ODOT contract 250490 bid tabulation
COL-SR 164-01.66 (CULVERT REPLACEMENT). Let by Ohio DOT on October 23, 2025, COL. 9 bids received; low bid $478,188 by S.T.A.R.T., LLC, -4.4% against the engineer's estimate of $500,000.
- Owner
- Ohio DOT
- Letting
- 23 OCT 2025
- Pay items
- 49
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | S.T.A.R.T., LLC | $478,188 | Low | -4.0% |
| 2 | Stanley Miller Construction Company | $484,876 | +1.0% | -3.0% |
| 3 | Eclipse Co LLC | $486,285 | +2.0% | -3.0% |
| 4 | A P O'Horo Company | $491,000 | +3.0% | -2.0% |
| 5 | Marucci & Gaffney Excavating Co | $498,161 | +4.0% | 0.0% |
| 6 | Rudzik Excavating Inc | $502,700 | +5.0% | +1.0% |
| 7 | S E T Inc | $519,280 | +9.0% | +4.0% |
| 8 | Ohio-West Virginia Excavating Co | $718,150 | +50% | +44% |
| 9 | Craig Edward Susany Inc | $799,918 | +67% | +60% |
Engineer's estimate: $500,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. S.T.A.R.T., LLC | 2. Stanley Miller Construction Company | 3. Eclipse Co LLC | 4. A P O'Horo Company | 5. Marucci & Gaffney Excavating Co | 6. Rudzik Excavating Inc |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $10,014 | $21,250 | $16,995 | $25,000 | $15,000 | $47,325 |
| 2 | Pavement removed (202E23000) | SY | 402 | $25.16 | $12.00 | $18.31 | $25.00 | $30.00 | $13.50 |
| 3 | Pipe removed, over 24" diameter (202E35200) | FT | 145 | $33.94 | $25.00 | $119.49 | $75.00 | $290.00 | $107.00 |
| 4 | Guardrail removed for storage, as per plan (202E38101) | FT | 300 | $3.40 | $8.00 | $3.40 | $3.40 | $15.00 | $7.00 |
| 5 | Excavation (203E10000) | CY | 469 | $45.01 | $56.00 | $34.55 | $25.00 | $30.00 | $60.00 |
| 6 | Embankment (203E20000) | CY | 22 | $84.84 | $95.00 | $45.29 | $50.00 | $20.00 | $75.00 |
| 7 | Subgrade compaction (204E10000) | SY | 455 | $7.92 | $1.00 | $1.68 | $3.00 | $5.00 | $5.00 |
| 8 | Guardrail, type MGS with long posts (606E15100) | FT | 187.50 | $24.80 | $35.00 | $24.80 | $24.80 | $24.80 | $32.30 |
| 9 | Anchor assembly, MGS type E, (MASH 2016) (606E26150) | EACH | 2 | $2,850.00 | $3,500.00 | $2,850.00 | $2,850.00 | $2,850.00 | $3,135.00 |
| 10 | Rock channel protection, type A with aggregate filter (601E32010) | CY | 309 | $124.48 | $149.00 | $164.80 | $140.00 | $175.00 | $173.00 |
| 11 | Rock channel protection, type C without filter (601E34200) | CY | 100 | $142.00 | $149.00 | $141.46 | $135.00 | $100.00 | $140.00 |
| 12 | Rock channel protection, with grout, type A (601E34400) | CY | 97 | $265.20 | $240.00 | $200.69 | $265.00 | $250.00 | $250.00 |
| 13 | Soil analysis test (659E00100) | EACH | 2 | $84.14 | $150.00 | $150.00 | $25.00 | $10.00 | $50.00 |
| 14 | Topsoil (659E00300) | CY | 64 | $92.21 | $50.00 | $82.75 | $35.00 | $30.00 | $35.00 |
| 15 | Seeding and mulching (659E10000) | SY | 579 | $3.72 | $4.40 | $5.20 | $2.50 | $6.00 | $5.00 |
| 16 | Repair seeding and mulching (659E14000) | SY | 29 | $11.55 | $1.00 | $5.20 | $2.50 | $0.27 | $5.00 |
| 17 | Commercial fertilizer (659E20000) | TON | 0.08 | $2,374.00 | $800.00 | $1,250.00 | $500.00 | $400.00 | $400.00 |
| 18 | Lime (659E31000) | ACRE | 0.12 | $1,435.00 | $150.00 | $150.00 | $500.00 | $10.00 | $50.00 |
| 19 | Water (659E35000) | MGAL | 5 | $2.00 | $1.00 | $1.00 | $1.00 | $0.01 | $0.01 |
| 20 | Erosion control (832E30000) | EACH | 5,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 21 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $11,005 | $21,000 | $10,555 | $10,000 | $7,500.00 | $6,500.00 |
