ODOT contract 250499 bid tabulation
JEF-SR 7-30.92 (CULVERT REPLACEMENT). Let by Ohio DOT on October 23, 2025, JEF. 6 bids received; low bid $1,467,579 by Marucci & Gaffney Excavating Co, -3.4% against the engineer's estimate of $1,520,000.
- Owner
- Ohio DOT
- Letting
- 23 OCT 2025
- Pay items
- 24
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Marucci & Gaffney Excavating Co | $1,467,579 | Low | -3.0% |
| 2 | Eclipse Co LLC | $1,570,112 | +7.0% | +3.0% |
| 3 | Rudzik Excavating Inc | $1,782,869 | +21% | +17% |
| 4 | Cast & Baker Corporation | $2,039,712 | +39% | +34% |
| 5 | Ohio-West Virginia Excavating Co | $2,297,086 | +57% | +51% |
| 6 | S E T Inc | $2,490,704 | +70% | +64% |
Engineer's estimate: $1,520,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Marucci & Gaffney Excavating Co | 2. Eclipse Co LLC | 3. Rudzik Excavating Inc | 4. Cast & Baker Corporation | 5. Ohio-West Virginia Excavating Co | 6. S E T Inc |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $20,000 | $3,968.20 | $5,000.00 | $10,000 | $5,000.00 | $50,000 |
| 2 | Erosion control (832E30000) | EACH | 5,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 3 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 50 | $50.00 | $99.00 | $90.00 | $100.00 | $75.00 | $70.00 |
| 4 | Asphalt concrete for maintaining traffic (614E13000) | CY | 30 | $90.00 | $550.00 | $250.00 | $300.00 | $400.00 | $500.00 |
| 5 | Portable changeable message sign, as per plan (614E18601) | SNMT | 16 | $200.00 | $440.00 | $900.00 | $1,260.00 | $1,500.00 | $900.00 |
| 6 | Water (616E10000) | MGAL | 10 | $1.00 | $1.05 | $0.10 | $130.00 | $5.00 | $50.00 |
| 7 | Calcium chloride (616E20000) | TON | 0.50 | $10.00 | $1,130.30 | $2.00 | $700.00 | $5,500.00 | $1,200.00 |
| 8 | Special - work involving asbestos containing mater (690E98400) | LS | 1 | $500.00 | $1,100.00 | $2,500.00 | $2,000.00 | $1,500.00 | $100.00 |
| 9 | Special - solid waste (690E98800) | TON | 40 | $200.00 | $117.71 | $350.00 | $260.00 | $400.00 | $140.00 |
| 10 | Special - engineered fill, low density cellular CO (203E02000) | CY | 769 | $169.00 | $161.06 | $190.00 | $185.00 | $265.00 | $190.00 |
| 11 | Unclassified excavation (503E21100) | CY | 294 | $96.94 | $99.63 | $130.00 | $100.00 | $80.00 | $130.00 |
| 12 | Epoxy coated steel reinforcement (509E10000) | LB | 14,454 | $1.50 | $1.99 | $3.00 | $2.60 | $4.00 | $2.00 |
| 13 | Concrete reinforcement, misc.:ized deformed welded (509E40000) | LB | 112 | $20.00 | $228.11 | $100.00 | $21.00 | $50.00 | $55.00 |
| 14 | Dowel holes with nonshrink, nonmetallic grout (510E10000) | EACH | 1,420 | $35.00 | $45.65 | $40.00 | $15.00 | $28.00 | $30.50 |
| 15 | Class QC1 concrete with QC/QA, substructure, as per plan (511E50213) | CY | 205 | $1,157.47 | $447.22 | $1,480.00 | $774.00 | $1,560.00 | $1,400.00 |
| 16 | Prefabricated geocomposite drain (518E20000) | SY | 1,509 | $20.00 | $22.55 | $30.00 | $40.00 | $25.00 | $64.00 |
| 17 | 4" perforated corrugated plastic pipe, as per plan (518E39801) | FT | 610 | $5.00 | $58.20 | $48.00 | $40.00 | $68.00 | $80.00 |
| 18 | 4" non-perforated corrugated plastic pipe, including specials (518E39900) | FT | 20 | $5.00 | $153.16 | $170.00 | $80.00 | $90.00 | $46.00 |
| 19 | Structural plate corrugated metal structure, as per plan (522E12201) | FT | 305 | $2,727.77 | $3,226.90 | $3,285.00 | $4,415.00 | $4,350.00 | $4,400.00 |
| 21 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $13,000 | $16,510 | $17,500 | $12,000 | $35,000 | $50,000 |
| 22 | Maintaining traffic, as per plan (614E11001) | LS | 1 | $15,000 | $13,099 | $4,500.00 | $5,000.00 | $10,000 | $5,000.00 |
| 23 | Field office, type B (619E16010) | MNTH | 8 | $500.00 | $840.00 | $2,000.00 | $2,500.00 | $3,000.00 | $2,750.00 |
| 24 | Construction layout stakes and surveying (623E10000) | LS | 1 | $5,000.00 | $5,921.54 | $2,500.00 | $15,000 | $15,000 | $10,000 |
| 25 | Mobilization, as per plan (624E10001) | LS | 1 | $54,000 | $63,260 | $10,500 | $100,000 | $85,000 | $271,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of October 23, 2025. Compiled by Mirage Metrics.