ODOT contract 260019 bid tabulation
JEF-SR 213-04.51 (SLIDE REPAIR). Let by Ohio DOT on January 15, 2026, JEF. 8 bids received; low bid $1,423,293 by Marucci & Gaffney Excavating Co, -23% against the engineer's estimate of $1,854,000.
- Owner
- Ohio DOT
- Letting
- 15 JAN 2026
- Pay items
- 62
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Marucci & Gaffney Excavating Co | $1,423,293 | Low | -23% |
| 2 | Rudzik Excavating Inc | $1,518,470 | +7.0% | -18% |
| 3 | Cast & Baker Corporation | $1,534,031 | +8.0% | -17% |
| 4 | Mike Pusateri Excavating Inc | $1,566,430 | +10% | -16% |
| 5 | HK Concrete LLC | $1,621,906 | +14% | -13% |
| 6 | Shelly & Sands Inc | $1,834,428 | +29% | -1.0% |
| 7 | Eclipse Co LLC | $2,299,155 | +62% | +24% |
| 8 | S E T Inc | $2,446,803 | +72% | +32% |
Engineer's estimate: $1,854,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Marucci & Gaffney Excavating Co | 2. Rudzik Excavating Inc | 3. Cast & Baker Corporation | 4. Mike Pusateri Excavating Inc | 5. HK Concrete LLC | 6. Shelly & Sands Inc |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $125,000 | $112,995 | $70,000 | $141,762 | $33,000 | $175,600 |
| 2 | Pavement removed (202E23000) | SY | 2,286 | $8.73 | $12.00 | $20.00 | $4.90 | $6.50 | $17.00 |
| 3 | Pipe removed, 24" and under (202E35100) | FT | 53 | $35.00 | $10.00 | $20.00 | $38.50 | $36.50 | $42.00 |
| 4 | Guardrail removed (202E38000) | FT | 878 | $2.25 | $3.30 | $6.00 | $2.36 | $6.00 | $7.00 |
| 5 | Catch basin removed (202E58100) | EACH | 1 | $250.00 | $500.00 | $1,000.00 | $350.00 | $500.00 | $400.00 |
| 6 | Removal misc.: post removed (202E98100) | EACH | 2 | $50.00 | $250.00 | $18.00 | $40.00 | $150.00 | $150.00 |
| 7 | Excavation (203E10000) | CY | 37,455 | $12.99 | $13.09 | $14.00 | $11.60 | $14.50 | $15.75 |
| 8 | Excavation, as per plan (203E10001) | CY | 16,709 | $12.99 | $18.00 | $14.00 | $18.25 | $23.25 | $20.00 |
| 9 | Embankment (203E20000) | CY | 201 | $5.00 | $30.00 | $10.00 | $26.50 | $10.70 | $20.00 |
| 10 | Subgrade compaction (204E10000) | SY | 2,607 | $1.50 | $1.00 | $3.00 | $2.00 | $2.50 | $4.00 |
| 11 | Excavation of subgrade (204E13000) | CY | 302 | $15.00 | $25.00 | $15.00 | $39.00 | $31.00 | $38.00 |
| 12 | Granular material, type B, as per plan (204E30011) | CY | 302 | $65.00 | $95.33 | $122.00 | $109.40 | $87.00 | $115.00 |
| 13 | Proof rolling (204E45000) | HR | 1 | $50.00 | $400.00 | $750.00 | $375.00 | $140.00 | $280.00 |
| 14 | Guardrail, type MGS with long posts (606E15100) | FT | 833 | $29.00 | $26.86 | $27.00 | $27.62 | $27.25 | $29.00 |
| 15 | Monument assembly, type C (623E38500) | EACH | 5 | $2,000.00 | $1,865.30 | $1,800.00 | $3,175.00 | $1,500.00 | $2,000.00 |
| 16 | Monument assembly removed and reset (623E40000) | EACH | 3 | $1,000.00 | $1,660.00 | $5,500.00 | $2,875.00 | $2,000.00 | $2,100.00 |
