ODOT contract 250006 bid tabulation
COL-SR 170-20.03 (CULVERT REPLACEMENT). Let by Ohio DOT on January 16, 2025, COL. 10 bids received; low bid $599,986 by Bog Construction Inc, -21% against the engineer's estimate of $760,000.
- Owner
- Ohio DOT
- Letting
- 16 JAN 2025
- Pay items
- 59
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Bog Construction Inc | $599,986 | Low | -21% |
| 2 | Rudzik Excavating Inc | $620,795 | +3.0% | -18% |
| 3 | Shelly & Sands Inc | $649,166 | +8.0% | -15% |
| 4 | Marucci & Gaffney Excavating Co | $727,607 | +21% | -4.0% |
| 5 | Eclipse Co LLC | $750,167 | +25% | -1.0% |
| 6 | S E T Inc | $779,420 | +30% | +3.0% |
| 7 | Stanley Miller Construction Company | $783,669 | +31% | +3.0% |
| 8 | Craig Edward Susany Inc | $847,569 | +41% | +12% |
| 9 | J S Bova Excavating LLC | $967,809 | +61% | +27% |
| 10 | S.T.A.R.T., LLC | $1,047,830 | +75% | +38% |
Engineer's estimate: $760,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Bog Construction Inc | 2. Rudzik Excavating Inc | 3. Shelly & Sands Inc | 4. Marucci & Gaffney Excavating Co | 5. Eclipse Co LLC | 6. S E T Inc |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $3,500.00 | $23,200 | $10,000 | $7,500.00 | $12,000 | $15,000 |
| 2 | Pavement removed (202E23000) | SY | 423 | $20.00 | $8.00 | $16.00 | $15.00 | $21.00 | $25.00 |
| 3 | Pipe removed, 24" and under (202E35100) | FT | 32 | $40.00 | $15.00 | $30.00 | $50.00 | $28.00 | $18.00 |
| 4 | Guardrail removed (202E38000) | FT | 411 | $3.00 | $4.00 | $2.00 | $2.00 | $2.00 | $3.00 |
| 5 | Fence removed (202E75000) | FT | 20 | $20.00 | $10.00 | $25.00 | $25.00 | $26.00 | $10.00 |
| 6 | Removal misc.: oepa notification of demolition (202E98100) | EACH | 1 | $500.00 | $750.00 | $536.00 | $100.00 | $526.00 | $2,000.00 |
| 7 | Excavation (203E10000) | CY | 352 | $25.00 | $25.00 | $10.00 | $50.00 | $47.00 | $25.00 |
| 8 | Embankment (203E20000) | CY | 462 | $20.00 | $25.00 | $6.00 | $49.00 | $31.00 | $20.00 |
| 9 | Subgrade compaction (204E10000) | SY | 969 | $3.00 | $2.00 | $2.00 | $2.00 | $1.00 | $3.00 |
| 10 | Guardrail, type MGS (606E15050) | FT | 175 | $28.00 | $33.50 | $28.00 | $26.40 | $28.00 | $27.00 |
| 11 | Anchor assembly, MGS type E (MASH 2016 or NCHRP 35 (606E26150) | EACH | 1 | $4,200.00 | $3,586.00 | $3,494.00 | $3,260.00 | $3,428.00 | $3,300.00 |
| 12 | Rock channel protection, type A with aggregate filter (601E32010) | CY | 86 | $120.00 | $154.00 | $151.00 | $170.00 | $243.00 | $150.00 |
| 13 | Rock channel protection, type B with aggregate filter (601E32110) | CY | 40 | $120.00 | $155.00 | $192.00 | $130.00 | $158.00 | $150.00 |
| 14 | Soil analysis test (659E00100) | EACH | 2 | $50.00 | $5.00 | $161.00 | $10.00 | $158.00 | $150.00 |
| 15 | Topsoil (659E00300) | CY | 169 | $30.00 | $18.00 | $46.00 | $50.00 | $65.00 | $75.00 |
| 16 | Seeding and mulching (659E10000) | SY | 1,526 | $4.00 | $2.50 | $2.50 | $4.00 | $2.00 | $3.00 |
| 17 | Repair seeding and mulching (659E14000) | SY | 76 | $1.00 | $0.01 | $2.50 | $0.25 | $2.00 | $1.00 |
| 18 | Commercial fertilizer (659E20000) | TON | 0.21 | $1,000.00 | $400.00 | $1,340.00 | $500.00 | $1,314.00 | $500.00 |
| 19 | Lime (659E31000) | ACRE | 0.32 | $100.00 | $1.00 | $161.00 | $40.00 | $158.00 | $40.00 |
| 20 | Water (659E35000) | MGAL | 10 | $1.00 | $0.01 | $1.00 | $0.01 | $1.00 | $2.00 |
| 21 | Erosion control (832E30000) | EACH | 7,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 22 | Seeding and erosion control with turf reinforcing mat, type 1 (836E10000) | SY | 179 | $10.00 | $12.00 | $6.40 | $10.00 | $6.00 | $9.00 |
| 23 | Aggregate drains (605E31100) | FT | 206 | $15.00 | $21.00 | $16.00 | $34.00 | $20.00 | $15.00 |
| 24 | 6" conduit, type F (611E01500) | FT | 20 | $25.00 | $22.00 | $46.00 | $4.00 | $36.00 | $20.00 |
| 25 | 24" conduit, type D (611E10900) | FT | 40 | $65.00 | $133.00 | $88.00 | $120.00 | $104.00 | $100.00 |
| 26 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 73 | $351.00 | $292.00 | $345.00 | $265.00 | $345.00 | $275.00 |
