ODOT letting results, September 26, 2024
26 contracts let by Ohio DOT on September 26, 2024, $59,098,488 in low bids, a median of 3 bidders per contract. On the 26 with an engineer's estimate, the low bid came in under it 21 times; median low bid -11% against the estimate.
- Owner
- Ohio DOT
- Contracts
- 26
- Low bids, total
- $59,098,488
- Data through
- 12 NOV 2026
Contracts let that day
| Contract | Project | County | Bids | Low bidder | Low bid | Second bid | Gap | Against estimate | Source |
|---|---|---|---|---|---|---|---|---|---|
| 240416 | CUY-IR 77-04.79/Wallings Road (INTERCHANGE) | CUY | 5 | J D Williamson Construction Co Inc | $8,035,650 | $8,086,632 | +1.0% | +8.0% | ODOT |
| 240428 | FRA-SR 161-15.80 Noise Abatement (NOISE WALLS) | FRA | 6 | Shelly & Sands Inc | $7,940,506 | $8,562,587 | +8.0% | -8.0% | ODOT |
| 240423 | SUM-IR 77-09.75 (NOISE WALLS) | SUM | 5 | Kenmore Construction Co Inc | $6,826,199 | $7,191,503 | +5.0% | -25% | ODOT |
| 240440 | HAM-IR 275-13.90 (FOUR LANE RESURFACING) | HAM | 2 | Barrett Paving Materials Inc | $3,875,540 | $4,016,818 | +4.0% | -3.0% | ODOT |
| 240448 | PRE-SR 726-00.00 (TWO LANE RESURFACING) | PRE | 2 | Barrett Paving Materials Inc | $3,597,411 | $3,971,598 | +10% | -7.0% | ODOT |
| 240438 | GRE-IR 675-14.91 (FOUR LANE RESURFACING) | GRE | 2 | John R Jurgensen Company | $3,504,216 | $3,558,416 | +2.0% | 0.0% | ODOT |
| 240432 | COL-SR 46/VAR-00.00/VAR (TWO LANE RESURFACING) | COL | 3 | Shelly & Sands Inc | $3,324,699 | $3,334,428 | 0.0% | -7.0% | ODOT |
| 240430 | ADA-SR 125/SR 247-09.22/00.35 (TWO LANE RESURFACING) | ADA | 4 | Brown County Asphalt Inc | $2,514,456 | $2,825,113 | +12% | -25% | ODOT |
| 240439 | GRE-SR 72-07.71 (BRIDGE REPLACEMENT (1 BRIDGE)) | GRE | 4 | Eagle Bridge Co | $2,474,161 | $2,816,532 | +14% | +16% | ODOT |
| 240447 | NOB-SR 313-00.00/SR 761-00.00 (TWO LANE RESURFACING) | NOB | 2 | Shelly & Sands Inc | $2,442,542 | $3,026,070 | +24% | -12% | ODOT |
| 240449 | UNI-SR 38-00.30 (TWO LANE RESURFACING) | UNI | 1 | Shelly Company | $2,152,758 | -7.0% | ODOT | ||
| 240441 | HAN-SR 568-02.88/03.63 (BRIDGE REPAIR) | HAN | 3 | BCC Ohio Inc | $1,958,359 | $2,033,293 | +4.0% | -11% | ODOT |
| 240456 | LUC-/OTT Sign FY2025 (SIGNING) | LUC | 1 | Lake Erie Construction Company | $1,842,420 | -14% | ODOT | ||
| 240442 | HAR-SR 81-06.36 (BRIDGE REPLACEMENT (1 BRIDGE)) | HAR | 5 | R G Zachrich Construction Inc | $1,188,994 | $1,219,790 | +3.0% | -15% | ODOT |
| 240443 | HAS-SR 151-14.00 (BRIDGE REPAIR) | HAS | 4 | BCC Ohio Inc | $1,039,783 | $1,097,906 | +6.0% | +28% | ODOT |
| 240435 | D07-BH-FY25 (C) (BRIDGE REPAIR) | District 7 | 4 | BCC Ohio Inc | $1,013,427 | $1,127,134 | +11% | -20% | ODOT |
| 240446 | MRW-SR 314-04.02 (TWO LANE RESURFACING) | MRW | 2 | Kokosing Construction Company Inc | $970,489 | $1,184,110 | +22% | -28% | ODOT |
| 240453 | D03-GR FY2025 (GUARDRAIL REBUILDING) | District 3 | 2 | Cuyahoga Fence LLC | $824,421 | $862,375 | +5.0% | -10% | ODOT |
| 240455 | D11-PM-FY2025(A) (PAVEMENT MARKING) | District 11 | 2 | The Aero-Mark Company LLC | $739,000 | $1,067,749 | +44% | +5.0% | ODOT |
| 240431 | CLE-Culverts FY25 (CULVERT REPLACEMENT) | CLE | 6 | BCC Ohio Inc | $655,913 | $816,793 | +25% | -12% | ODOT |
| 240433 | COS-TR 252-00.00 (BRIDGE REPLACEMENT (1 BRIDGE)) | COS | 11 | MC Connell Contracting Inc | $552,633 | $663,865 | +20% | -35% | ODOT |
| 240451 | BEL-SR 379-02.23 (SLIDE REPAIR) | BEL | 5 | Alan Stone Co Inc | $479,955 | $480,060 | 0.0% | -15% | ODOT |
| 240452 | D02-RPM FY2025 (RAISED PAVEMENT MARKERS) | District 2 | 2 | A & A Safety Inc | $453,086 | $471,014 | +4.0% | -3.0% | ODOT |
| 240437 | ERI-SR 2-21.23 (CULVERT REPLACEMENT) | ERI | 3 | Great Lakes Demolition Company | $412,364 | $541,983 | +31% | -31% | ODOT |
| 240445 | MOT-IR 70/IR 75-11.30/03.73L (BRIDGE REPAIR) | MOT | 2 | Enneking Pressure Cleaning Inc | $183,991 | $297,018 | +61% | -23% | ODOT |
| 240454 | D03-LG FY2025(A) (LIGHTING) | District 3 | 6 | Cornerstone Electric Inc | $95,518 | $112,847 | +18% | -27% | ODOT |
Gap is the second bid over the low bid. Where a contract shows fewer bids than ODOT received, the others did not match their published totals and are left out.