| 17 | Tied concrete block mat with type 1 underlayment (601E21050) | SY | 726 | $65.00 | $50.00 | $100.00 | $96.00 | $87.00 | $54.00 |
| 18 | Soil analysis test (659E00100) | EACH | 2 | $50.00 | $165.00 | $150.00 | $29.50 | $30.00 | $150.00 |
| 19 | Topsoil (659E00300) | CY | 371 | $35.00 | $18.00 | $40.00 | $38.00 | $42.50 | $23.00 |
| 20 | Seeding and mulching (659E10000) | SY | 3,342 | $0.75 | $1.32 | $2.00 | $1.07 | $1.00 | $1.20 |
| 21 | Seeding and mulching, as per plan (659E10001) | SY | 11,678 | $2.20 | $1.10 | $1.10 | $1.18 | $1.10 | $1.00 |
| 22 | Repair seeding and mulching (659E14000) | SY | 167 | $0.27 | $1.00 | $1.10 | $1.18 | $1.10 | $1.00 |
| 23 | Inter-seeding (659E15000) | SY | 167 | $0.27 | $1.00 | $1.10 | $0.02 | $0.20 | $1.00 |
| 24 | Commercial fertilizer (659E20000) | TON | 2.05 | $400.00 | $1,375.00 | $1,400.00 | $295.00 | $275.00 | $1,250.00 |
| 25 | Lime (659E31000) | ACRE | 3.10 | $20.00 | $150.00 | $160.00 | $29.50 | $28.00 | $150.00 |
| 26 | Water (659E35000) | MGAL | 81 | $0.01 | $1.00 | $1.10 | $2.00 | $1.00 | $1.00 |
| 27 | Storm water pollution prevention plan (832E15000) | LS | 1 | $3,200.00 | $2,200.00 | $5,500.00 | $6,231.95 | $2,500.00 | $2,100.00 |
| 28 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $7,490.00 | $7,568.00 | $10,000 | $5,161.60 | $5,000.00 | $7,500.00 |
| 29 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $10,500 | $10,000 | $12,000 | $645.20 | $12,000 | $10,500 |
| 30 | Erosion control (832E30000) | EACH | 40,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 31 | Aggregate drains (605E31100) | FT | 490 | $23.00 | $18.00 | $12.00 | $19.95 | $19.50 | $42.00 |
| 32 | 24" conduit, type D (611E10900) | FT | 96 | $84.88 | $145.00 | $100.00 | $142.90 | $105.50 | $130.00 |
| 33 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 251 | $230.00 | $269.50 | $245.00 | $283.20 | $308.00 | $230.00 |
| 34 | Aggregate base (304E20000) | CY | 403 | $97.25 | $115.33 | $115.00 | $100.35 | $87.00 | $120.00 |
| 35 | Non-tracking tack coat (407E20000) | GAL | 328 | $3.50 | $3.85 | $3.25 | $7.10 | $3.40 | $3.50 |
| 36 | Prime coat, as per plan (408E10001) | GAL | 280 | $12.50 | $9.35 | $10.00 | $10.05 | $6.00 | $12.50 |
| 37 | Asphalt concrete surface course, type 1, (449), PG70-22M (441E70100) | CY | 76 | $230.00 | $412.50 | $310.00 | $401.20 | $560.00 | $230.00 |
| 38 | Asphalt concrete intermediate course, type 2, (449) (441E70300) | CY | 107 | $230.00 | $330.00 | $265.00 | $354.00 | $353.00 | $230.00 |
| 39 | 6" non-reinforced concrete pavement, class QC MS (452E10050) | SY | 89 | $150.00 | $215.00 | $105.00 | $175.00 | $74.25 | $135.00 |
| 40 | Compacted aggregate (617E10100) | CY | 156 | $90.00 | $104.50 | $150.00 | $172.00 | $100.00 | $88.00 |
| 41 | RPM (621E00100) | EACH | 33 | $100.00 | $110.00 | $105.00 | $141.60 | $132.00 | $100.00 |
| 42 | Raised pavement marker removed (621E54000) | EACH | 33 | $1.00 | $35.00 | $0.01 | $40.00 | $30.00 | $15.00 |
| 43 | Barrier reflector, type 2 (bidirectional) (626E00110) | EACH | 18 | $13.00 | $13.86 | $12.00 | $15.22 | $13.00 | $13.00 |
| 44 | Ground mounted support, no. 3 post (630E03100) | FT | 113.40 | $27.50 | $30.25 | $17.00 | $31.95 | $16.50 | $27.50 |
| 45 | Sign post reflector (630E08600) | EACH | 14 | $55.00 | $60.50 | $30.00 | $113.70 | $31.00 | $55.00 |
| 46 | Sign, flat sheet (630E80100) | SF | 66 | $45.00 | $49.50 | $33.00 | $37.28 | $33.00 | $45.00 |
| 47 | Removal of ground mounted sign and disposal (630E84900) | EACH | 22 | $75.00 | $50.00 | $17.00 | $19.55 | $16.50 | $75.00 |
| 48 | Removal of ground mounted post support and disposal (630E86002) | EACH | 14 | $75.00 | $50.00 | $17.00 | $75.00 | $16.50 | $75.00 |
| 49 | Edge line, 6" (646E10010) | MI | 0.31 | $8,000.00 | $8,800.00 | $14,000 | $9,440.00 | $14,300 | $8,500.00 |
| 50 | Center line (646E10200) | MI | 0.16 | $8,000.00 | $8,800.00 | $23,000 | $9,440.00 | $22,550 | $16,500 |
| 51 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 50 | $40.00 | $65.00 | $65.00 | $225.00 | $100.00 | $97.00 |
| 52 | Detour signing (614E12420) | LS | 1 | $20,000 | $4,015.00 | $4,000.00 | $13,500 | $9,350.00 | $3,650.00 |
| 53 | Asphalt concrete for maintaining traffic (614E13000) | CY | 50 | $100.00 | $193.60 | $450.00 | $225.00 | $300.00 | $425.00 |
| 54 | Work zone center line, class II, 642 paint (614E21500) | MI | 0.16 | $1,000.00 | $4,200.00 | $3,500.00 | $4,484.00 | $4,180.00 | $3,200.00 |
| 55 | Work zone center line, class III, 642 paint (614E21550) | MI | 0.16 | $3,200.00 | $3,520.00 | $3,500.00 | $4,484.00 | $4,180.00 | $3,200.00 |
| 56 | Work zone edge line, class III, 6", 642 paint (614E22360) | MI | 0.31 | $1,650.00 | $1,815.00 | $1,800.00 | $4,484.00 | $4,180.00 | $1,650.00 |
| 57 | Water (616E10000) | MGAL | 110 | $1.00 | $50.00 | $150.00 | $2.00 | $15.00 | $65.00 |
| 58 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $12,000 | $14,430 | $14,000 | $18,574 | $28,000 | $13,310 |
| 59 | Maintaining traffic (614E11000) | LS | 1 | $33,000 | $12,150 | $3,500.00 | $15,750 | $15,000 | $9,500.00 |
| 60 | Field office, type B (619E16010) | MNTH | 8 | $500.00 | $1,600.00 | $1,500.00 | $2,875.00 | $3,000.00 | $4,800.00 |
| 61 | Construction layout stakes and surveying (623E10000) | LS | 1 | $24,000 | $10,000 | $28,000 | $10,000 | $24,475 | $38,000 |
| 62 | Mobilization (624E10000) | LS | 1 | $45,000 | $41,500 | $40,000 | $34,795 | $17,000 | $90,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of January 15, 2026. Compiled by Mirage Metrics.