| 27 | Aggregate base (304E20000) | CY | 176 | $95.00 | $68.00 | $100.00 | $105.00 | $118.00 | $75.00 |
| 28 | Tack coat (407E10000) | GAL | 48 | $12.00 | $4.50 | $3.05 | $4.00 | $3.00 | $5.00 |
| 29 | Prime coat, as per plan (408E10001) | GAL | 156 | $12.00 | $7.00 | $8.00 | $6.00 | $8.00 | $7.00 |
| 30 | Asphalt concrete surface course, type 1, (449), PG70-22M (441E70100) | CY | 15 | $596.00 | $582.00 | $680.00 | $529.00 | $680.00 | $545.00 |
| 31 | Asphalt concrete intermediate course, type 2, (449) (441E70300) | CY | 21 | $526.00 | $374.00 | $500.00 | $340.00 | $500.00 | $350.00 |
| 32 | RPM (621E00100) | EACH | 4 | $1,000.00 | $965.00 | $938.00 | $875.00 | $1,053.00 | $800.00 |
| 33 | Raised pavement marker removed (621E54000) | EACH | 4 | $100.00 | $20.00 | $23.00 | $50.00 | $11.00 | $25.00 |
| 34 | Barrier reflector, type 2, bidirectional (626E00110) | EACH | 7 | $20.00 | $14.00 | $15.00 | $14.00 | $15.00 | $15.00 |
| 35 | Edge line, 6" (646E10010) | MI | 0.08 | $50,000 | $44,000 | $42,000 | $40,000 | $40,000 | $45,000 |
| 36 | Center line (646E10200) | MI | 0.03 | $45,000 | $44,000 | $42,000 | $40,000 | $40,000 | $45,000 |
| 37 | Detour signing (614E12420) | LS | 1 | $6,500.00 | $7,060.00 | $6,400.00 | $6,000.00 | $6,269.00 | $6,000.00 |
| 38 | Asphalt concrete for maintaining traffic (614E13000) | CY | 75 | $120.00 | $0.10 | $500.00 | $50.00 | $415.00 | $300.00 |
| 39 | Work zone center line, class III, 642 paint (614E21550) | MI | 0.06 | $5,000.00 | $2,170.00 | $2,112.00 | $2,000.00 | $2,073.00 | $2,000.00 |
| 40 | Work zone edge line, class III, 6", 642 paint (614E22360) | MI | 0.16 | $1,000.00 | $2,170.00 | $2,112.00 | $2,000.00 | $2,073.00 | $2,000.00 |
| 41 | Water (616E10000) | MGAL | 10 | $1.00 | $0.10 | $55.00 | $1.00 | $27.00 | $100.00 |
| 42 | Structure removed (202E11000) | LS | 1 | $60,000 | $6,800.00 | $10,000 | $60,000 | $12,695 | $20,000 |
| 43 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $5,000.00 | $9,000.00 | $13,000 | $49,000 | $23,000 | $25,000 |
| 44 | Unclassified excavation (503E21100) | CY | 630 | $28.00 | $26.00 | $22.00 | $25.00 | $36.00 | $65.00 |
| 45 | Epoxy coated steel reinforcement (509E10000) | LB | 10,547 | $1.75 | $0.25 | $1.50 | $1.50 | $2.20 | $2.00 |
| 46 | Class QC1 concrete, retaining/wingwall not including footing (511E46010) | CY | 27 | $800.00 | $1,762.00 | $1,600.00 | $1,875.00 | $1,810.00 | $2,000.00 |
| 47 | Class QC1 concrete, footing (511E46510) | CY | 74 | $450.00 | $700.00 | $520.00 | $642.00 | $528.00 | $600.00 |
| 48 | Class QC1 concrete, headwall (511E46610) | CY | 2 | $1,000.00 | $1,110.00 | $2,200.00 | $1,750.00 | $1,919.00 | $2,500.00 |
| 49 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 79 | $32.00 | $40.00 | $37.50 | $40.00 | $28.00 | $50.00 |
| 50 | Type 2 waterproofing (512E33000) | SY | 366 | $25.00 | $25.00 | $37.50 | $40.00 | $23.82 | $25.00 |
| 51 | 1" preformed expansion joint filler (516E13600) | SF | 58 | $15.00 | $5.00 | $2.00 | $15.00 | $5.00 | $15.00 |
| 52 | Porous backfill with geotextile fabric (518E21200) | CY | 27 | $90.00 | $148.00 | $245.00 | $175.00 | $130.00 | $125.00 |
| 53 | 12' X 8' conduit, type A, 706.05, as per plan (611E96001) | FT | 93 | $1,366.00 | $1,970.00 | $1,410.00 | $1,225.00 | $1,549.00 | $1,800.00 |
| 54 | Low strength mortar backfill (613E41200) | CY | 482 | $127.00 | $147.00 | $156.00 | $165.00 | $216.00 | $140.00 |
| 55 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $15,000 | $6,300.00 | $3,800.00 | $10,000 | $13,000 | $9,000.00 |
| 56 | Maintaining traffic (614E11000) | LS | 1 | $4,000.00 | $3,400.00 | $12,000 | $30,000 | $28,308 | $20,000 |
| 57 | Field office, type B (619E16010) | MNTH | 4 | $500.00 | $1,600.00 | $4,200.00 | $1,000.00 | $683.00 | $1,500.00 |
| 58 | Construction layout stakes and surveying (623E10000) | LS | 1 | $15,000 | $3,000.00 | $12,500 | $10,000 | $8,000.00 | $20,000 |
| 59 | Mobilization (624E10000) | LS | 1 | $25,000 | $20,000 | $32,000 | $20,000 | $24,000 | $62,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of January 16, 2025. Compiled by Mirage Metrics.