ODOT contract 260183 bid tabulation
STA-Sippo Valley Trail Bridge 8 (BRIDGE REPLACEMENT (1 BRIDGE)). Let by Ohio DOT on April 9, 2026, STA. 5 bids received; low bid $744,413 by Matt Winters Excavation LLC, -12% against the engineer's estimate of $850,000.
- Owner
- Ohio DOT
- Letting
- 09 APR 2026
- Pay items
- 39
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Matt Winters Excavation LLC | $744,413 | Low | -12% |
| 2 | Stanley Miller Construction Company | $796,619 | +7.0% | -6.0% |
| 3 | J D Williamson Construction Co Inc | $798,548 | +7.0% | -6.0% |
| 4 | Black Horse Bridge Construction Inc | $864,336 | +16% | +2.0% |
| 5 | S E T Inc | $1,282,374 | +72% | +51% |
Engineer's estimate: $850,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Matt Winters Excavation LLC | 2. Stanley Miller Construction Company | 3. J D Williamson Construction Co Inc | 4. Black Horse Bridge Construction Inc | 5. S E T Inc |
|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $9,000.00 | $16,000 | $12,000 | $24,750 | $100,000 |
| 2 | Pavement removed (202E23000) | SY | 117 | $15.00 | $8.00 | $5.00 | $7.00 | $27.00 |
| 3 | Excavation (203E10000) | CY | 29 | $27.00 | $67.00 | $20.00 | $48.00 | $100.00 |
| 4 | Embankment (203E20000) | CY | 6 | $95.00 | $80.00 | $20.00 | $80.00 | $115.00 |
| 5 | Fence, misc.:wood fence (607E98000) | FT | 117 | $85.00 | $86.00 | $90.00 | $120.00 | $76.00 |
| 6 | Special - as-built construction plans (690E91000) | LS | 1 | $1,500.00 | $2,500.00 | $1,500.00 | $3,000.00 | $2,200.00 |
| 7 | Special - survey control verification (690E98400) | LS | 1 | $1,500.00 | $1,422.00 | $1,500.00 | $3,000.00 | $2,200.00 |
| 8 | Topsoil (659E00300) | CY | 9 | $90.00 | $56.00 | $115.00 | $190.00 | $185.00 |
| 9 | Seeding and mulching (659E10000) | SY | 76 | $30.00 | $44.00 | $5.00 | $10.00 | $10.00 |
| 10 | Commercial fertilizer (659E20000) | TON | 0.02 | $850.00 | $750.00 | $475.00 | $1,000.00 | $1,000.00 |
| 11 | Lime (659E31000) | ACRE | 0.02 | $50.00 | $300.00 | $31.00 | $500.00 | $600.00 |
| 12 | Water (659E35000) | MGAL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $20.00 |
| 13 | Erosion control (832E30000) | EACH | 6,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 14 | Subgrade compaction (204E10000) | SY | 124 | $7.00 | $2.00 | $10.00 | $11.00 | $4.00 |
| 15 | Aggregate base (304E20000) | CY | 19 | $110.00 | $226.00 | $160.00 | $200.00 | $185.00 |
| 16 | Tack coat (407E10000) | GAL | 7 | $6.00 | $4.00 | $12.00 | $12.00 | $3.50 |
| 17 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 9 | $1,150.00 | $1,440.00 | $800.00 | $800.00 | $1,200.00 |
| 18 | Structure removed, over 20 foot span, as per plan (202E11003) | LS | 1 | $111,900 | $10,611 | $158,000 | $65,120 | $55,000 |
| 19 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $24,000 | $34,389 | $60,000 | $500.00 | $165,000 |
| 20 | Unclassified excavation (503E21100) | CY | 240 | $40.00 | $97.00 | $100.00 | $115.00 | $110.00 |
| 21 | Pile driving equipment mobilization (505E11100) | LS | 1 | $40,500 | $43,945 | $20,000 | $83,000 | $35,000 |
| 22 | 12" cast-in-place reinforced concrete piles, driven (507E00500) | FT | 870 | $6.00 | $19.00 | $45.00 | $11.00 | $24.00 |
| 23 | 12" cast-in-place reinforced concrete piles, furnished (507E00550) | FT | 930 | $85.00 | $60.00 | $50.00 | $70.00 | $78.00 |
| 24 | Epoxy coated steel reinforcement (509E10000) | LB | 4,900 | $3.00 | $1.90 | $2.00 | $2.50 | $2.05 |
| 25 | Class QC1 concrete, abutment including footing (511E43510) | CY | 43 | $775.00 | $723.00 | $1,000.00 | $1,000.00 | $1,000.00 |
| 26 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 28 | $75.00 | $95.00 | $39.00 | $55.00 | $40.00 |
| 27 | Structural steel, misc.: prefabricated bridge (513E95020) | LS | 1 | $311,945 | $252,540 | $225,000 | $375,000 | $540,000 |
| 28 | Structural steel expansion joint, as per plan (516E12201) | FT | 28 | $120.00 | $165.00 | $675.00 | $300.00 | $275.00 |
| 29 | Integral abutment expansion joint seal (516E14014) | FT | 34 | $35.00 | $47.00 | $75.00 | $48.00 | $44.00 |
| 30 | Porous backfill with geotextile fabric (518E21200) | CY | 55 | $135.00 | $168.00 | $115.00 | $190.00 | $60.00 |
| 31 | 6" perforated corrugated plastic pipe (518E40000) | FT | 66 | $11.00 | $22.00 | $21.00 | $14.00 | $11.50 |
| 32 | 6" non-perforated corrugated plastic pipe, including specials (518E40010) | FT | 40 | $10.00 | $22.00 | $34.00 | $22.00 | $8.00 |
| 33 | Dynamic load testing (523E20000) | EACH | 1 | $3,400.00 | $5,124.00 | $5,000.00 | $6,000.00 | $5,200.00 |
| 34 | Rock channel protection, type C with geotextile fabric (601E32204) | CY | 52 | $205.00 | $234.00 | $140.00 | $220.00 | $255.00 |
| 35 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $10,600 | $9,340.00 | $10,000 | $9,500.00 | $20,000 |
| 36 | Maintaining traffic (614E11000) | LS | 1 | $2,800.00 | $4,000.00 | $4,000.00 | $10,000 | $6,000.00 |
| 37 | Field office, type B (619E16010) | MNTH | 12 | $100.00 | $500.00 | $1,200.00 | $1,000.00 | $500.00 |
| 38 | Construction layout stakes and surveying (623E10000) | LS | 1 | $2,800.00 | $18,200 | $15,000 | $12,000 | $6,000.00 |
| 39 | Mobilization (624E10000) | LS | 1 | $20,000 | $183,100 | $40,000 | $30,000 | $100,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of April 9, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way