ODOT letting results, September 12, 2024
13 contracts let by Ohio DOT on September 12, 2024, $21,459,152 in low bids, a median of 3 bidders per contract. On the 13 with an engineer's estimate, the low bid came in under it 9 times; median low bid -11% against the estimate.
- Owner
- Ohio DOT
- Contracts
- 13
- Low bids, total
- $21,459,152
- Data through
- 12 NOV 2026
Contracts let that day
| Contract | Project | County | Bids | Low bidder | Low bid | Second bid | Gap | Against estimate | Source |
|---|---|---|---|---|---|---|---|---|---|
| 240419 | MAH-IR 680-09.30 Noise Walls (NOISE WALLS) | MAH | 7 | A P O'Horo Company | $3,984,000 | $4,049,816 | +2.0% | -39% | ODOT |
| 240421 | PAU-/DEF-SR 49-06.94/00.00 (TWO LANE RESURFACING) | PAU | 2 | Shelly Company | $3,013,200 | $3,094,396 | +3.0% | +2.0% | ODOT |
| 240415 | BEL-US 40/VAR-27.47/VAR (TWO LANE RESURFACING) | BEL | 3 | NLS Paving, Inc | $2,633,945 | $2,781,983 | +6.0% | +28% | ODOT |
| 240425 | WOO-SR 582-05.43/10.24 Resurf (TWO LANE RESURFACING) | WOO | 3 | Shelly Company | $2,498,297 | $2,596,644 | +4.0% | -14% | ODOT |
| 240418 | LAW-SR 141-08.40 (TWO LANE RESURFACING) | LAW | 1 | Shelly Company | $2,283,126 | +7.0% | ODOT | ||
| 240429 | MEG-US 33-13.96 Tree Cutting (LANDSCAPING) | MEG | 4 | Complete Clearing Inc | $1,692,209 | $1,869,114 | +10% | -17% | ODOT |
| 240420 | MEG-Middleport Streetscape Ph 1 (SIDEWALK) | MEG | 7 | Axis Civil Construction LLC | $1,690,309 | $1,734,387 | +3.0% | -6.0% | ODOT |
| 240414 | ALL-SR 65-00.00/03.94 (TWO LANE RESURFACING) | ALL | 2 | Shelly Company | $1,096,533 | $1,163,700 | +6.0% | -11% | ODOT |
| 240424 | TUS-SR 516-03.70 (TWO LANE RESURFACING) | TUS | 6 | Karvo Companies Inc | $1,068,000 | $1,076,460 | +1.0% | -11% | ODOT |
| 240417 | HAN-SR 12-17.45 (MICROSURFACING) | HAN | 2 | Strawser Construction Inc | $840,550 | $1,071,718 | +28% | +2.0% | ODOT |
| 240426 | CLE-SR 232-01.80 (CULVERT REPLACEMENT) | CLE | 5 | Axis Civil Construction LLC | $340,657 | $355,906 | +4.0% | -28% | ODOT |
| 240427 | D03-PR FY2025 (B) (PRUNING/OR TREE/BRUSH REMOVAL) | District 3 | 6 | BCC Ohio Inc | $259,325 | $279,830 | +8.0% | -15% | ODOT |
| 240422 | PIC-Ashville-Ped Improve (MISCELLANEOUS) | PIC | 3 | Miller Cable Company | $59,000 | $59,531 | +1.0% | -30% | ODOT |
Gap is the second bid over the low bid. Where a contract shows fewer bids than ODOT received, the others did not match their published totals and are left out.
Your own bid history, read the same way