| 22 | Unclassified excavation, including rock (503E21104) | CY | 325 | $65.58 | $85.00 | $52.86 | $20.00 | $100.00 | $20.00 |
| 23 | Epoxy coated steel reinforcement (509E10000) | LB | 4,354 | $3.75 | $2.50 | $3.56 | $1.85 | $1.90 | $2.00 |
| 24 | Class QC1 concrete, retaining/wingwall not including footing (511E46010) | CY | 14 | $1,690.00 | $1,099.00 | $2,089.92 | $1,700.00 | $1,200.00 | $1,300.00 |
| 25 | Class QC1 concrete, footing (511E46510) | CY | 28 | $948.00 | $770.00 | $896.57 | $700.00 | $900.00 | $1,650.00 |
| 26 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 49 | $50.35 | $77.00 | $12.46 | $60.00 | $40.00 | $65.00 |
| 27 | Porous backfill with geotextile fabric (518E21200) | CY | 15 | $198.90 | $185.00 | $133.75 | $80.00 | $100.00 | $196.00 |
| 28 | Concrete masonry (602E20000) | CY | 0.33 | $5,412.12 | $3,125.00 | $5,378.36 | $2,000.00 | $3,000.00 | $8,250.00 |
| 29 | 18" conduit, type C (611E07600) | FT | 11 | $191.45 | $102.00 | $84.81 | $150.00 | $454.00 | $225.00 |
| 30 | 60" conduit, type A (706.02, 707.02 (0.079) alumin (611E23600) | FT | 74 | $568.71 | $520.00 | $474.65 | $250.00 | $438.78 | $540.00 |
| 31 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 69 | $500.00 | $467.00 | $315.00 | $349.00 | $420.00 | $462.00 |
| 32 | Aggregate base (304E20000) | CY | 111 | $129.29 | $135.00 | $113.92 | $105.00 | $120.00 | $140.00 |
| 33 | Tack coat (407E10000) | GAL | 44 | $4.00 | $5.00 | $3.05 | $3.10 | $4.00 | $4.50 |
| 34 | Prime coat, as per plan (408E10001) | GAL | 71 | $20.00 | $22.00 | $20.00 | $15.00 | $20.00 | $22.00 |
| 35 | Asphalt concrete surface course, type 1, (449), PG70-22M (441E70100) | CY | 14 | $500.00 | $806.00 | $430.00 | $1,007.00 | $725.00 | $797.50 |
| 36 | Asphalt concrete intermediate course, type 2, (449) (441E70300) | CY | 20 | $500.00 | $750.00 | $333.00 | $951.00 | $675.00 | $742.50 |
| 37 | Barrier reflector, type 2, bidirectional (626E00110) | EACH | 8 | $12.50 | $15.00 | $12.50 | $12.50 | $12.50 | $14.00 |
| 38 | Edge line, 6" (646E10010) | MI | 0.06 | $38,500 | $44,000 | $49,090 | $38,500 | $49,090 | $38,500 |
| 39 | Center line (646E10200) | MI | 0.03 | $60,500 | $68,000 | $65,600 | $60,500 | $65,600 | $77,000 |
| 40 | Detour signing (614E12420) | LS | 1 | $7,560.00 | $8,400.00 | $8,887.06 | $15,000 | $20,000 | $5,800.00 |
| 41 | Asphalt concrete for maintaining traffic (614E13000) | CY | 110 | $100.45 | $180.00 | $465.00 | $631.00 | $180.00 | $50.00 |
| 42 | Work zone center line, class III, 642 paint (614E21550) | MI | 0.03 | $34,730 | $34,800 | $26,255 | $24,950 | $1,000.00 | $27,500 |
| 43 | Work zone edge line, class III, 6", 642 paint (614E22360) | MI | 0.06 | $17,535 | $17,600 | $21,585 | $12,750 | $1,000.00 | $14,000 |
| 44 | Water (616E10000) | MGAL | 10 | $1.00 | $1.00 | $131.69 | $1.00 | $0.01 | $0.10 |
| 45 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $7,200.00 | $8,000.00 | $7,003.54 | $10,016 | $5,000.00 | $5,300.00 |
| 46 | Maintaining traffic (614E11000) | LS | 1 | $20,622 | $9,500.00 | $8,678.20 | $25,000 | $15,000 | $13,960 |
| 47 | Field office, type B (619E16010) | MNTH | 6 | $3,200.00 | $1,000.00 | $306.37 | $1,000.00 | $500.00 | $1,400.00 |
| 48 | Construction layout stakes and surveying (623E10000) | LS | 1 | $8,000.00 | $15,000 | $7,370.30 | $10,000 | $6,000.00 | $4,500.00 |
| 49 | Mobilization (624E10000) | LS | 1 | $25,185 | $22,500 | $36,851 | $24,000 | $25,000 | $23,375 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of October 23, 2025. Compiled by Mirage Metrics.