ODOT letting results, October 13, 2022
29 contracts let by Ohio DOT on October 13, 2022, $72,313,663 in low bids, a median of 3 bidders per contract. On the 29 with an engineer's estimate, the low bid came in under it 20 times; median low bid -7.0% against the estimate.
- Owner
- Ohio DOT
- Contracts
- 29
- Low bids, total
- $72,313,663
- Data through
- 12 NOV 2026
Contracts let that day
| Contract | Project | County | Bids | Low bidder | Low bid | Second bid | Gap | Against estimate | Source |
|---|---|---|---|---|---|---|---|---|---|
| 220512 | CUY-IR 77-00.42 Interchange (PART 1 AND PART 2) (MAJOR RECONSTRUCTION) | CUY | 7 | Kokosing Construction Company Inc | $31,632,497 | $33,910,769 | +7.0% | -9.0% | ODOT |
| 220529 | POR-SR 43-18.65 (MINOR RECONSTRUCTION) | POR | 7 | Fechko Excavating LLC | $5,902,535 | $6,228,816 | +6.0% | +7.0% | ODOT |
| 220550 | PIC-US 23-17.37 (FOUR LANE RESURFACING) | PIC | 2 | Shelly Company | $4,636,206 | $5,981,852 | +29% | +2.0% | ODOT |
| 220543 | BEL-IR 70-00.00 (FOUR LANE RESURFACING) | BEL | 2 | Shelly & Sands Inc | $4,393,600 | $4,956,945 | +13% | -1.0% | ODOT |
| 220552 | PIK-SR 104/SR 220/SR 551-06.62/00.00/00.00 (TWO LANE RESURFACING) | PIK | 2 | Shelly & Sands Inc | $3,223,869 | $3,494,786 | +8.0% | -13% | ODOT |
| 220546 | D10-Chip Seal FY2023 North (CHIP SEAL) | District 10 | 2 | Shelly Company | $2,359,453 | $2,427,206 | +3.0% | 0.0% | ODOT |
| 220526 | MED-SR 252-03.95 (BRIDGE REPLACEMENT (1 BRIDGE)) | MED | 5 | Black Horse Bridge Construction Inc | $2,121,526 | $2,473,190 | +17% | -14% | ODOT |
| 220555 | STA-SR 183-06.47 (TWO LANE RESURFACING) | STA | 4 | Shelly Company | $2,012,472 | $2,293,134 | +14% | -2.0% | ODOT |
| 220554 | SCI-SR 348-12.80 PV (TWO LANE RESURFACING) | SCI | 1 | Shelly Company | $1,682,949 | -3.0% | ODOT | ||
| 220553 | ROS-SR 138-10.38 (BRIDGE REPLACEMENT (1 BRIDGE)) | ROS | 6 | D G M Inc | $1,615,255 | $1,698,925 | +5.0% | -12% | ODOT |
| 220541 | CUY-IR 480-20.33/VAR Noise Wall (NOISE WALLS) | CUY | 4 | Great Lakes Construction Co | $1,430,160 | $1,678,255 | +17% | -49% | ODOT |
| 220549 | JAC-US 35-08.35 (MICROSURFACING) | JAC | 2 | American Pavements Inc | $1,395,778 | $1,471,790 | +5.0% | +25% | ODOT |
| 220562 | D05-Guardrail FY2023 (GUARDRAIL REBUILDING) | District 5 | 4 | M P Dory Co | $1,293,909 | $1,384,821 | +7.0% | -19% | ODOT |
| 224028 | RIC-SR 39-14.98 (BRIDGE REPLACEMENT (1 BRIDGE)) | RIC | 2 | Rietschlin Construction Inc | $1,206,665 | $1,697,353 | +41% | +4.0% | ODOT |
| 220551 | PIC-SR 316-04.31 (PART 1 AND PART 2) (BRIDGE REPAIR) | PIC | 3 | BCC Ohio Inc | $976,358 | $1,113,155 | +14% | -10% | ODOT |
| 220560 | D03-GR FY2023 (GUARDRAIL REBUILDING) | District 3 | 2 | Lake Erie Construction Company | $874,225 | $911,074 | +4.0% | +4.0% | ODOT |
| 220547 | HAM-SRTS Lockland FY 23 (SIDEWALK) | HAM | 3 | Adleta Inc | $699,064 | $699,705 | 0.0% | +24% | ODOT |
| 220542 | ALL-/HAN/WYA-SR 103/SR 117/SR 53-VAR. (TWO LANE RESURFACING) | ALL | 3 | Helms and Sons Excavating | $674,704 | $717,736 | +6.0% | -9.0% | ODOT |
| 220559 | D02-LG FY2023 (LIGHTING) | District 2 | 2 | U S Utility Contractor Company | $634,242 | $738,545 | +16% | -12% | ODOT |
| 220556 | VIN-SR 160-16.05 (CULVERT REPLACEMENT) | VIN | 7 | Parker Corporation | $621,451 | $713,063 | +15% | -12% | ODOT |
| 220563 | D06-ELEC FY23 (LIGHTING) | District 6 | 3 | Perram Electric Inc | $481,300 | $517,255 | +7.0% | +2.0% | ODOT |
| 220565 | RIC-SYSSIGN FY2023 (SIGNING) | RIC | 2 | Lake Erie Construction Company | $467,650 | $478,187 | +2.0% | -18% | ODOT |
| 220548 | HOC-CR 418-00.06 (BRIDGE REPAIR) | HOC | 3 | Double Z Construction Company | $417,781 | $455,628 | +9.0% | -7.0% | ODOT |
| 220564 | MAR-US 23-01.52 (CULVERT REPLACEMENT) | MAR | 1 | Municipal and Contractors Sealing Products, Inc | $364,294 | -40% | ODOT | ||
| 224027 | LIC-US 62-18.90 (BRIDGE REPAIR) | LIC | 2 | BCC Ohio Inc | $335,528 | $387,700 | +16% | -7.0% | ODOT |
| 220557 | WAR-IR 71/SR 123-08.05/20.89 (CULVERT REPLACEMENT) | WAR | 5 | Eagle Bridge Co | $294,775 | $328,445 | +11% | 0.0% | ODOT |
| 220544 | CLE-SR 125-01.47 (INTERSECTION) | CLE | 5 | Bansal Construction Inc | $279,754 | $285,349 | +2.0% | -5.0% | ODOT |
| 220561 | D03-PR FY2023 (B) (PRUNING/OR TREE/BRUSH REMOVAL) | District 3 | 3 | Van Curen Services Inc | $164,324 | $199,275 | +21% | -10% | ODOT |
| 227002 | HOC-SR 678-02.10 (SLIDE REPAIR) | HOC | 3 | Allard Excavation LLC | $121,339 | $150,274 | +24% | -12% | ODOT |
Gap is the second bid over the low bid. Where a contract shows fewer bids than ODOT received, the others did not match their published totals and are left out.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.