ODOT contract 260008 bid tabulation
BEL-SR 149-15.10 (SLIDE REPAIR). Let by Ohio DOT on January 15, 2026, BEL. 4 bids received; low bid $558,225 by Shelly & Sands Inc, +4.1% against the engineer's estimate of $536,000.
- Owner
- Ohio DOT
- Letting
- 15 JAN 2026
- Pay items
- 42
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Shelly & Sands Inc | $558,225 | Low | +4.0% |
| 2 | Rudzik Excavating Inc | $570,000 | +2.0% | +6.0% |
| 3 | Eclipse Co LLC | $600,100 | +8.0% | +12% |
| 4 | Ohio-West Virginia Excavating Co | $626,402 | +12% | +17% |
Engineer's estimate: $536,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Shelly & Sands Inc | 2. Rudzik Excavating Inc | 3. Eclipse Co LLC | 4. Ohio-West Virginia Excavating Co |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $33,925 | $26,000 | $23,545 | $10,000 |
| 2 | Pavement removed (202E23000) | SY | 327 | $20.00 | $19.00 | $24.76 | $29.17 |
| 3 | Guardrail removed (202E38000) | FT | 263 | $7.50 | $6.00 | $2.00 | $8.46 |
| 4 | Excavation (203E10000) | CY | 539 | $48.00 | $65.00 | $70.04 | $50.00 |
| 5 | Embankment (203E20000) | CY | 8 | $60.00 | $100.00 | $33.39 | $103.06 |
| 6 | Subgrade compaction (204E10000) | SY | 395 | $6.00 | $3.00 | $1.21 | $2.91 |
| 7 | Granular embankment, as per plan (204E21001) | CY | 32 | $154.00 | $128.00 | $138.91 | $205.43 |
| 8 | Geotextile fabric (204E50000) | SY | 476 | $3.00 | $3.00 | $3.53 | $7.76 |
| 9 | Guardrail, type MGS half post spacing, as per plan (606E15151) | FT | 275 | $41.40 | $49.00 | $41.40 | $51.38 |
| 10 | Rock channel protection, type A without filter (601E34000) | CY | 469 | $115.00 | $135.00 | $138.18 | $115.14 |
| 11 | Rock channel protection, type C without filter (601E34200) | CY | 62 | $105.00 | $135.00 | $112.74 | $216.26 |
| 12 | Seeding and mulching (659E10000) | SY | 696 | $4.50 | $3.00 | $4.45 | $5.58 |
| 13 | Commercial fertilizer (659E20000) | TON | 0.09 | $1,250.00 | $400.00 | $900.00 | $1,550.00 |
| 14 | Lime (659E31000) | ACRE | 0.14 | $150.00 | $5.00 | $10.00 | $200.00 |
| 15 | Water (659E35000) | MGAL | 5 | $1.00 | $0.05 | $0.50 | $1.00 |
| 16 | Erosion control (832E30000) | EACH | 5,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 17 | Pavement planing, asphalt concrete, 3" (254E01000) | SY | 345 | $25.00 | $16.50 | $25.00 | $27.21 |
| 18 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 61 | $388.00 | $545.60 | $388.00 | $337.92 |
| 19 | Aggregate base (304E20000) | CY | 86 | $120.00 | $140.00 | $133.35 | $148.81 |
| 20 | Non-tracking tack coat (407E20000) | GAL | 95 | $3.50 | $3.41 | $3.50 | $19.39 |
| 21 | Asphalt concrete surface course, type 1, (449), PG70-22M (441E70100) | CY | 25 | $450.00 | $543.40 | $450.00 | $654.79 |
| 22 | Asphalt concrete intermediate course, type 2, (449) (441E70300) | CY | 35 | $388.00 | $548.90 | $388.00 | $434.00 |
| 23 | RPM (621E00100) | EACH | 4 | $500.00 | $550.00 | $500.00 | $620.48 |
| 24 | Raised pavement marker removed (621E54000) | EACH | 4 | $70.00 | $50.00 | $68.34 | $40.60 |
| 25 | Barrier reflector, type 2, bidirectional (626E00110) | EACH | 6 | $11.50 | $13.00 | $11.50 | $14.27 |
| 26 | Edge line, 6" (646E10010) | MI | 0.10 | $22,300 | $25,735 | $22,300 | $44,275 |
| 27 | Center line (646E10200) | MI | 0.05 | $35,300 | $34,370 | $35,300 | $70,100 |
| 28 | Detour signing (614E12420) | LS | 1 | $3,200.00 | $3,190.00 | $2,900.00 | $3,600.00 |
| 29 | Asphalt concrete for maintaining traffic (614E13000) | CY | 50 | $400.00 | $100.00 | $567.75 | $586.00 |
| 30 | Water (616E10000) | MGAL | 5 | $50.00 | $1.00 | $271.84 | $10.00 |
| 31 | Portions of structure removed (202E11200) | LS | 1 | $3,500.00 | $7,500.00 | $2,836.54 | $7,960.00 |
| 32 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $19,000 | $16,000 | $82,241 | $91,180 |
| 33 | Unclassified excavation, including rock (503E21320) | LS | 1 | $8,000.00 | $6,625.00 | $4,499.66 | $10,500 |
| 34 | Dowel holes with cement grout (510E09950) | EACH | 148 | $24.00 | $40.00 | $66.21 | $50.00 |
| 35 | Class QC1 concrete, misc.: scour protection (511E53010) | CY | 53 | $740.00 | $610.00 | $807.00 | $708.36 |
| 36 | Concrete repair by epoxy injection (512E10600) | FT | 150 | $95.00 | $188.00 | $43.93 | $89.50 |
| 37 | Patching concrete structure (519E11100) | SF | 150 | $210.00 | $188.00 | $30.87 | $91.00 |
| 38 | Special - retaining wall, stacked cellular wall (530E50010) | SF | 1,581 | $87.00 | $70.00 | $46.92 | $81.50 |
| 39 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $3,250.00 | $5,700.00 | $8,070.87 | $8,200.00 |
| 40 | Maintaining traffic (614E11000) | LS | 1 | $7,220.00 | $12,420 | $4,125.53 | $7,730.00 |
| 41 | Construction layout stakes and surveying (623E10000) | LS | 1 | $11,000 | $5,000.00 | $7,321.63 | $6,500.00 |
| 42 | Mobilization (624E10000) | LS | 1 | $25,000 | $43,716 | $76,974 | $22,100 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of January 15, 2026. Compiled by Mirage Metrics.