 33% |
| ATB | 4 | 1 | 25% |
| TRU | 3 | 0 | 0% |
| POR | 3 | 0 | 0% |
| SUM | 2 | 0 | 0% |
| GEA | 2 | 0 | 0% |
| CUY | 2 | 0 | 0% |
| STA | 1 | 1 | 100% |
| District 12 | 1 | 0 | 0% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Erosion control | 832E30000 | EACH | 51 | 51 (100%) | $1.00 | $1.00 |
| Topsoil | 659E00300 | CY | 42 | 22 (52%) | $25.50 | $45.00 |
| Commercial fertilizer | 659E20000 | TON | 36 | 20 (56%) | $500.00 | $850.00 |
| Water | 659E35000 | MGAL | 23 | 14 (61%) | $1.00 | $1.00 |
| Lime | 659E31000 | ACRE | 32 | 12 (38%) | $55.00 | $150.00 |
| Pavement removed | 202E23000 | SY | 31 | 11 (35%) | $12.00 | $17.00 |
| Seeding and mulching | 659E10000 | SY | 39 | 9 (23%) | $3.00 | $2.60 |
| Asphalt concrete for maintaining traffic | 614E13000 | CY | 24 | 9 (38%) | $196.80 | $250.00 |
| Law enforcement officer with patrol car for assistance | 614E11110 | HR | 22 | 8 (36%) | $67.50 | $80.00 |
| Soil analysis test | 659E00100 | EACH | 26 | 7 (27%) | $50.00 | $115.50 |
| Excavation | 203E10000 | CY | 45 | 6 (13%) | $35.00 | $27.00 |
| Repair seeding and mulching | 659E14000 | SY | 30 | 6 (20%) | $1.50 | $1.25 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Shelly & Sands Inc | 33 | 18 of 33 |
| Eclipse Co LLC | 32 | 12 of 32 |
| S E T Inc | 24 | 5 of 24 |
| Marucci & Gaffney Excavating Co | 23 | 17 of 23 |
| Ohio-West Virginia Excavating Co | 19 | 9 of 19 |
| Lockhart Concrete Co | 13 | 5 of 13 |
| Great Lakes Construction Co | 9 | 7 of 9 |
| Tucson Inc | 9 | 9 of 9 |
| Mike Pusateri Excavating Inc | 9 | 4 of 9 |
| Stanley Miller Construction Company | 8 | 4 of 8 |
Latest bids
| Let | Contract | County | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 13 AUG 2026 | 268017 | ATB | ATB-US 6-22.78 (CULVERT REPLACEMENT) | 1 of 3 | $343,274 | Low, 15% under the second |
| 09 APR 2026 | 260189 | ATB | ATB-/TRU Culverts FY2026 (CULVERT REPLACEMENT) | 2 of 5 | $593,000 | +9.0% |
| 29 JAN 2026 | 260054 | JEF | JEF-US 22-06.99 (SLIDE REPAIR) | 2 of 8 | $544,820 | +7.0% |
| 15 JAN 2026 | 260008 | BEL | BEL-SR 149-15.10 (SLIDE REPAIR) | 2 of 4 | $570,000 | +2.0% |
| 15 JAN 2026 | 260019 | JEF | JEF-SR 213-04.51 (SLIDE REPAIR) | 2 of 8 | $1,518,470 | +7.0% |
| 15 JAN 2026 | 264000 | COL | COL-SR 644-07.96 (MISCELLANEOUS) | 2 of 4 | $660,049 | -1.0% |
| 15 JAN 2026 | 268000 | TRU | TRU-IR 80-11.32 Truck Parking (PARKING AREAS) | 7 of 7 | $6,370,000 | +35% |
| 23 OCT 2025 | 250490 | COL | COL-SR 164-01.66 (CULVERT REPLACEMENT) | 6 of 9 | $502,700 | +5.0% |
| 23 OCT 2025 | 250499 | JEF | JEF-SR 7-30.92 (CULVERT REPLACEMENT) | 3 of 6 | $1,782,869 | +21% |
| 16 JAN 2025 | 250006 | COL | COL-SR 170-20.03 (CULVERT REPLACEMENT) | 2 of 10 | $620,795 | +3.0% |
| 31 OCT 2024 | 240486 | COL | COL-SR 172-10.80 (CULVERT REPLACEMENT) | 2 of 7 | $365,449 | +2.0% |
| 12 SEP 2024 | 240419 | MAH | MAH-IR 680-09.30 Noise Walls (NOISE WALLS) | 5 of 7 | $4,670,870 | +17% |
| 21 MAR 2024 | 240199 | MAH | MAH-/POR Culverts FY2024 (CULVERT REPLACEMENT) | 1 of 4 | $690,000 | Low, 3.0% under the second |
| 25 JAN 2024 | 240064 | POR | POR-/TRU-SR 305/VAR-00.72/VAR (CULVERT REPLACEMENT) | 4 of 4 | $2,705,880 | +25% |
| 11 JAN 2024 | 240018 | MAH | MAH-SR 11-13.30 Noise Wall (NOISE WALLS) | 1 of 5 | $1,983,589 | Low, 4.0% under the second |
| 30 NOV 2023 | 230569 | JEF | JEF-US 22-13.83/14.71 (CULVERT REPLACEMENT) | 2 of 6 | $883,769 | +4.0% |
| 09 NOV 2023 | 230545 | MAH | MAH-IR 76-03.03 Noise Wall (NOISE WALLS) | 3 of 7 | $1,269,000 | +10% |
| 28 SEP 2023 | 230472 | MAH | MAH-SR 170-04.35 (MINOR RECONSTRUCTION) | 5 of 6 | $9,130,000 | +14% |
| 25 MAY 2023 | 230329 | District 4 | D04-Culverts FY2023 (East) (CULVERT REPLACEMENT) | 3 of 5 | $1,108,795 | +2.0% |
| 25 MAY 2023 | 230345 | POR | POR-/STA Culverts FY2023 (CULVERT REPLACEMENT) | 2 of 6 | $906,449 | +18% |
| 11 MAY 2023 | 238003 | ATB | ATB-SR 531-13.50/15.85 (SLIDE REPAIR) | 3 of 7 | $5,424,000 | +9.0% |
| 27 APR 2023 | 230272 | TRU | TRU-SR 46-01.05 (MISCELLANEOUS) | 3 of 5 | $1,971,770 | +6.0% |
| 26 JAN 2023 | 230059 | POR | POR-IR 76-20.05 Slide (SLIDE REPAIR) | 3 of 5 | $2,773,300 | +13% |
| 12 JAN 2023 | 230006 | BEL | BEL-SR 9-18.70 (SLIDE REPAIR) | 5 of 6 | $363,476 | +35% |
| 15 DEC 2022 | 220654 | COL | COL-SR 14-01.42 (CULVERT REPLACEMENT) | 1 of 6 | $466,400 | Low, 3.0% under the second |
How this record was read
ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
- Every bid counted here matched its published total to within one dollar; ODOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.