ODOT letting results, September 29, 2022

26 contracts let by Ohio DOT on September 29, 2022, $49,058,942 in low bids, a median of 4 bidders per contract. On the 26 with an engineer's estimate, the low bid came in under it 15 times; median low bid -3.0% against the estimate.

Owner
Ohio DOT
Contracts
26
Low bids, total
$49,058,942
Data through
12 NOV 2026

Contracts let that day

ContractProjectCountyBidsLow bidderLow bidSecond bidGapAgainst estimateSource
220532TUS-IR 77-20.73, TUS-US 250-11.88 (FOUR LANE RESURFACING)TUS2Shelly & Sands Inc$8,933,634$10,499,915+18%+8.0%ODOT
220517HAM-IR 74/IR 275-03.54/03.97 (FOUR LANE RESURFACING)HAM2John R Jurgensen Company$7,995,513$8,845,989+11%+9.0%ODOT
220523JEF-SR 7-19.21 (FOUR LANE RESURFACING)JEF2Shelly & Sands Inc$4,659,500$6,029,804+29%-13%ODOT
220518HAM-SR 264-01.08 (FOUR LANE RESURFACING)HAM2John R Jurgensen Company$3,620,744$4,598,089+27%+22%ODOT
220531SEN-SR 224-19.85 Resurfacing (TWO LANE RESURFACING)SEN5Erie Blacktop Inc$3,264,099$3,581,821+10%-17%ODOT
220521HUR-SR 601-00.00 (TWO LANE RESURFACING)HUR3Erie Blacktop Inc$2,626,470$2,651,647+1.0%-12%ODOT
220515GEA-SR 306-04.45 (MINOR WIDENING)GEA2Chagrin Valley Paving Inc$2,276,024$2,351,941+3.0%+40%ODOT
220528PER-/HOC-SR 668-00.00/00.00 (TWO LANE RESURFACING)PER1Shelly Company$2,256,243+3.0%ODOT
220530PRE-US 127-04.50 (INTERSECTION)PRE5Barrett Paving Materials Inc$1,486,946$1,577,490+6.0%+11%ODOT
220540PER-SR 204-09.42 (BRIDGE REPAIR)PER5J & J Bridge Company Inc$1,327,839$1,480,559+12%+6.0%ODOT
220524MAH-SR 170-13.19 (FOUR LANE RESURFACING)MAH4Shelly & Sands Inc$1,226,201$1,272,575+4.0%-9.0%ODOT
220514D04-BH FY2023 (BRIDGE REPAIR)District 45B & G Trucking & Construction Inc$955,375$1,322,169+38%-17%ODOT
220534D02-GR FY2023 (GUARDRAIL REBUILDING)District 21Lake Erie Construction Company$952,875+2.0%ODOT
220522HUR-SR 547-07.25 (BRIDGE REPLACEMENT (1 BRIDGE))HUR5Great Lakes Demolition Company$928,902$1,134,433+22%-22%ODOT
220539MRG-Burr Oak SP Lodge Road (PARKING AREAS)MRG3Albatross Management LLC$860,634$899,019+4.0%+20%ODOT
220533CUY-US 422-18.74/VAR Slide (SLIDE REPAIR)CUY11Great Lakes Construction Co$845,874$878,407+4.0%-21%ODOT
220513D02-R-WR & WR FY23 (PAVEMENT MARKING)District 24Griffin Pavement Striping LLC$812,558$945,634+16%-9.0%ODOT
220520HOC-SR 180-05.36 (CULVERT REPLACEMENT)HOC8D G M Inc$798,761$868,889+9.0%-7.0%ODOT
220516HAM-CR 457-01.52 (INTERSECTION)HAM4Bansal Construction Inc$496,196$514,404+4.0%+25%ODOT
224025PIC-SR 56-28.27 (CULVERT REPLACEMENT)PIC4Axis Civil Construction LLC$477,950$529,722+11%-1.0%ODOT
220525MAR-SR 309-14.03 (MINOR RECONSTRUCTION)MAR5D L Smith Concrete LLC$474,561$476,7530.0%-1.0%ODOT
220527NOB-IR 77-04.75 (BRIDGE REPAIR)NOB4I V S Hydro Inc$459,716$485,194+6.0%-15%ODOT
220519HIG-SR 72-02.26 (CULVERT REPLACEMENT)HIG10Allard Excavation LLC$438,751$448,679+2.0%-18%ODOT
220537D09-PM FY2023 (A) (PAVEMENT MARKING)District 94Central Seal Company$399,255$407,150+2.0%-9.0%ODOT
220538D12-MNT FY2023 Tree Removal (PRUNING/OR TREE/BRUSH REMOVAL)District 122H & H Land Clearing, LLC$379,325$414,790+9.0%+30%ODOT
220536D03-PR FY2023 (PRUNING/OR TREE/BRUSH REMOVAL)District 34Ecotree Services LLC$104,995$122,390+17%-5.0%ODOT
ODOT contracts let on September 29, 2022, largest low bid first

Gap is the second bid over the low bid. Where a contract shows fewer bids than ODOT received, the others did not match their published totals and are left out.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy